42 Trinity Place
Manhattan, NY 10006BBL 1-00019-7501Map
Owner of record: Tphgreenwich Owner LLC
42 Trinity Place is a condominium built in 2018 in Manhattan, 10006. It has 90 residential units across 40 floors. The owner of record is Tphgreenwich Owner LLC. HPD has recorded 4 housing violations here, most recently on October 25, 2019.
- HPD violations
- 4
- DOB violations
- 14
- ECB violations
- 53
- HPD complaints
- 3
What to know
No open immediately-hazardous violations among recent records.
Date of the most recent HPD inspection that found a problem.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 4
- IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Oct 25, 2019
Closed — Violation dismissed - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Oct 9, 2018
Closed — Violation dismissed - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Oct 25, 2016
Closed — Violation dismissed - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Oct 1, 2015
Closed — Violation dismissed
DOB building violations · 14
- Low pressure boiler boiler required
Violation issued-failure to file 2024 external low pressure inspection
Nov 14, 2025
Dob violation - dismissed - Landmark none
Landmk-landmark none
Oct 17, 2024
Dob violation - dismissed - Landmark none
Landmk-landmark none
Oct 16, 2024
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2023 external low pressure inspection
Sep 23, 2024
Dob violation - dismissed - Construction other optional
Emergency work order due to the hazard posed from falling exterior facade tiles on9/20/23.owner to immediately maintain exterior building facade.immediately remove all loose exterior facade tiles from all exposures of bulging take and provide adequate safety measures to protect and secure public safety
Sep 22, 2023
Dob violation - dismissed - Construction other optional
Failure to maintain facade&appurt.on 9/20/23 exterior facade tiles for reason to be determ.failed&fell to st.level.remedy:owner immed.retain nys rdp to determ.safety of same&perform 100% hands on inspect.of all exterior facade tiles.rdp shallcreate rpt of all inspect&cause of fail file&permit allwork.rpt/drawingsto [email protected] by10/6/23
Sep 22, 2023
Dob violation - dismissed - Construction other optional
C-construction other optional
Feb 19, 2022
Dob violation - dismissed - Failure to benchmark none
Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4
Feb 2, 2022
Dob violation - dismissed - Failure to post energy grade/score none
Failure to display energy efficiency score and energy efficiency grade as per adcode sec. 28-309.12.3
Dec 1, 2021
Dob violation - dismissed - Failure to benchmark none
Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4
Nov 2, 2021
Dob violation - dismissed
Show 4 more ↓
- Construction other optional
C-construction other optional
Sep 18, 2021
Dob violation - dismissed - Failure to benchmark none
Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4
Aug 2, 2021
Dob violation - dismissed - Failure to benchmark none
Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4
Jun 2, 2021
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Sep 2, 2020
Dob violation - dismissed
ECB violations · 53
- Class - 1
Note while responding to an incident where a glacier worker accidentally, cut his left hand using a grinder to cut metal panels my inspection reveal the worker was using the grinder without the handle attachmen
Jun 9, 2025 · Penalty $2,500
Resolve - Class - 2
No watchperson. atoi of a 40-story new building approx. 10,691 sq ft. site was closed with no construction activity. i shouted around the perimeter and banged on the fence/door to alert the watchperson and veri
May 31, 2025
Resolve - Class - 2
40 story new building active site. observed unfinished exterior work on facade at exp#2,3 missing stone cladding. upon inspection of site safety plans ssp-008.09. observed umbrella sidewalk shed not fully exten
Jan 15, 2025
Resolve - Class - 2
40 story new building active site. observed unfinished exterior work on facade at exp#2 missing stone cladding.observed occupied school adjoining property roof not fully protected exp#2.missing protection on pa
Jan 15, 2025
Resolve - Class - 1
The registered design professional hired by the owner failed to immediately notify the department of unsafe conditions as mandated by ac28-302.3. through a review of dob compliance filing record tr6-919245-9a-i
Dec 6, 2024 · Penalty $12,500
Active - Class - 1
Unlawful acts. failure to comply with commissioner's order. note: dob 092223llf02jf requires the owner to immediately retain a licensed professional to perform 100% hands on inspection of all exterior facade ti
May 21, 2024 · Penalty $12,500
Active - Class - 1
In response to an incident where a piece of facade stone approx. 30"by18" came down from the building on 39th floor approx 400 feet height during stone replacement operation landed on the street inspection reve
Sep 19, 2023
Resolve - Class - 1
In response to an incident where a piece of facade stone approx. 30"by18" came down from the building on 39th floor approx 400 feet height during facade operation pre shift safety meeting records show 13 worker
Sep 19, 2023 · Penalty $5,000
Resolve - Class - 1
In response to an incident where a piece of facade stone approximately 30"by18" came down from the building on 39th floor approximately 400 feet height during stone replacement operation landed on the street on
Sep 19, 2023 · Penalty $625
Resolve - Class - 2
At the time of inspection, i observed a 39' pipe scaffold installed on the roof. upon further inspection, i observed that there was no daily maintenance logbook for the scaffold as required.
