159 Stanton Street
Manhattan, NY 10002BBL 1-00349-0016Map
Owner of record: 159-161 Stanton LLC
159 Stanton Street is a walk-up apartment building built in 1900 in Manhattan, 10002. It has 20 residential units across 5 floors. The owner of record is 159-161 Stanton LLC. HPD has recorded 259 housing violations here, most recently on July 20, 2026. 29 of the 50 most recent violations are still open. City tax records listed 19 rent-stabilized apartments here in 2024.
- HPD violations
- 259
- DOB violations
- 16
- ECB violations
- 41
- HPD complaints
- 431
What to know
Immediately hazardous issues among recent violations are still open.
Date of the most recent HPD inspection that found a problem.
No balance due on recent ECB violations.
Rent stabilization
Counts come from owners' rent-stabilization filings shown on NYC Department of Finance tax bills, as extracted by JustFix. They tell you a building has stabilized apartments, not which ones.
Think your apartment is stabilized? Request its rent history from HCR (free), then check your renewal with the renewal calculator.
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 259
- BHazardous
Properly repair or replace the broken or defective light fixture at ceiling at public hall, 1st story
Jul 20, 2026
Open — Nov sent out - BHazardous
Properly secure the loose hand railing at public hall, 2nd story
Jul 10, 2026
Open — Nov sent out - CImmediately hazardous
Replace or repair the self-closing doors that is missing or defective latch at 1st from east at north firedoor at boiler room
Jul 10, 2026
Open — Nov certified late - BHazardous
Properly repair the source and abate the evidence of a water leak at ceiling in the 2nd room from north located at apt 7, 3rd story
Jul 10, 2026 · Apt 7
Open — Nov sent out - ANon-hazardous
Trace and repair the source and abate the visible mold condition... less than 10 sqft at ceiling in the 1st bathroom from north located at apt 7, 3rd story
Jul 10, 2026 · Apt 7
Open — Notice of issuance sent to tenant - ANon-hazardous
Properly repair or replace the broken or defective sink base cabinet in the kitchen located at apt 7, 3rd story
Jul 10, 2026 · Apt 7
Open — Nov sent out - CImmediately hazardous
Properly repair and abate unsafe electric wiring condition consisting of the main power wires exposed at meter room
Jul 10, 2026
Open — Nov sent out - ANon-hazardous
Cleanse to the satisfaction of this department the floors at cellar
Jul 10, 2026
Open — Nov sent out - CImmediately hazardous
Abate the nuisance consisting of evidence of rats and all underlying causes creating the pest infestations, by using integrated pest management (ipm), eliminate all burrow entry and passageways, pest nests, holes, gaps or cracks in walls, ceilings, floors, fixing leaks and managing garbage in public areas. evidence found at .. at cellar
Jul 10, 2026
Open — Nov sent out - CImmediately hazardous
Properly repair with similar material the broken or defective fire retardant material at ceiling at boiler room
Jul 10, 2026
Open — Nov sent out
Show 40 more ↓
- CImmediately hazardous
Replace or repair the self-closing doors that is missing or defective latch at bulkhead door
Jul 10, 2026
Open — Nov certified late - BHazardous
Repair, replace or provide an approved and operational smoke detecting device, installed in accordance with department of buildings rules and regulations defective in the entire apartment located at apt 7, 3rd story
Jul 10, 2026 · Apt 7
Open — Nov sent out - BHazardous
Repair, replace or provide an approved and operational carbon monoxide detecting device, installed in accordance with applicable law and rules defective in the entire apartment located at apt 7, 3rd story
Jul 10, 2026 · Apt 7
Open — Nov sent out - ANon-hazardous
Properly repair or replace the broken or defective upper escutcheon plate at riser in the 2nd room from north located at apt 7, 3rd story
Jul 10, 2026 · Apt 7
Open — Nov sent out - BHazardous
Repair the broken or defective plastered surfaces and paint in a uniform color the ceiling in the 2nd room from north located at apt 7, 3rd story
Jul 10, 2026 · Apt 7
Open — Nov sent out - BHazardous
Properly repair with similar material the broken or defective ceramic floor tiles at public hall, 2nd story
Jun 24, 2026
