202-30 Rockaway Point Blvd is an one-family home built in 1938 in Queens, 11697. It has 539 residential units across 1 floor. The owner of record is Breezy Point Cooperative, INC. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
122
ECB violations
100
HPD complaints
5

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 122

  • Construction other optional

    Work without a permit. at time of inspection observed existing electrical has been removed with new electrical bx wiring installed throughout along with associated electrical junction/splice boxes. no permits for work type.

    Apr 10, 2023

    Dob violation - dismissed
  • Elevator annual inspection / test elevatorrequired

    Violation issued to elevator - failure to file category 1 2017 inspection/test

    Apr 5, 2019

    Dob violation - dismissed
  • Elevator annual inspection / test elevatorrequired

    Violation issued to elevator - failure to file category 1 2017 inspection/test

    Apr 5, 2019

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Mar 6, 2019

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Mar 6, 2019

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Oct 3, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Oct 3, 2018

    Dob violation - dismissed
  • Construction other optional

    Boro commissioner has ordered swo for job # 421061004 due to contracto r withdrawal

    Sep 17, 2018

    Dob violation - dismissed
  • Construction other optional

    Boro commissioner has ordered work stopped for job # 421061004 due to contractor withdrawal

    Sep 17, 2018

    Dob violation - dismissed
  • Construction other optional

    Boro commissioner has ordered stop work order for job # 421061004 due to contractor withdrawal

    Sep 17, 2018

    Dob violation - dismissed
Show 40 more ↓
  • Construction other optional

    Boro commissioner has ordered stop work order for job # 421061004 due to contractor withdrawal

    Sep 17, 2018

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued for failure to file annual boiler 2016 inspection report

    Apr 6, 2018

    Dob violation - active
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Apr 4, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    May 17, 2017

    Dob violation - dismissed
  • Construction other optional

    Boro commissioner has ordered work stopped for # 421298054

    Apr 19, 2017

    Dob violation - active
  • Construction other optional

    Borough commissioner has issued stop work order for permit # 420971915 due to plumber not authorizing permits

    Oct 15, 2016

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Oct 5, 2016

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Oct 5, 2016

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Oct 5, 2016

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Oct 5, 2016

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Oct 5, 2016

    Dob violation - dismissed
  • Plumbing none

    Unlicensed plumbing work

    Aug 17, 2016

    Dob violation - dismissed
  • Construction other optional

    Boro-comm

    Jul 29, 2015

    Dob violation - active
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Feb 11, 2015

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Aug 13, 2014

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jul 23, 2014

    Dob violation - dismissed
  • Emergency none

    Demo legalization - building totally destroyed by superstorm sandy

    Mar 27, 2014

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jan 15, 2014

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jan 15, 2014

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jan 15, 2014

    Dob violation - dismissed
  • Emergency none

    Due to storm sandy building structurally damaged or destroyed . ..... remove debris and/or per order demolish remnant building . ........complaint#: 4546378

    Apr 22, 2013

    Dob violation - dismissed
  • Emergency none

    Egncy-emergency none

    Apr 5, 2013

    Dob violation - dismissed
  • Emergency none

    ...due to storm sandy building structurally damaged or destroyed . remove debris and/or per order demolish remnant buildi ... ....... ... complaint number: 4544372

    Apr 1, 2013

    Dob violation - dismissed
  • Emergency none

    .due to storm sandy building structurally damaged or destroyed . remove debris and/or per order demolish remnant building . .complaint number: 4533433

    Mar 21, 2013

    Dob violation - dismissed
  • Emergency none

    ...due to storm sandy building structurally damaged or destroyed ... remove debris and/or per order demolish remnant building

    Mar 21, 2013

    Dob violation - dismissed
  • Emergency none

    ......due to storm sandy building structurally damaged or destroyed ...... remove debris and/or per order demolish remnant building ...... .complaint number: 4543309

    Mar 20, 2013

    Dob violation - dismissed
  • Emergency none

    .....due to storm sandy building structurally damaged or destroyed ..... remove debris and/or per order demolish remnant building ..... .complaint number: 4533380

    Mar 20, 2013

    Dob violation - dismissed
  • Emergency none

    ......due to storm sandy building structurally damaged or destroyed ...... ... remove debris and/or per order demolish remnant building

    Mar 7, 2013

    Dob violation - dismissed
  • Emergency none

    ........due to storm sandy building structurally damaged or destroyed ........ ... remove debris and/or per order demolish remnant building ........ ... complaint number: 4538872

