roofy

185 Broadway

Manhattan, NY 10007BBL 1-00063-7501Map

Owner of record: 183 Broadway Owner LLC

185 Broadway is a condominium built in 2019 in Manhattan, 10007. It has 209 residential units across 33 floors. The owner of record is 183 Broadway Owner LLC. HPD has recorded 12 housing violations here, most recently on December 26, 2023. City tax records listed 64 rent-stabilized apartments here in 2024.

HPD violations
12
DOB violations
1
ECB violations
11
HPD complaints
7

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
Last violation Dec 26, 2023

Date of the most recent HPD inspection that found a problem.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

Rent-stabilized units in 2024
64
About 31% of the building's 209 apartments
Down from 105 in 2022

Counts come from owners' rent-stabilization filings shown on NYC Department of Finance tax bills, as extracted by JustFix. They tell you a building has stabilized apartments, not which ones.

Stabilized units by tax-bill year

Think your apartment is stabilized? Request its rent history from HCR (free), then check your renewal with the renewal calculator.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 12

  • C

    Replace or repair the self-closing doors that is missing or defective latch in the entrance located at apt 18h, 18th story, 1st apartment from south at west

    Dec 26, 2023 · Apt 18H

    Closed — Violation closed
  • C

    Replace or repair the self-closing doors that is missing or defective latch at fire door leading to stairway b at public hall, 22nd story

    Dec 26, 2023

    Closed — Violation closed
  • C

    Replace or repair the self-closing doors that is missing or defective latch at fire door leading to stairway b at public hall, 27th story

    Dec 26, 2023

    Closed — Violation closed
  • C

    Replace or repair the self-closing doors that is missing or defective latch at fire door leading to stairway b at public hall, 29th story

    Dec 26, 2023

    Closed — Violation closed
  • C

    Replace or repair the self-closing doors that is missing or defective hinges at trash chute door at compactor closet, 10th story

    Dec 26, 2023

    Closed — Violation closed
  • C

    Replace or repair the self-closing doors that is missing or defective hinges at trash chute door at compactor closet, 12th story

    Dec 26, 2023

    Closed — Violation closed
  • C

    Replace or repair the self-closing doors that is missing or defective hinges at trash chute door at compactor closet, 16th story

    Dec 26, 2023

    Closed — Violation closed
  • C

    Replace or repair the self-closing doors that is missing or defective hinges at trash chute door at compactor closet, 21st story

    Dec 26, 2023

    Closed — Violation closed
  • C

    Replace or repair the self-closing doors that is missing or defective hinges at (glass) door to the west terrace at public hall, 32nd story

    Dec 26, 2023

    Closed — Violation closed
  • C

    Replace or repair the self-closing doors that is missing or defective latch at laundry room

    Dec 26, 2023

    Closed — Violation closed
Show 2 more ↓
  • C

    Replace or repair the self-closing doors that is missing or defective latch at the trash room

    Dec 26, 2023

    Closed — Violation closed
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Mar 10, 2022

    Closed — Violation dismissed

DOB building violations · 1

  • Landmark none

    Landmk-landmark none

    Aug 1, 2023

    Dob violation - dismissed

ECB violations · 11

  • Class - 2

    Bc 3303.16 contractor shed and office note:at time of inspection of a 34 story new bldg.i observed there are three sheds in one site two areat 3rd floor and one is at 4th floor.and two of them are not made by m

    Jan 25, 2022

    Resolve
  • Class - 2

    Condition of sidewalk shed contrary to drawing.note:at time of inspection i observed the sidewalk shed cross beam at expo#2 contrary to approved drawing.it is not constructed per the approved plan.few cross bea

    Jan 25, 2022

    Resolve
  • Class - 2

    Failure to post or distribute notice of tpp meeting requirements.at time of inspection of 34 story nb active job site observed that building is partially occupied from 9th floor to 18th floor while construction

    Oct 13, 2021 · Penalty $312

    Resolve
  • Class - 2

    Bc3314.4 supported pipe scaffold not installed/maintained as per code.at time of inspection of 34 story nb active job site observed at roof level supported pipe scaffold not installed as per code.supported scaf

    Oct 13, 2021 · Penalty $625

    Resolve
  • Class - 2

    Failure to institute & maintain safety measures. note: at time of inspection in response to incident where worker fell off bakers scaffold(approx 4-5 feet)ambulance was called. inspection reveals that the scaff

    Jul 22, 2021

    Resolve
  • Class - 2

    Failure to institute & maintain safety measures. note: at the time of my inspection of a proposed 34 sty nb active job site,in response to an incident reported where 1 worker tripped on construction material &

    Sep 28, 2020 · Penalty $5,000

    Resolve
  • Class - 1

    Provision of law:bc3314.14.deficient design-the respondent registerd design professional failed to met the minimum requirements set forth inbc3314.14.bc3314.14 mandates that outrigger scaffolds(thrust-out)shall

    May 28, 2020 · Penalty $2,530

    Resolve
  • Class - 2

    Provision of law:bc3314.3.3 and bc1603.1.deficient drwaings-the respondent registered design professional failed to meet the minimum requirements set forth in bc3314.3.3 and bc1603.1.bc3314.3.3 mandates that sc

    May 28, 2020 · Penalty $1,280

    Resolve
  • Class - 2

    Sidewalk shed parapet pamel.at time of inspection on an 34 stories wb,i observed active site with a ssm dm site.also observed exp3 4 5 ws parapet w/o a information panel.heavy duty sws parapet w/o information p

    Mar 17, 2020 · Penalty $1,250

    Resolve
  • Class - 1

    Oac sign on display without a permit (time warner) rem: remove illegalsign.

    Oct 15, 2008 · Penalty $10,000

    Resolve
Show 1 more ↓
  • Class - 1

    Oac sign prohibited in c5-5 district. (time warner) rem: remove illegal sign.

    Oct 15, 2008 · Penalty $10,000

    Resolve

Complaints

  • Heat/hot water

    Entire building

    Apr 26, 2026 · Apt BLDG

    Close
  • Appliance

    Refrigerator

    Oct 23, 2023 · Apt 25B

    Close
  • Door/window

    Window frame

    Jan 11, 2023 · Apt 7J

    Close
  • Water leak

    Heavy flow

    Apr 2, 2022 · Apt 11G

    Close
  • Electric

    Lighting

    Apr 2, 2022 · Apt 11G

    Close
  • Heat/hot water

    Entire building

    Feb 20, 2015 · Apt BLDG

    Close
  • Heat/hot water

    Entire building

    Feb 20, 2015 · Apt BLDG

    Close

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Condominium (RM)
Year built
2019
Floors
33
Residential units
209
Building area
220,695 ft²
Lot area
2,510 ft²
Zoning
C5-5
Community board
101
Council district
1
Block / lot
63 / 7501
Assessed value
$49,315,185
Landmark / historic district
No

HPD registration #144974, last renewed Aug 28, 2025.

Questions about 185 Broadway

Who owns 185 Broadway?

The owner of record in NYC Department of City Planning PLUTO data is 183 Broadway Owner LLC.

Does 185 Broadway have violations?

Yes. NYC HPD has recorded 12 housing violations at this property.

Is 185 Broadway rent stabilized?

NYC Department of Finance tax bills listed 64 rent-stabilized units here in 2024 (about 31% of its 209 apartments). To confirm a specific apartment, request its rent history from NYS Homes and Community Renewal.

When was 185 Broadway built?

City records list 2019 as the year it was built.

How many apartments are in 185 Broadway?

It has 209 residential units and 211 units in total.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.