Open — Nov sent out - BHazardous
Repair the broken or defective plastered surfaces and paint in a uniform color at north wall in the 1st room from north located at apt 2, 2nd story, 1st apartment from east at south
Mar 14, 2026 · Apt 2
Closed — Violation closed - CImmediately hazardous
Abate the infestation consisting of mice in the entire apartment located at apt 2, 2nd story, 1st apartment from east at south
Mar 14, 2026 · Apt 2
Open — False certification - CImmediately hazardous
Abate the infestation consisting of roaches in the entire apartment located at apt 2, 2nd story, 1st apartment from east at south
Mar 14, 2026 · Apt 2
Open — False certification - BHazardous
Repair the broken or defective plastered surfaces and paint in a uniform color at south wall in the 1st room from north located at apt 2, 2nd story, 1st apartment from west at north
Sep 26, 2025 · Apt 2
Open — Nov sent out - CImmediately hazardous
Abate the infestation consisting of roaches in the entire apartment located at apt 2, 2nd story, 1st apartment from west at north
Sep 26, 2025 · Apt 2
Open — Notice of issuance sent to tenant - ANon-hazardous
Properly repair with similar material the broken or defective caulking around bathtub in the bathroom located at apt 2, 2nd story, 1st apartment from west at north
Sep 26, 2025 · Apt 2
Closed — Violation dismissed - CImmediately hazardous
Abate the infestation consisting of roaches at public hall, 1st story
Sep 26, 2025
Open — Nov sent out - ANon-hazardous
Provide and maintain approved mail receptacles and directories for the persons residing in the dwelling as provided in the u.s. postal regulations. at public hall, 1st story
Sep 4, 2025
Open — Nov sent out - ANon-hazardous
Trace and repair the source and abate the visible mold condition... less than 10 sq.ft at ceiling in the bathroom located at apt 7, 4th story, 1st apartment from east at south
Jun 5, 2025 · Apt 7
Closed — Violation closed - BHazardous
Repair or replace the carbon monoxide detecting device(s). defective in the entire apartment located at apt 7, 4th story, 1st apartment from east at south
Jun 5, 2025 · Apt 7
Open — Nov sent out - BHazardous
Repair or replace the smoke detector defective in the entire apartment located at apt 7, 4th story, 1st apartment from east at south
Jun 5, 2025 · Apt 7
Open — Nov sent out - BHazardous
Trace and repair the source and abate the visible mold condition... less than 10 sq.ft at ceiling in the bathroom located at apt 7, 4th story, 1st apartment from east at south original violation 17973481 issued 05-jun-25 has been upgraded to class b per administrative code 27-2017.3a(3)(a) or (b).
Jun 5, 2025 · Apt 7
Open — First no access to re- inspect violation - CImmediately hazardous
Replace or repair the self-closing doors that is missing or defective vestibule door at public hall, 1st story
Jul 15, 2024
Closed — Violation closed - CImmediately hazardous
Abate the infestation consisting of roaches in the entire apartment located at apt 7, 4th story, 1st apartment from east at south
Nov 2, 2023 · Apt 7
Closed — Violation dismissed - BHazardous
Properly repair or replace the broken or defective upper escutcheon plate ceiling at heat riser in the kitchen located at apt 7, 4th story, 1st apartment from east at south
Nov 2, 2023 · Apt 7
Open — Not complied with - BHazardous
Properly repair the source and abate the evidence of a water leak at ceiling in the kitchen located at apt 7, 4th story, 1st apartment from east at south
Nov 2, 2023 · Apt 7
Closed — Violation closed - ANon-hazardous
Properly secure the loose upper cabinets at east wall in the kitchen located at apt 7, 4th story, 1st apartment from east at south
Nov 2, 2023 · Apt 7
Closed — Violation dismissed - BHazardous
Repair the broken or defective plastered surfaces and paint in a uniform color at ceiling in the kitchen located at apt 7, 4th story, 1st apartment from east at south
Nov 2, 2023 · Apt 7
Closed — Violation closed - ANon-hazardous
Post sign on wall of entrance story bearing name, address including apartment number if any, and telephone number of superintendent, janitor or housekeeper. at public hall, 1st story
Mar 30, 2023
Closed — Violation dismissed - BHazardous
Provide dwelling with a janitor or responsible person or janitorial service.