    Mar 5, 2013

    Dob violation - dismissed
  • Emergency none

    .....due to storm sandy building structurally damaged or destroyed ..... ... ... remove debris and/or per order demolish remnant building ..... ... ... complaint number:4534043

    Mar 4, 2013

    Dob violation - dismissed
  • Emergency none

    ..due to storm sandy building structurally damaged or destroyed .. ... ... remove debris and/or per order demolish remnant building .. ... ... complaint number:4533545

    Mar 1, 2013

    Dob violation - dismissed
  • Emergency none

    ....due to storm sandy building structurally damaged or destroyed .... ... remove debris and/or per order demolish remnant building .... ... complaint number:4533119

    Feb 22, 2013

    Dob violation - dismissed
  • Emergency none

    ....due to storm sandy building structurally damaged or destroyed .... ... remove debris and/or per order demolish remnant building .... ... complaint number: 4533434

    Feb 22, 2013

    Dob violation - dismissed
  • Emergency none

    ....due to storm sandy building structurally damaged or destroyed .... ... remove debris and/or per order demolish remnant building .... ... complaint number: 4539823

    Feb 22, 2013

    Dob violation - dismissed
  • Emergency none

    ...due to storm sandy building structurally damaged or destroyed ... ... remove debris and/or per order demolish remnant building ... ... complaint number: 4533310

    Feb 22, 2013

    Dob violation - dismissed
  • Emergency none

    ......due to storm sandy building structurally damaged or destroyed ...... ... remove debris and/or per order demolish remnant building ...... ... complaint number: 4533349

    Feb 22, 2013

    Dob violation - dismissed
  • Emergency none

    ..due to storm sandy building structurally damaged or destroyed .. ... remove debris and/or per order demolish remnant building .. ... complaint number: 4535683

    Feb 22, 2013

    Dob violation - dismissed
  • Emergency none

    .due to storm sandy building structurally damaged or destroyed . remove debris and/or per order demolish remnant building . complaint number: 4533431

    Feb 19, 2013

    Dob violation - dismissed
  • Emergency none

    ......due to storm sandy building structurally damaged or destroyed ...... ... ... remove debris and/or per order demolish remnant buildin ...... ... ... complaint number: 4533356

    Feb 13, 2013

    Dob violation - dismissed
  • Emergency none

    .....due to storm sandy building structurally damaged or destroyed ..... ... remove debris and/or per order demolish remnant building ..... ... complaint :4533148

    Feb 12, 2013

    Dob violation - dismissed

ECB violations · 100

  • Class - 2

    Work not conforming to plans. at time of inspection, door type 11 has a u-value of .29, drawings calls out for 0.27. also, window type e is specified to have u-value of .27, window installed has a u-value of .3

    Mar 31, 2026 · Penalty $6,250

    Active
  • Class - 2

    Upon inspection i observed a fence installed at exposure 1 with not fence project info panel installed contrary to code 3301.9.1 fence project information panel. where a site is enclosed with a fence in accorda

    Dec 4, 2025 · Penalty $1,250

    Resolve
  • Class - 2

    Jobsite fence not constructed or maintained pursuant to subsection.at the time of inspection of enlargement ext,1 family dwelling.i observedthe fence at all exposure were leaning,unattached,unpainted and were n

    Mar 23, 2023

    Resolve
  • Class - 2

    At the time of inspection, i observed pump jack scaffolds installed for use at expos #1, 2 and #4. upon further inspection it was also observed the scaffolds installed was within distance of 6ft away of un-insu

    Feb 4, 2023

    Resolve
  • Class - 2

    At time energy code compliance inspection. i observed that there were no complete sets of dob approved plans at site.(missing energy analysis and architectural plans.), provide approved /accepted construction d

    Apr 23, 2021

    Resolve
  • Class - 2

    At time of inspection,observed ongoing construction contrary to mayorsemergency executive order 120 and subsequent orders incorporating requirements of governor's executive order 202.34 and subsequent orders an

    Oct 5, 2020

    Resolve
  • Class - 3

    Work w/o a permit noted: @time of inspection observed an woofen deck is being built @exp #2 & 3 of the bldg. the deck measures approx. 40*12'*3'h @exp & 30'*12'*3'h @exp#3 80% pf work in complete. no permit

    Jul 2, 2020 · Penalty $500

    Active
  • Class - 2

    Work without a permit. work noted. concrete deck constructed at rear of building, approx. 5'-7" in height x 27' wide x 20' length, with a door 3' x 5' located on right side of building. work 100 % completed. no

