75-59 188 Street
Queens, NY 11366BBL 4-07205-0044Map
Owner of record: 7559 188 LLC
75-59 188 Street is an office building built in 2024 in Queens, 11366. The owner of record is 7559 188 LLC. HPD has no housing violations on record for this property.
- HPD violations
- 0
- DOB violations
- 2
- ECB violations
- 25
- HPD complaints
- 0
What to know
No open immediately-hazardous violations among recent records.
HPD has not cited this building.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 0
No HPD violations on record
DOB building violations · 2
- Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Nov 13, 2024
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Apr 17, 2024
Dob violation - dismissed
ECB violations · 25
- Class - 2
Failure to maintain adequate housekeeping per section requirement. as noted: at time of inspection at an active jobsite of a proposed 3 story building already at the rooftop level. observed at 1st floor exposur
Nov 19, 2025 · Penalty $6,250
Active - Class - 1
Failure to institute safety equipment measures or temporary construction-no guardrails. as noted: at time of inspection at an active jobsitefor a proposed 3 story building already at the rooftop level. observed
Nov 19, 2025 · Penalty $25,000
Active - Class - 2
Observed 3 story new building under permit #q08035309-i1 with an erected fence and upon further review on crm no active permit was found.
Mar 27, 2025 · Penalty $625
Resolve - Class - 1
Upon request to review a site safety plan (ssp), approved construction fence drawings, manufacturer specifications for active pump-jack equipment at exposure #4 and daily hot-work permits; gc was unable to prov
Sep 6, 2024 · Penalty $2,500
Resolve - Class - 1
Gc failed to provide adjacent property protection. observed no over-head protection (ohp) and no roof protection (per bc3309.10) at exposure #2 and #4. active construction operations at each exposure and roof p
Sep 6, 2024 · Penalty $10,000
Resolve - Class - 1
Observed the accumulation of debris, construction waste and unconsolidated material throughout site. additionally, observed missing floor numbering, inadequate lighting at cellar, and water accumulating in the
Sep 6, 2024 · Penalty $2,500
Resolve - Class - 1
Observed failure to maintain guardrails on multiple floors, presenting an immediate fall-hazard to personnel and the public.
Sep 6, 2024 · Penalty $5,000
Resolve - Class - 1
Per bc3311.3; observed the improper storage of (400) powder-actuated charges (.27 caliber), presenting an immediate hazard to first-responders and the public should there be a fire or theft at the site.comply w
Sep 6, 2024 · Penalty $5,000
Resolve - Class - 2
Observed construction fence erected at all exposures. on researching dob now the equipment was found to have an expired permit.
Sep 6, 2024
Resolve - Class - 1
Observed pre-shift meetings failed to communicate required information regarding hazards and mitigation of those conditions which presented an immediate threat to the public and personnel. note additional viola
Sep 6, 2024 · Penalty $5,000
Resolve
Show 15 more ↓
- Class - 1
Inspection of steel erection going on and multiple workers onsite, there was no superintendent or competent person onsite. the log book was not filled out the pre-shift was not done by a competent person, there
Jun 5, 2024 · Penalty $10,000
Resolve - Class - 1
During inspection of a proposed 3 story building with active steel erection taking place, i requested to speak to the superintendent, who was not onsite. the lack of safety supervision onsite created a hazardou
Jun 5, 2024
Resolve - Class - 1
No competent person: during inspection of a proposed 3 story building with active steel erection taking place, i requested to speak to the competent person, who was not onsite. the lack of safety supervision on
Jun 5, 2024
Resolve - Class - 1
During inspection of a proposed 3 story building with active steel erection going on, i observed that there was open, inadequate, and unsafe perimeter and inside drop offs, creating fall hazards to the worker a
Jun 5, 2024 · Penalty $5,000
Resolve - Class - 1
All guardrail systems on site around leading edges/shafts missing toe-boards, netting, and unable to support 200# on 1st floor creating hazardous condition in which a worker might push tools or materials toward
May 9, 2024 · Penalty $5,000
Resolve - Class - 2
Observed workers installing steel connections between 1st & 2nd floor with no competent person designated by construction superintendent (on permit) with notarized letter as warranted by code. pre-shift logs fa
May 9, 2024 · Penalty $5,000
Resolve - Class - 2
Observed workers installing steel connections at a height exceeding the height of construction fence between 1st & 2nd floor. no over head protection or controlled access agreement provided at exposure 4 for pa
May 9, 2024 · Penalty $5,000
Resolve - Class - 1
Structural work does not conform to plan. at time of inspection observed rakers support beam not per plan, at exp#2 plan does not indicate excavation support, ramp and exit point which indicate on plan does not
Dec 8, 2023 · Penalty $6,250
Resolve - Class - 1
At time of inspection observed , rebars exposed/uncapped, no guard railing where required around excavated arear, missing construction fence at multiple locations, adjecent foundation unprotected/exposed, worke
Dec 8, 2023 · Penalty $6,250
Resolve - Class - 2
At the time of my re-inspection observed multiple crack son adj properties at expos #2, upon request for pre construction survey and agreements, non was provided, was not at site. maintain all required document
Dec 7, 2023 · Penalty $3,125
Resolve - Class - 1
At time of inspection on a active jobsite of a 3 story nb,currently at foundation/excavation phase,observed that safe means of egress and ingress was not provided from foundation/excavation pit.this condition
Dec 6, 2023 · Penalty $5,000
Resolve - Class - 1
At time of inspection on a active jobsite of a 3 story nb,currently at foundation/excavation phase,observed that excavator is stored at the edge of excavation. this condition is very dangerous for workers to ge
Dec 6, 2023 · Penalty $5,000
Resolve - Class - 2
At time of my inspection on a active jobsite of a 3 story nb,observed that housekeeping throughout the entire site were inadequate,mix material and debris creating a trip and fall hazard for workers and persona
Dec 6, 2023 · Penalty $3,125
Resolve - Class - 2
During an inspection of a 3-story building with a basement, improper timber wood lagging installation was observed in the ongoing soe work. the soe plans revealed deviations, including insufficient 3.5-foot bra
Sep 26, 2023
Resolve - Class - 2
Time of inspection at 3 story nb with cellar observed soe work,timber wood laggings install in progress, upon request to see site safety plans , none was provided by cp, without ssp unable to verify safety meas
Sep 26, 2023 · Penalty $1,250
Resolve
Complaints
No HPD complaints in our records
Sales history
No recorded sales in our data
Building details
- Building type
- Office building (O5)
- Year built
- 2024
- Floors
- 3
- Residential units
- —
- Building area
- 9,032 ft²
- Lot area
- 4,000 ft²
- Zoning
- R2A
- Community board
- 408
- Council district
- 23
- Block / lot
- 7205 / 44
- Assessed value
- $609,750
- Landmark / historic district
- No
Questions about 75-59 188 Street
Who owns 75-59 188 Street?
The owner of record in NYC Department of City Planning PLUTO data is 7559 188 LLC.
Does 75-59 188 Street have violations?
NYC HPD has no housing violations on record for this property.
Is 75-59 188 Street rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 75-59 188 Street built?
City records list 2024 as the year it was built.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.