Mar 30, 2023
Closed — Violation dismissed - ANon-hazardous
Properly repair the broken or defective bell, return buzzer and intercome system from front building entrance door to the panel in the in the entire apartment located at apt 11b, 5th story, 1st apartment from west at north
Mar 30, 2023 · Apt 11B
Closed — Violation dismissed - BHazardous
Fire escape defective. adjust the dropladder so that it will slide easily in the guide rods .. at fire escape
Mar 30, 2023
Closed — Violation dismissed - BHazardous
Repair the broken or defective plastered surfaces and paint in a uniform color all walls and ceiling in the kitchen located at apt 8b, 4th story, 1st apartment from south at west
Mar 7, 2023 · Apt 8B
Closed — Violation dismissed - BHazardous
Repair the broken or defective plastered surfaces and paint in a uniform color all walls and ceiling in the 3rd room from north located at apt 8b, 4th story, 1st apartment from south at west
Mar 7, 2023 · Apt 8B
Closed — Violation dismissed - BHazardous
Repair the broken or defective plastered surfaces and paint in a uniform color all walls and ceiling in the foyer located at apt 8b, 4th story, 1st apartment from south at west
Mar 7, 2023 · Apt 8B
Closed — Violation dismissed - BHazardous
Properly repair the broken or defective mechanical ventilation system at ceiling in the kitchen located at apt 8b, 4th story, 1st apartment from south at west
Mar 7, 2023 · Apt 8B
Closed — Violation dismissed - BHazardous
Properly repair with similar material the broken or defective porcelain enamel glaze inside of bathtub in the bathroom located at apt 8b, 4th story, 1st apartment from south at west
Mar 7, 2023 · Apt 8B
Closed — Violation dismissed - BHazardous
Properly repair the broken or defective mechanical ventilation system at ceiling in the bathroom located at apt 8b, 4th story, 1st apartment from south at west
Mar 7, 2023 · Apt 8B
Closed — Violation dismissed - BHazardous
Properly repair the broken or defective bell and return buzzer from building entrance leading to the panel in the foyer located at apt 8b, 4th story, 1st apartment from south at west
Mar 7, 2023 · Apt 8B
Closed — Violation dismissed - CImmediately hazardous
Repair the broken or defective plastered surfaces and paint in a uniform color the ceiling in the bathroom located at apt 8b, 4th story, 1st apartment from south at west
Mar 7, 2023 · Apt 8B
Closed — Violation dismissed - CImmediately hazardous
Replace or repair the self-closing doors that is missing or defective missing vestibule door at public hall, 1st story
Feb 21, 2023
Open — Violation will be reinspected - BHazardous
Replace with new the broken or defective marble saddle at entrance door in the bathroom located at apt 10, 5th story, 1st apartment from east at south
Apr 7, 2022 · Apt 10
Closed — Violation closed - CImmediately hazardous
Abate the infestation consisting of roaches in the entire apartment located at apt 2, 2nd story, 1st apartment from west at north
Dec 18, 2021 · Apt 2
Open — Violation will be reinspected - BHazardous
Repair or replace the smoke detector missing in the entire apartment located at apt 2, 2nd story, 1st apartment from west at north
Dec 18, 2021 · Apt 2
Open — Violation will be reinspected
DOB building violations · 16
- Construction other optional
Observed structural work in progress between floors w/ temporary make-shift shoring on occupied building to secure/ support floors. failure to provide pe approved plans for structural stability & shoring of floors can create a hazardous condition for a possible dislodgment & detrimental for residents.