Apr 7, 2023
Resolve
Show 40 more ↓
- Class - 1
At the time of my inspection, i observed two suspended scaffolds installed and in use at expo# 1. upon further inspection, i observed that the competent person on site during active work did not have the requir
Apr 7, 2023 · Penalty $5,000
Resolve - Class - 1
Observed active suspended scaffold operations at exposure #1 of premises - 67 greenwich street (filed-at 42 trinity place) where cross-bracing and motor sizing were found to be installed contrary to section s-9
Feb 6, 2023 · Penalty $625
Resolve - Class - 1
Atoi i observed a 40 story partial occupied building still actively under construction. i also observed at exposure 4 (ps 150 school) currently occupied with no roof protection. glass panels still need to be in
Oct 27, 2022 · Penalty $2,500
Resolve - Class - 2
Site condition was not conform to approved ssp. construction fence was built in front of fire hydrant blocking fdny access. ssp show construction fence built around fire hydrant so it is exposed to public and a
Sep 30, 2022
Resolve - Class - 2
Atoi, inadequately maintained storage zone was observed at exp 3. garbage/material were stored over 3 feet without any pedestrian protection. no use of storaze zone/road operation is allowed except to maintain
Sep 30, 2022
Resolve - Class - 2
Atoi, inadequate housekeeping/large amount of material/debris were stored around installed suspended scaffolding observed on roof level. maintain house keeping as per code.
Sep 30, 2022
Resolve - Class - 2
At time of inspection, observed suspended scaffold system installed at main roof level at exposure#1 near corner of exposure#1 and #4. the approved documents provided did not show the insulation and plank at ba
Jun 23, 2022 · Penalty $3,125
Resolve - Class - 1
Failure to institute safety equipment measures.responding to an incident where a piece of wood 2x4 inches and approx 6ft in length fell off the building of debris container and landed on the loading area at exp
May 10, 2021
Resolve - Class - 1
Failure to safeguard. at time of inspection of an active 40 sty nb i observed delivery operation of stone at exp 1&4 corner w/ forklift. forklift was operated by worker w/ no flagman posted on duty to safeguard
Jan 6, 2021 · Penalty $10,000
Resolve - Class - 2
Bc 3307.5 failure to designate flagman. at time of inspection of an active 40 sty nb i observed delivery operation ground level corner at exp 1&2 of stone w/ a forklift. operator of forklift back into pedestria
Jan 6, 2021
Resolve - Class - 2
Work does not conform to approved construction documents and/or approved amendments.at the time of inspection of 40 story new building observed sidewalk shed on exp#1.upon review of the approved design drawings
Dec 15, 2020
Resolve - Class - 1
Failure to safeguard person & property note:at time of my inspection in responding to an incident where a piece of marstone on panel fell (approx) 5lbs from 38 ft level (approx) 400 ft in height landed on sid
Dec 8, 2020
Resolve - Class - 1
Bc 3301.2 failure to institute and maintain safety equipment measures and temporary construction. at time of inspection responding to a complaint where the ssm reported that a metal kindorf fell of building. in
Sep 25, 2020
Resolve - Class - 1
Failure to notify the department of an accident/incident that resultedin a fatality or an injury.a worker was injured suffering a cut to thetop of his hand while he was drilling into sheetrock and the drill kic
Sep 15, 2020 · Penalty $5,000
Resolve - Class - 1
Failure to notify the department of an accident/incident that resultedin a fatality or an injury.a worker fell from a frame ladder and hit his head.an ambulance was called and the worker transported to a hospit
Sep 15, 2020 · Penalty $5,000
