roofy

75-59 188 Street

Queens, NY 11366BBL 4-07205-0044Map

Owner of record: 7559 188 LLC

75-59 188 Street is an office building built in 2024 in Queens, 11366. The owner of record is 7559 188 LLC. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
2
ECB violations
25
HPD complaints
0

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 2

  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Nov 13, 2024

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Apr 17, 2024

    Dob violation - dismissed

ECB violations · 25

  • Class - 2

    Failure to maintain adequate housekeeping per section requirement. as noted: at time of inspection at an active jobsite of a proposed 3 story building already at the rooftop level. observed at 1st floor exposur

    Nov 19, 2025 · Penalty $6,250

    Active
  • Class - 1

    Failure to institute safety equipment measures or temporary construction-no guardrails. as noted: at time of inspection at an active jobsitefor a proposed 3 story building already at the rooftop level. observed

    Nov 19, 2025 · Penalty $25,000

    Active
  • Class - 2

    Observed 3 story new building under permit #q08035309-i1 with an erected fence and upon further review on crm no active permit was found.

    Mar 27, 2025 · Penalty $625

    Resolve
  • Class - 1

    Upon request to review a site safety plan (ssp), approved construction fence drawings, manufacturer specifications for active pump-jack equipment at exposure #4 and daily hot-work permits; gc was unable to prov

    Sep 6, 2024 · Penalty $2,500

    Resolve
  • Class - 1

    Gc failed to provide adjacent property protection. observed no over-head protection (ohp) and no roof protection (per bc3309.10) at exposure #2 and #4. active construction operations at each exposure and roof p

    Sep 6, 2024 · Penalty $10,000

    Resolve
  • Class - 1

    Observed the accumulation of debris, construction waste and unconsolidated material throughout site. additionally, observed missing floor numbering, inadequate lighting at cellar, and water accumulating in the

    Sep 6, 2024 · Penalty $2,500

    Resolve
  • Class - 1

    Observed failure to maintain guardrails on multiple floors, presenting an immediate fall-hazard to personnel and the public.

    Sep 6, 2024 · Penalty $5,000

    Resolve
  • Class - 1

    Per bc3311.3; observed the improper storage of (400) powder-actuated charges (.27 caliber), presenting an immediate hazard to first-responders and the public should there be a fire or theft at the site.comply w

    Sep 6, 2024 · Penalty $5,000

    Resolve
  • Class - 2

    Observed construction fence erected at all exposures. on researching dob now the equipment was found to have an expired permit.

    Sep 6, 2024

    Resolve
  • Class - 1

    Observed pre-shift meetings failed to communicate required information regarding hazards and mitigation of those conditions which presented an immediate threat to the public and personnel. note additional viola

    Sep 6, 2024 · Penalty $5,000

    Resolve
Show 15 more ↓
  • Class - 1

    Inspection of steel erection going on and multiple workers onsite, there was no superintendent or competent person onsite. the log book was not filled out the pre-shift was not done by a competent person, there

    Jun 5, 2024 · Penalty $10,000

    Resolve
  • Class - 1

    During inspection of a proposed 3 story building with active steel erection taking place, i requested to speak to the superintendent, who was not onsite. the lack of safety supervision onsite created a hazardou

    Jun 5, 2024

    Resolve
  • Class - 1

    No competent person: during inspection of a proposed 3 story building with active steel erection taking place, i requested to speak to the competent person, who was not onsite. the lack of safety supervision on

    Jun 5, 2024

    Resolve
  • Class - 1

    During inspection of a proposed 3 story building with active steel erection going on, i observed that there was open, inadequate, and unsafe perimeter and inside drop offs, creating fall hazards to the worker a

    Jun 5, 2024 · Penalty $5,000

    Resolve
  • Class - 1

    All guardrail systems on site around leading edges/shafts missing toe-boards, netting, and unable to support 200# on 1st floor creating hazardous condition in which a worker might push tools or materials toward

    May 9, 2024 · Penalty $5,000

    Resolve
  • Class - 2

    Observed workers installing steel connections between 1st & 2nd floor with no competent person designated by construction superintendent (on permit) with notarized letter as warranted by code. pre-shift logs fa

    May 9, 2024 · Penalty $5,000

    Resolve
  • Class - 2

    Observed workers installing steel connections at a height exceeding the height of construction fence between 1st & 2nd floor. no over head protection or controlled access agreement provided at exposure 4 for pa

    May 9, 2024 · Penalty $5,000

    Resolve
  • Class - 1

    Structural work does not conform to plan. at time of inspection observed rakers support beam not per plan, at exp#2 plan does not indicate excavation support, ramp and exit point which indicate on plan does not

    Dec 8, 2023 · Penalty $6,250

    Resolve
  • Class - 1

    At time of inspection observed , rebars exposed/uncapped, no guard railing where required around excavated arear, missing construction fence at multiple locations, adjecent foundation unprotected/exposed, worke

    Dec 8, 2023 · Penalty $6,250

    Resolve
  • Class - 2

    At the time of my re-inspection observed multiple crack son adj properties at expos #2, upon request for pre construction survey and agreements, non was provided, was not at site. maintain all required document

    Dec 7, 2023 · Penalty $3,125

    Resolve
  • Class - 1

    At time of inspection on a active jobsite of a 3 story nb,currently at foundation/excavation phase,observed that safe means of egress and ingress was not provided from foundation/excavation pit.this condition

    Dec 6, 2023 · Penalty $5,000

    Resolve
  • Class - 1

    At time of inspection on a active jobsite of a 3 story nb,currently at foundation/excavation phase,observed that excavator is stored at the edge of excavation. this condition is very dangerous for workers to ge

    Dec 6, 2023 · Penalty $5,000

    Resolve
  • Class - 2

    At time of my inspection on a active jobsite of a 3 story nb,observed that housekeeping throughout the entire site were inadequate,mix material and debris creating a trip and fall hazard for workers and persona

    Dec 6, 2023 · Penalty $3,125

    Resolve
  • Class - 2

    During an inspection of a 3-story building with a basement, improper timber wood lagging installation was observed in the ongoing soe work. the soe plans revealed deviations, including insufficient 3.5-foot bra

    Sep 26, 2023

    Resolve
  • Class - 2

    Time of inspection at 3 story nb with cellar observed soe work,timber wood laggings install in progress, upon request to see site safety plans , none was provided by cp, without ssp unable to verify safety meas

    Sep 26, 2023 · Penalty $1,250

    Resolve

Complaints

No HPD complaints in our records

Complaint data is still being backfilled from NYC Open Data.

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Office building (O5)
Year built
2024
Floors
3
Residential units
—
Building area
9,032 ft²
Lot area
4,000 ft²
Zoning
R2A
Community board
408
Council district
23
Block / lot
7205 / 44
Assessed value
$609,750
Landmark / historic district
No

Questions about 75-59 188 Street

Who owns 75-59 188 Street?

The owner of record in NYC Department of City Planning PLUTO data is 7559 188 LLC.

Does 75-59 188 Street have violations?

NYC HPD has no housing violations on record for this property.

Is 75-59 188 Street rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 75-59 188 Street built?

City records list 2024 as the year it was built.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.