Sep 26, 2024
Dob violation - active - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Sep 2, 2020
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
May 17, 2017
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
May 17, 2017
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
May 17, 2017
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
May 17, 2017
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
May 17, 2017
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
May 3, 2017
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2015 inspection report
Feb 24, 2017
Dob violation - dismissed - Plumbing none
Boro commisioner issued a notice of immediate stop work order due to applicant withdrawl of application #140380521 as of 01/10/17
Jan 10, 2017
Dob violation - dismissed
Show 6 more ↓
- Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jan 27, 2016
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2012 inspection report
May 15, 2014
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2010 inspection report
Dec 13, 2011
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Sep 1, 1994
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Mar 18, 1994
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Mar 18, 1993
Dob violation - dismissed
ECB violations · 41
- Class - 1
Failure to maintain building in code-compliant manner. observed ceiling fireproofing, falling/deteriorating in various locations throughout boiler room at cellar level, exposing wood joist for floor above., rep
Jul 10, 2026 · Penalty $2,530
Active - Class - 1
Unapproved/unsafe/unsuitable electrical equipment, apparatus, materials, devices, appliances or wiring in use. observed exposed high-voltage conductors feeding electrical panel. provide approved protection or e
Jul 10, 2026 · Penalty $1,630
Active - Class - 2
Hb smith steam boiler has noise+vibration from the oil burner;correct violation+submit certificate of correction
Feb 11, 2026 · Penalty $6,250
Active - Class - 1
No certificate of correction on file as per commissioner's request for class 1 work-without-permit violation #39125901j issued 9/26/2024 for electrical work performed throughout the premises. no permits have be
Feb 10, 2026 · Penalty $12,500
Active - Class - 1
No certificate of correction on file as per commissioner's request for class 1 work-without-permit violation #39125916m issued 9/26/2024 for temporary make-shift shoring, exposed plumbing pipes permits have bee
Feb 10, 2026 · Penalty $6,250
Resolve - Class - 1
No certificate of correction on file as per commissioner's request for class 1 work-without-permit violation #39125921r issued 9/26/2024 for temporary makeshift shoring and exposed plumbing pipes. although perm
Feb 10, 2026 · Penalty $6,250
Resolve - Class - 2
No access. no certificate of correction filed for class 1 violation #39125928j issued 9/26/24 citing work between floors 2 & 3, with temporary make shift shoring and supports observed. violation remains open du
Feb 10, 2026 · Penalty $3,125
Resolve - Class - 2
No access. no certificate of correction filed for class 1 violation #39126023j issued 9/26/24 citing work between floors w/ temporary make-shift shoring and certificate of occupancy not reflecting occuppied apa
Feb 10, 2026 · Penalty $3,125
Resolve - Class - 2
No access. no certificate of correction filed for class 1 violation #39126026p issued 9/26/24 asking to provide pe assessment report, structural stability, shoring plans & means & methods for removing beams .,
Feb 10, 2026 · Penalty $6,250
Active - Class - 2
No access. no certificate of correction filed for class 1 violation #39126037k issued 9/26/24 citing unsuitable, electrical conditions creating a potential electrical hazard w/ panels w/out covers and no gfci p
Feb 10, 2026 · Penalty $6,250
Active
Show 31 more ↓
- Class - 2
No access. no certificate of correction on file for class 1 failure to maintain violation #39126039y issued 9/26/2024 citing dislodged bricks and deterioration/step cracks at chimney at exposure 3., file a cert