    Jul 19, 2019

    Resolve
  • Class - 2

    Exit door not self closing at first floor in main entrance.main entrance door way to bayside lane one door not self closing properly at the time of inspection when tested.rem:repair/replace door

    Mar 21, 2019 · Penalty $1,562

    Resolve
  • Class - 2

    Failure to comply with the commissioners order contained in summons/violation #35376342n issued on 12/27/18 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01.for doing work that was

    Mar 13, 2019 · Penalty $625

    Resolve
Show 40 more ↓
  • Class - 2

    Failure to comply with the commissioners order contained in summons/violation #35376344r issued on 12/27/18 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01.for no guard rails.rem:c

    Mar 13, 2019 · Penalty $625

    Resolve
  • Class - 2

    Occupancy contrary to that allowed by the cert of occupancy or bldg deppt records. noted: 1 sty bldg arranged as a church w/no pa on file is being occupied contrary to dob records reflecting a 1 family dwelling

    Mar 4, 2019

    Resolve
  • Class - 3

    Work without permit. noted: at time of inspection observed a wooden deck with vinyl railings constructed at back yard measuring approximately 22 ft x 11ft high. no records on dob file. rem: obtain permit or res

    Feb 20, 2019

    Resolve
  • Class - 2

    Respondent failed to make the proper notification for mobile crane after may 1, 2018 to the dept. at time of inspection it was discoveredthat no mobile crane (cn28818) was on site. notification was made of

    Dec 31, 2018 · Penalty $2,500

    Resolve
  • Class - 1

    Work does not conform to approved construction documents. note, on second floor missing exterior door in bedroom in conflict with roof. attic stair location opposite side on second floor bedroom along with stru

    Dec 27, 2018 · Penalty $2,500

    Resolve
  • Class - 1

    Failure to file evidence of compliance with workers comp law and/or disability benefits law. disability insurance expired 12/17/18. remedy: obtain/maintain workers compensation insurance.

    Dec 27, 2018 · Penalty $5,000

    Resolve
  • Class - 1

    Failure to insititure/maintain safety equiptment measures. no guard rails. note: i observed no guardrails of any kind where the workers walk on 3' walkway up a flight of stairs- to enter the jobsite. this is th

    Dec 27, 2018

    Resolve
  • Class - 2

    Job site fence not constructed or maintained pursuant to subsection. noted: construction fence installed under app#421061004 fn exp 9-17-19 has an unsealed opening,granting unauthorized access to vacant lot.

    Sep 17, 2018

    Resolve
  • Class - 1

    Failure to have new or altered plumbing system tested. on 7-3-18 @ 9:30am i observed on the 1st fl a new gas appliance shut off valve w/new gas piping & fittings installed for a gas hot water heater w/o any gas

    Jul 3, 2018 · Penalty $2,500

    Resolve
  • Class - 1

    Work w/o a permit. on 7-3-18 @ approx 9:30am i observed on the 1st fl a new gas appliance shut off valve w/new gas piping & fittings installed for a gas hot water heater w/o any permits on file under dob record

    Jul 3, 2018 · Penalty $1,600

    Resolve
  • Class - 2

    Fence.@ time of inspection observed fence not maintained.1.not paintedhunter green.2. missing 8'0" sections.3.part of fence has fallen against neighbors.fence & also deck(214-11 palmer drive).4.plexi glass or s

    Nov 18, 2017

    Resolve
  • Class - 2

    Failure to safeguard all persons & property affected by construction. noted: at time of inspection approx 6ft of railing missing at upper landing leasing into front entrance of residence,creating a fall hazard.

    Nov 16, 2017

    Resolve
  • Class - 1

    Failure to maintain bldg in code compliant manner. noted: inadequate handrails on upper wooden deck. handrail below code specifications. at t a height of 36"inches,code is 42"inches. at this heights a potential

    Nov 13, 2017

    Resolve
  • Class - 2

    Work without permit.condensor for split type a/c unit is mounted to right side of house,there was a electrical permit signed off on 9/16/16 but that scope of work was not included.also note compliant is from de

    Apr 7, 2017

    Resolve
  • Class - 1

    Failure to provide required notification prior to the commencement of demolition. noted: a check of dept records at time of inspection,indicated that notification was not given.rmdy:notify the dept.

    Feb 16, 2017 · Penalty $1,200

    Resolve
  • Class - 1

    Failure to institute/maintain safety equipment measures or temporary construction-no guardrails.noted:no guardrails on first fl decking are a and roof top level.endangering workers.rem:provide guardrails.

