183 Street is a vacant lot in Queens, 11365. The owner of record is Cung, Jonathan. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
14
ECB violations
33
HPD complaints
0

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 14

  • Failure to post energy grade/score none

    Failure to display energy efficiency score and energy efficiency grade as per adcode sec. 28-309.12.3

    Apr 29, 2021

    Dob violation - active
  • Failure to post energy grade/score none

    Failure to display energy efficiency score and energy efficiency grade as per adcode sec. 28-309.12.3

    Apr 29, 2021

    Dob violation - dismissed
  • Elevator annual inspection / test elevatorrequired

    Violation issued to elevator-failure to file category 1 2016 inspection/test

    Sep 15, 2017

    Dob violation - dismissed
  • Elevator annual inspection / test elevatorrequired

    Violation issued to elevator-failure to file category 1 2016 inspection/test

    Sep 15, 2017

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Sep 7, 2011

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Dec 2, 2010

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Dec 2, 2010

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Dec 2, 2010

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Dec 2, 2010

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Dec 2, 2010

    Dob violation - dismissed
Show 4 more ↓
  • Construction other optional

    C-construction other optional

    Jul 29, 2010

    Vw*-violation - work w/o permit dismissed
  • Emergency none

    Egncy-emergency none

    Nov 8, 2004

    Dob violation - dismissed
  • Unsafe buildings none

    Ub-unsafe buildings none

    Nov 1, 2004

    V%*-dob violation - dismissed
  • Construction other optional

    Jv

    Feb 1, 1989

    Dob violation - dismissed

ECB violations · 33

  • Class - 2

    Failure to post d.o.t. permit for street/sidewalk closing. as noted: at time of inspection at a active construction site,material block & sand is unloaded off a flatbed track at exposure #1 west bound site of

    Apr 19, 2011

    Resolve
  • Class - 2

    Failure to provide filed storage curing facility at construction site.as noted: at time of inspection at a active construction site,concrete placement at steel ( ) floor #2,intl geo tech lab molded 9 -

    Apr 15, 2011 · Penalty $1,600

    Resolve
  • Class - 2

    Failure to provide/post signs at job site pursuant to subsection. as noted: at time of inspection at an active construction site, observed at exp 1 (horace harding expwy) there is no contractor info sign post

    Mar 7, 2011

    Resolve
  • Class - 1

    Failure to provide a flagperson. as noted: at time of inspection at anactive construction site, bldg up to 2 stories, observed at exp 1 a flatbed truck unloading material (block) at street level, failure to

    Mar 7, 2011 · Penalty $1,600

    Resolve
  • Class - 2

    Sec. 3307.5.1 failure to provide a watchperson on duty at constructionsite. as noted: at time of inspection construction site is closed,i observed no watchperson on duty at 6:40am to 7:40am. all plywood entranc

    Feb 1, 2011

    Resolve
  • Class - 2

    Bc3307.5.1)failure to provide a watchperson on duty @ construction site.noted:@ time of inspection construction site is closed.i observed no watchperson on duty @ 6:20am to 7:25am when workers open construction

    Jan 4, 2011 · Penalty $400

    Resolve
  • Class - 1

    Bc3313.1)flammable & combustible mixtures compressed gases & other hazardous material.noted:@ time of inspection on an active construction site steel erection in progress observed 2 oxygen & two aceylene tanks

    Dec 22, 2010 · Penalty $1,600

    Resolve
  • Class - 2

    Failure to provide storage curing facility(curing box)@ construction site.as noted:@ time of inspection @ an active construction site light weight concrete placement @ deck#1 level on 12/10/10.i observed 35-4"x

    Dec 13, 2010 · Penalty $1,600

    Resolve
  • Class - 2

    Failure to remove strength test cylinders stored for a perios up to 48 hrs.as noted:@ time of inspection on an active const site,light weight concrete placement @ deck#1 level on 12/10/10.i observed 35-4"x8" st