Feb 10, 2026 · Penalty $6,250
Active - Class - 1
Certificate of correction has not been submitted for class 1 violation #39127765n issued 10/18/2024 for failure to submit the engineer's report requested under dob violation #24-02617 dated 9/26/2024.. the viol
Feb 10, 2026 · Penalty $12,500
Resolve - Class - 1
Unlawful acts: failure to comply with the commissioners order contained in summons/violation# 039126037k, issued on 09/26/2024 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01. fail
Jan 21, 2025 · Penalty $2,500
Resolve - Class - 1
Unlawful acts: failure to comply with the commissioners order contained in summons/violation# 039126026p, issued on 09/26/2024 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01. fail
Jan 21, 2025 · Penalty $2,500
Resolve - Class - 1
Unlawful acts: failure to comply with the commissioners order contained in summons/violation# 039125901j, issued on 09/26/2024 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01. fail
Jan 21, 2025 · Penalty $2,500
Resolve - Class - 1
Unlawful acts: failure to comply with the commissioners order contained in summons/violation# 039126039y, issued on 09/26/2024 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01. fail
Jan 21, 2025 · Penalty $2,500
Resolve - Class - 1
Unlawful acts: failure to comply with the commissioners order contained in summons/violation# 039126023j, issued on 09/26/2024 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01. fail
Jan 21, 2025 · Penalty $2,500
Resolve - Class - 1
Unlawful acts: failure to comply with the commissioners order contained in summons/violation# 039125928j, issued on 09/26/2024 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01. fail
Jan 21, 2025 · Penalty $2,500
Resolve - Class - 1
Unlawful acts: failure to comply with the commissioners order contained in summons/violation# 039125921r, issued on 09/26/2024 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01. fail
Jan 21, 2025 · Penalty $2,500
Resolve - Class - 1
Unlawful acts: failure to comply with the commissioners order contained in summons/violation# 039125916m, issued on 09/26/2024 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01. fail
Jan 21, 2025 · Penalty $2,500
Resolve - Class - 1
Failure to comply with the commissioners order contained in dob violation#vio24-02617 issued on 9/26/24 to hire nyspe and submit report to [email protected] within 7 days., comply with commissioner's
Oct 18, 2024
Resolve - Class - 1
Observed structural work in progress between floors w/ temporary make-shift shoring, exposed plumbing pipes & lines @ multiple locations. upon reviewing. and doing a search on bis/dob now reveal to me that no p
Sep 26, 2024
Resolve - Class - 1
Structural work in progress under application #m00218553-i1-st, w/out nb our alt1 issued. stop all structural work., obtain permit
Sep 26, 2024
Resolve - Class - 1
Observed structural work in progress between floors w/ temporary make-shift shoring on occupied building to secure/ support floors. no special inspections tr1 filled. stop all work at floors 2 & 3.; 1704.1, com
Sep 26, 2024
Resolve - Class - 1
Observed structural work in progress between floors w/ temporary make-shift shoring on occupied building to secure/ support floors. upon reviewing the department records for certificate of occupancy noticed tha
Sep 26, 2024
Resolve - Class - 1
Observed fire escape at exposure #3 on a # 5 stories occupied residential at window location at 3rd floor locationdislodged facade bricks, missing pointing, damaged by water. chimney step cracking an inside sta
Sep 26, 2024 · Penalty $1,250
Active - Class - 1
Atoi on an active jobsite, observed electrical work being done throughout the entire premises. upon reviewing. and doing a search on bis/dob now reveal to me that no permit was issued for electrical work for th
Sep 26, 2024 · Penalty $8,000