    Jul 12, 2016 · Penalty $2,400

    Resolve
  • Class - 2

    Failure to post permit for work @premises,for application,permit#420971915-pl permit not posted anywhere @site under renovation.rem:post permit.

    Jul 12, 2016

    Resolve
  • Class - 1

    Failure to safeguard all persons&property affected by construction operations.@exp#1 no guard/hand rails on wood staircase,creating a fall hazard for construction workers &owner.failed to install temporary rail

    Jul 12, 2016 · Penalty $1,200

    Resolve
  • Class - 1

    Work w/o a permit.noted:@exp #1 installing new wood deck,wood entrancestairs(deck is approx 15'wx10'.staircase @exp#1&#4 one flight to 1st flr.no permit for work in progress.ongoing work,construction workers on

    Jul 12, 2016 · Penalty $800

    Resolve
  • Class - 1

    Work w/o a permit.noted:construction fence is in place w/o @time of inspection permit#420971915-01-eq-fn expired on 5/13/16.fence is a construction 4'x8' panel wood perimeter fence.rem:obtain permit.

    Jul 12, 2016 · Penalty $800

    Resolve
  • Class - 1

    Work does not conform to approved construction documents and/or approved amendments.noted:created at roof top level 2 rooms with plumbing waste line,ceiling fan for venting and electrical wiring for a 2pc bath

    Jul 12, 2016 · Penalty $1,000

    Resolve
  • Class - 2

    Exit door not self closing. noted: all the doors in 2 bldg's missing door closers. remedy: repair/replace door.

    Sep 30, 2015

    Resolve
  • Class - 1

    Failure to comply w/commissioner's order contained in nov #35152259j issued on 11/07/14,for work w/o permit. rmdy:comply with the commissioner's order. history of compliance.

    Apr 9, 2015 · Penalty $6,000

    Resolve
  • Class - 1

    Failure to comply w/the commissioner's order contained in notice of violation #35152259j issued on 11/7/14,for work w/o permit-demolition ofold bldg. cmu foundation wall,plumbing & electrical work for new bldg.

    Feb 25, 2015 · Penalty $6,000

    Resolve
  • Class - 1

    Failure to comply with the commissioner's order contained in notice of violation #35152259j issued on 11/07/14 for work w/o permit demolition of old bldg,cmu foundation wall,plumbing and electrical work for new

    Jan 10, 2015 · Penalty $2,400

    Resolve
  • Class - 1

    Failure to comply w/the commissioner's order contained in notice of violation #35091282l issued on 8/13/13,for work w/o permit - wood frame structure "bay house" remedy: comply w/the comm's order.

    Nov 8, 2014 · Penalty $6,000

    Resolve
  • Class - 2

    Work w/o a permit.work noted:demolished entire bldg one to band damage and being built a new bldg w/new foundations.remedy:obtain permits.

    Nov 7, 2014

    Resolve
  • Class - 1

    Work w/o a permit.work noted new bldg being erected w/new cmu wall foundation, including new plumbing,electrical work.no fence installed old bldg demolished w/o permot.work approx.70% complete.full swo issued p

    Nov 7, 2014 · Penalty $1,600

    Resolve
  • Class - 1

    Failure to comply w/the commissioner's order contained in notice of violation #35091282l issued on 8/13/13,for work w/o permit - wood frame structure dob bay house. remedy: comply w/the comm's order.

    Sep 13, 2014 · Penalty $2,400

    Resolve
  • Class - 2

    Work w/o permit:noted:job#420854542.permit expired on 08/23/14.work inprogress 2 story n.b.90% job completed.rem:stop all work make site safe.renew permit.

    Sep 11, 2014 · Penalty $400

    Active
  • Class - 1

    Unlawful acts failure to comply with an order of the comm.noted:swo#032913 cerdm01 was issued 03/29/13.vio states:@ time of insp cons work substantially completed(work#41089804-nb)rem:contact dob office to reso

    May 12, 2014 · Penalty $2,400

    Resolve
  • Class - 1

    Failure to provide pedestrian protection for sidewalks walkway no jobsite fence provided at nb jobsite with open foundation. remedy:stop all work and provide protection/fence

    May 4, 2014 · Penalty $4,800

    Resolve
  • Class - 1

    Failure to comply w/the commissioner's order contained in notice of violation #35030231m issued on 08/13/13 for work w/out permit-created app 800 s.f. structure dba "bay house". rem:comply w/the commissioners o

    Apr 5, 2014

    Resolve
  • Class - 1

    Failure to comply w/the commissioner's order contained in notice of violation #35030231m issued on 8/13/13,for work w/o permit - created app 800 s.f. structure dba "bry house". remedy: comply w/the comm's.