Resolve - Class - 1
Failure to comply with manufacturers specifications.note:at time of myinspection of a 40 story nb under framing and sheet rocking in response to an incident reported by s.s.m that one worker fell from "a" frame
Aug 27, 2020 · Penalty $2,500
Resolve - Class - 1
Bc 3301.2 failure to maintain safety measure.note:at time of my inspection responding to complaint one worker got injuried by hit street study inspection renel that during constructing steel study framing unsaf
Jul 7, 2020
Resolve - Class - 1
Prohibited outdoor advertising company sign on sidewalk shed. noted: at time of my inspection of a new 40 sty bldg construction in progress i observed the parapet of the sidewalk shed on trinity place had been
May 20, 2020 · Penalty $2,500
Resolve - Class - 1
Bc330851-inadequate vertical netting large opening.on time of a inspection on an nb 40 stories with a ssm on site i observed active site-upon inspection on roof and several floors was found inadequate netting i
Feb 28, 2020 · Penalty $625
Resolve - Class - 1
Work does not conform to approved construction documents and/or approved amendments.noted:at time of inspection on an 40 stories nb.i observed active site with a ssm present.also observed adjoining property on
Feb 28, 2020 · Penalty $2,500
Resolve - Class - 1
Failure to institute/maintain saftey equipment measures or temporary construction.no guardrails with a ssm on site.i observed active site.also observed at exp#4 for facade work.2 suspended scaffold over adjoini
Feb 28, 2020 · Penalty $2,500
Resolve - Class - 1
Bc330372-fire extinguisher inadequate.at time of inspection on an nb 40 stories with ssm on site i observed active site.also observed in different floors/different locations some fire extinguishers were located
Feb 28, 2020 · Penalty $625
Resolve - Class - 1
Failure to notify the dept of an accident or incident that resulted ina fatality or injury. a worker was moving sheetrock when he hurt his back. worker went to urjent care, as per a check of dept records permit
Feb 19, 2020
Resolve - Class - 1
Failure to notify the department of an accident that resulted in a fatality or injury.a worker injured himself his index finger when it got trapped between the stacker and a concrete column was taken to new yor
Feb 3, 2020
Resolve - Class - 1
Failure to communicate required information to workers during pre shift safety meeting at the tim eof inspection of a 40 story nb in repsonse to an incident where it was reported by ss that workers index finger
Dec 16, 2019
Resolve - Class - 2
Failure to safeguard workers and property.at time of my inspection in response to an incident,where it was reported that a worker nicholas blake was struck by a loaded"a"frame was rolling down on the ramp at 1
Nov 12, 2019
Resolve - Class - 1
Bc331433-scaffold in use contrary to design draw inp:at the time of myinspection of a 40 story building currently as roof level with construction operations in progress.i observed a suspended scaffold rigged at
Oct 30, 2019 · Penalty $2,500
Resolve - Class - 1
Operation of a crane in an unsafe manner,operator harrington michael jnyc hmo#9470 while hoisting catwalk out of the building at 32 trinitonpl,operating tower crane cd#4863 cn#1219/17 caused damage to the windo
Oct 28, 2019
Resolve - Class - 1
Failure to safeguard property.while serving as the lift director masteer rigger jeff#203 working for able rigging who was hired by ercss count construction llc.the user of the tower crane.while the tower crane
Oct 28, 2019
Resolve - Class - 1
At the time of inspection tie#5 on floor#29 was not released accordingto plans submitted for approval by e.o.r steve valjato#082512 crane user united glass systems the crane user of tower crane cd#4863 cn#1219/
Sep 9, 2019 · Penalty $6,250