Active - Class - 1
Observed structural work in progress between floors w/ temporary make-shift shoring on occupied building to secure/ support floors. failure to provide pe approved plans for structural stability & shoring of flo
Sep 26, 2024 · Penalty $10,000
Active - Class - 1
Unapproved/unsafe/unsuitable electrical equipment, apparatus, materials, devices, appliances or wiring in use. note:at time of inspection observed unsuitable, electrical conditions creating a potential electric
Sep 26, 2024 · Penalty $8,000
Active - Class - 1
Cease use blr; correct haz immediately+call dob 212 3932784/lift ceaseuse order-fumes+smoke-poor bnr flame-flue defct/improper support-flue plates defct bolts+gaskets-waste pipe broke@blr-steam leak@top blr-equ
Jan 28, 2020 · Penalty $1,250
Resolve - Class - 2
Failure to comply with the commissioners order contained in summons/violation#35219579m issued on 02/25/17 and to file a certificate of correction pursuant to 28-201.1 ad 1rcny 102-01.apt 1 on 2nd flr kitchen c
May 31, 2017
Resolve - Class - 2
Failure to comply with the commissioner's order contained in summons/volations 35219579m issued on 2/25/17 and to filea certificate of corr ection pursuant to 28-201.1 and 1rcny 102.01.failure to file a c of o
Apr 15, 2017
Resolve - Class - 1
Failure to safeguard all persons & property affected by consturction operations. noted: at time of inspection,observed ceilings in kitchen of pat#1 2nd fl has been compromised due to construction in apt on 3rd
Feb 25, 2017
Resolve - Class - 1
Bc28-104.4.1/bc1603.1;inadequate plans;noted:contractor is working on alt2 renovation of applicant #'s 1,4,5a,5b,6 and 11a.it was observed on the 3rd flr in apartments 4,5a,5b,&6 that the flr joist and ceiling
Feb 17, 2017 · Penalty $1,600
Resolve - Class - 1
Bc3303.10/failure to comply with tenant protection plan.noted:contractor was awarded contractor was awarded contract to work on alt2.application#140380521.this job intails interior ruination of apartment#'s 1,4
Feb 17, 2017 · Penalty $1,600
Resolve - Class - 1
Failure to maintain building in a code compliant manner:no fire stopping per bc712.3.noted:contractor is responsible for alt 2 application#140380521.this job intails interior renovation of apartments #1,4,5a,5b
Feb 17, 2017 · Penalty $1,000
Resolve - Class - 2
Failure to maintain adequate housekeeping.per section requirements.noted:contractor is working on alt2 application#140380521.which intails interior renovation of several appartment in the bldg.as a result exces
Feb 17, 2017
Resolve - Class - 1
Unapproved/unsafe/unsuitable/electrical equipment,apparatus,materials,devices,appliances or wiring in use.noted;there are numerous open exposed energized wiring and electrical equipment observes throughout the
Feb 17, 2017 · Penalty $1,600
Active - Class - 1
Right of entry: alt tpe 2 job#s: 122495013,122495004,140380521.interior renovation's with partition work and combining apartments, with plumbing and electrical work. noted: access to apartments under renovation
Jan 23, 2017 · Penalty $800
Resolve - Class - 1
Electrical work w/o a permit. removed & installed new-the entire theseapts #1,5b,5a,#6,#4,11: branch circuit wiring,receptacles outlets,lighting fixtures. not on file. m373604,m025236 does not covered the above
Oct 28, 2015 · Penalty $8,000
Resolve - Class - 2
Failure to maintain bldg.noted @ 5th fl metal stairs,2 to 3ft section of stair stringer along left side near top landing is separating from wall w/ 1/2in space evident.observed also damaged plaster @ stairs loc
Jun 11, 2015 · Penalty $250
Resolve
Complaints
- Unsanitary condition
Garbage/recycling storage
Jul 24, 2026 · Apt BLDG
Close - Unsanitary condition
Garbage/recycling storage
Jul 18, 2026 · Apt BLDG
Close - Electric
Power outage
Jul 18, 2026 · Apt BLDG
Close - Electric
Power outage
Jul 17, 2026 · Apt 1STFLO
Close - Unsanitary condition
Garbage/recycling storage
Jul 14, 2026 · Apt BLDG