    Feb 8, 2014

    Resolve
  • Class - 1

    Failure to comply w/the commissioner's order contained in nov #35030231m issued on 8.13.13 for work w/o permit - created approx 800 s.f. structure dba "bay house". remedy: comply w/the commissioner's order.

    Dec 21, 2013

    Resolve
  • Class - 2

    Work w/o permit. noted: illegal rear extension created approx 21' x 21' (wood frame) w/no permit on file. work 75% complete pictures taken. remedy: stop work at extension immediately obtain approvals, permits &

    Dec 16, 2013 · Penalty $800

    Resolve
  • Class - 1

    Work without permit. noted: structure created approx 800 sq ft, consisting of wood frame, with tarp as roof, d.b.a. "bayhouse" no permit obtained, pictures taken, work completed, premises being used as a "eatin

    Aug 13, 2013 · Penalty $1,600

    Resolve
  • Class - 1

    Work w/o permit. noted: structure created approx 800sq feet consistingof wood frame w/tarp as roof. d.b.a. "bay house" no permit obtained,pictures taken work completed. premises being used as a "eating & drinki

    Aug 13, 2013

    Resolve
  • Class - 2

    Failure to safeguard all persons and property affected by constructionoperations. noted the following conditions: the fire steps leading to patio deck which does not have walkway covering. also front entrance

    Apr 17, 2013 · Penalty $1,200

    Resolve
  • Class - 1

    Full *swo*.work w/o permit.noted:premises installed new foundation walls @all sides of bldg & raised the bldg height.installed wooden new beams @entire 1st fl & metal (i) beams.installed new water @waste lines

    Apr 13, 2013 · Penalty $1,600

    Resolve

Complaints

  • Heating

    Heat related

    Feb 10, 2010 · Apt A7

    Close
  • Electric

    Electric-supply

    Feb 10, 2010 · Apt A7

    Close
  • Electric

    Electric-supply

    Feb 10, 2010 · Apt A7

    Close
  • Heating

    Heat related

    Feb 17, 2007 · Apt BLDG

    Close
  • Nonconst

    Illegal

    Jul 17, 2003 · Apt BLDG

    Close

Sales history

DatePriceTypeUnits
Aug 14, 2026Non-market transferOne family dwellings—
Jul 30, 2026$885,000One family dwellings—
Jul 22, 2026Non-market transferOne family dwellings—
Jul 21, 2026Non-market transferOne family dwellings—
Jul 20, 2026$1,375,000One family dwellings—
Jun 2, 2026Non-market transferOne family dwellings—
May 22, 2026Non-market transferOne family dwellings—
May 15, 2026$585,000One family dwellings—
Apr 30, 2026$300,000One family dwellings—
Mar 26, 2026Non-market transferOne family dwellings—
Mar 6, 2026$500,000One family dwellings—
Mar 4, 2026$510,000One family dwellings—
Feb 6, 2026$850,000One family dwellings—
Jan 9, 2026$630,000One family dwellings—
Dec 5, 2025$1,405,000One family dwellings—
Nov 14, 2025$650,000One family dwellings—
Nov 7, 2025Non-market transferOne family dwellings—
Oct 27, 2025$750,000One family dwellings—
Sep 26, 2025$775,000One family dwellings—
Sep 24, 2025$190,000One family dwellings—

Building details

Building type
One-family home (A8)
Year built
1938
Floors
1
Residential units
539
Building area
460,000 ft²
Lot area
3,589,344 ft²
Zoning
R4
Community board
414
Council district
32
Block / lot
16350 / 300
Assessed value
$8,031,973
Landmark / historic district
No

Questions about 202-30 Rockaway Point Blvd

Who owns 202-30 Rockaway Point Blvd?

The owner of record in NYC Department of City Planning PLUTO data is Breezy Point Cooperative, INC.

Does 202-30 Rockaway Point Blvd have violations?

NYC HPD has no housing violations on record for this property.

Is 202-30 Rockaway Point Blvd rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 202-30 Rockaway Point Blvd built?

City records list 1938 as the year it was built.

How many apartments are in 202-30 Rockaway Point Blvd?

It has 539 residential units.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.