Resolve - Class - 2
Notification of adjusted suspended scaffold installation and removal. note: at the time of my inspection of a 40story building at roof leveli observed suspended scaffolding installed on 30 floor level at exp1
Jul 30, 2019 · Penalty $5,000
Resolve - Class - 1
Failure to institute & maintain safety equipment measures & temporary construction equipment.responding to an incident where a worker was caught between wall & curtain wall in shipping crate.inspection reveal t
Jul 26, 2019 · Penalty $10,000
Resolve - Class - 2
Failure to comply with commissioner's order contained in summons/violation #35354011l issued on 09/27/2018, and to file a certificate of correction pursuant to 28.201.1 and 1rcny 102-01(d)(2). an acceptable cer
Jul 10, 2019 · Penalty $1,250
Resolve - Class - 2
Failure to comply w/the comm's order contained in summons/vio#35375221m issued on 04-15-19 & to file a c of c pursuant to 28-201.1 & 1rcny 102-01. failure to safeguard all persons & property affected by constru
Jul 3, 2019 · Penalty $1,250
Resolve - Class - 1
Failure to designate site safety manager on work permit application. at time of inspection, of a new 40 story building under construction, i observed that brandon a. rohls was the active site safety manager on
May 30, 2019 · Penalty $10,030
Resolve - Class - 2
Posting or unlawful signs, information, pictorial representation, business or advertising messages on protective structures. at time of inspection of a new 40 story building under construction, i observed illeg
May 30, 2019 · Penalty $2,500
Resolve - Class - 2
Work does not conform to approved construction documents and/or approved amendments. at time of inspection of a new 40 story building under construction, i observed an alternate netting "cocoon system" around t
May 30, 2019 · Penalty $625
Resolve - Class - 1
Fai;lure to safeguard all person & property affected by construction operations-an'a'frame ladder(broken)was observed at the ground level ofthe job site fallen from approx at the 9th fl level & displaced by hig
Apr 15, 2019 · Penalty $10,000
Resolve - Class - 2
Bc 3301.7 failure to provide p.e. approved design drawings: as noted at time of my inspection of a 40 storeis building observed 1 exposed rebars with no cover; b-sign of homey combing / voids / pockets and
Apr 3, 2019 · Penalty $625
Resolve - Class - 1
Bc3301.6.2 design-inadequate (climbking formwork-use of ladders) at time of inspection observed climbing formwork in place at exp#2 (edgar street) floors 13-15. upon review of design drawings observed that
Feb 6, 2019 · Penalty $2,530
Resolve
Complaints
- Heat/hot water
Apartment only
Jan 6, 2026 · Apt 31B
Close - Door/window
Window pane
Oct 26, 2024 · Apt 27B
Close - Construction
Roof
Aug 4, 2004 · Apt 0
Close
Sales history
No recorded sales in our data
Building details
- Building type
- Condominium (RM)
- Year built
- 2018
- Floors
- 40
- Residential units
- 90
- Building area
- 229,336 ft²
- Lot area
- 15,286 ft²
- Zoning
- C5-5
- Community board
- 101
- Council district
- 1
- Block / lot
- 19 / 7501
- Assessed value
- $47,716,996
- Landmark / historic district
- INDIVIDUAL LANDMARK
HPD registration #122636, last renewed Jul 15, 2026.
Questions about 42 Trinity Place
Who owns 42 Trinity Place?
The owner of record in NYC Department of City Planning PLUTO data is Tphgreenwich Owner LLC.
Does 42 Trinity Place have violations?
Yes. NYC HPD has recorded 4 housing violations at this property.
Is 42 Trinity Place rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 42 Trinity Place built?
City records list 2018 as the year it was built.
How many apartments are in 42 Trinity Place?
It has 90 residential units and 92 units in total.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.