Close - Unsanitary condition
Garbage/recycling storage
Jul 9, 2026 · Apt BLDG
Close - Unsanitary condition
Garbage/recycling storage
Jun 27, 2026 · Apt BLDG
Close - General
Mailbox
Jun 26, 2026 · Apt 3
Close - Unsanitary condition
Garbage/recycling storage
Jun 18, 2026 · Apt BLDG
Close - Unsanitary condition
Sewage
Jun 13, 2026 · Apt 2
Close
Show 40 more ↓
- Unsanitary condition
Garbage/recycling storage
May 19, 2026 · Apt BLDG
Close - Heat/hot water
Entire building
May 6, 2026 · Apt BLDG
Close - Heat/hot water
Entire building
May 6, 2026 · Apt BLDG
Close - Heat/hot water
Entire building
May 6, 2026 · Apt BLDG
Close - Heat/hot water
Entire building
Apr 27, 2026 · Apt BLDG
Close - Unsanitary condition
Garbage/recycling storage
Mar 21, 2026 · Apt BLDG
Close - Unsanitary condition
Garbage/recycling storage
Mar 17, 2026 · Apt LOBBY
Close - Heat/hot water
Entire building
Mar 17, 2026 · Apt BLDG
Close - Heat/hot water
Entire building
Feb 13, 2026 · Apt BLDG
Close - Heat/hot water
Entire building
Feb 13, 2026 · Apt BLDG
Close - Heat/hot water
Entire building
Feb 4, 2026 · Apt BLDG
Close - Heat/hot water
Entire building
Feb 3, 2026 · Apt 11B
Close - Paint/plaster
Wall
Feb 3, 2026 · Apt 2
Close - Unsanitary condition
Mold
Feb 3, 2026 · Apt 2
Close - Unsanitary condition
Pests
Feb 3, 2026 · Apt 2
Close - Heat/hot water
Entire building
Feb 3, 2026 · Apt BLDG
Close - Heat/hot water
Entire building
Feb 3, 2026 · Apt BLDG
Close - Heat/hot water
Entire building
Feb 3, 2026 · Apt BLDG
Close - Flooring/stairs
Floor
Feb 3, 2026 · Apt 2
Close - Paint/plaster
Wall
Feb 3, 2026 · Apt 2
Close - Unsanitary condition
Garbage/recycling storage
Jan 17, 2026 · Apt BLDG
Close - Unsanitary condition
Mold
Jan 16, 2026 · Apt 2
Close - Heat/hot water
Entire building
Dec 30, 2025 · Apt BLDG
Close - Heat/hot water
Entire building
Dec 30, 2025 · Apt BLDG
Close - Heat/hot water
Entire building
Nov 4, 2025 · Apt BLDG
Close - Unsanitary condition
Garbage/recycling storage
Nov 2, 2025 · Apt BLDG
Close - Heat/hot water
Entire building
Nov 1, 2025 · Apt BLDG
Close - Heat/hot water
Entire building
Oct 31, 2025 · Apt BLDG
Close - Heat/hot water
Entire building
Oct 15, 2025 · Apt 3
Close - Unsanitary condition
Mold
Sep 30, 2025 · Apt 2
Close - Flooring/stairs
Floor
Sep 30, 2025 · Apt 2
Close - Paint/plaster
Wall
Sep 22, 2025 · Apt 2
Close - Flooring/stairs
Floor
Sep 22, 2025 · Apt 2
Close - Unsanitary condition
Pests
Sep 22, 2025 · Apt 2
Close - Unsanitary condition
Mold
Sep 22, 2025 · Apt 2
Close - Unsanitary condition
Garbage/recycling storage
Sep 14, 2025 · Apt BLDG
Close - Flooring/stairs
Floor
Sep 4, 2025 · Apt 2
Close - Unsanitary condition
Pests
Sep 4, 2025 · Apt 2
Close - Unsanitary condition
Pests
Sep 4, 2025 · Apt 2
Close - Unsanitary condition
Pests
Sep 4, 2025 · Apt 2
Close
Sales history
No recorded sales in our data
Building details
- Building type
- Walk-up apartment building (C4)
- Year built
- 1900
- Floors
- 5
- Residential units
- 20
- Building area
- 8,201 ft²
- Lot area
- 2,504 ft²
- Zoning
- R7A
- Community board
- 103
- Council district
- 1
- Block / lot
- 349 / 16
- Assessed value
- $864,900
- Landmark / historic district
- No
HPD registration #124273, last renewed Nov 5, 2025.
Questions about 159 Stanton Street
Who owns 159 Stanton Street?
The owner of record in NYC Department of City Planning PLUTO data is 159-161 Stanton LLC.
Does 159 Stanton Street have violations?
Yes. NYC HPD has recorded 259 housing violations at this property.
Is 159 Stanton Street rent stabilized?
NYC Department of Finance tax bills listed 19 rent-stabilized units here in 2024 (about 95% of its 20 apartments). To confirm a specific apartment, request its rent history from NYS Homes and Community Renewal.
When was 159 Stanton Street built?
City records list 1900 as the year it was built.
How many apartments are in 159 Stanton Street?
It has 20 residential units.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.