    Dec 13, 2010 · Penalty $1,600

    Resolve
  • Class - 2

    Failure to remove strength test cylinders stored for a period of up to 48 hours.as noted:@ time of inspection on an active construction site.light weight concrete placement @ deck#1 level on 12/10/10.i observed

    Dec 13, 2010 · Penalty $1,600

    Resolve
Show 23 more ↓
  • Class - 2

    (misc)bc3307.5.1failure to provide a watchperson on duty @ construction site.as noted:@ time of inspection construction site is closed i observed no watch person on duty @ 1:40pm to 2:30pm lot gorund coverage i

    Dec 11, 2010

    Resolve
  • Class - 1

    207.2.2 misc vio. failure to comply w/ an order to stop work by dept there was some underpinning completed under an existing retaining wall @ exposure 4 which was working against a stop work order issued on 8-6

    Aug 13, 2010

    Resolve
  • Class - 1

    Failure to provide protection @ sides of excavation there are portions of the excavated site that do not have any support of excavation or a 45 degree angle of repose making the stability of the earth unstable

    Aug 13, 2010 · Penalty $2,400

    Resolve
  • Class - 1

    3304.4.4 & 27-1032b misc vio failure to provide 3'-6" guardrail & accessible sides of excavation there are no guardrails installed @ the top of the excavation the excavation is approx 15' deep 402238333 nb reme

    Aug 9, 2010 · Penalty $1,600

    Resolve
  • Class - 1

    Failure to provide protection @ sides of excavation there was a shear cut approx 15' high & 30' long & no support for excavation (@ exposure 2) 402238333 nb remedy: backfill immediately provide protection

    Aug 9, 2010 · Penalty $2,400

    Resolve
  • Class - 1

    Work w/o a permit @ time of inspection approx 4ftwx5ftd section of foundation wall @ 184-17 horace harding expwy was undermined & underpinned by the ongoing const work @ adjacent bldg (183-15 hh expwy) w/o

    Aug 6, 2010 · Penalty $800

    Resolve
  • Class - 2

    Sec. 3307.5.1. failure to provide watch person on duty at site. as noted: at time of inspection site is closed, i observed no watchperson onduty at 6:25 am, lot ground coverage is approx 200' x 125', all three

    Jul 20, 2010 · Penalty $800

    Resolve
  • Class - 1

    Work does not conform to approved construction documents &/or approved.there are areas of this large construction site that don't have the 1 to 1 slope as indicated on the plans,also there is a raker & whaler i

    Jul 20, 2010 · Penalty $1,000

    Resolve
  • Class - 2

    Work does not conform to approved const. documents &/or approved amendment. noted : plans fail to provide details for retaining wall @ exp 1& for removal of wall. wall approx 10ft high 60 ft in length job # 402

    Mar 15, 2010 · Penalty $500

    Resolve
  • Class - 2

    Jobsite fence not constucted pursuant to subsection. note: job site fence erected under job#402238324 harding exp. northside & approx 200' of job site fence displaced on booth memorial ave side. stop all work-m

    Jul 26, 2009 · Penalty $400

    Resolve
  • Class - 1

    Failure to safeguard all eprsons an property affected by construction operations. noed; job site fence erected under job #402238324 has various sections dispaced throughout leaving job site open to approx. 8'dr

    Jul 26, 2009 · Penalty $1,200

    Resolve
  • Class - 2

    Job site fence not constructed pursuant to sub section. at time of inspection job site fence erected under job #40223824 is defective. defects noted: along west side of property missing approx 50-60/near feet

    Aug 20, 2008

    Resolve
  • Hazardous

    No sidewalk shed provided. on inspection of above premises demolition of bldg was in progress with machine. bldg is standing on just property line with sidewalk and is having 32'+ height. no sidewalk shed was

    Mar 29, 2005

    Resolve
  • Hazardous

    Demolition in unsafe (method) manner. on inspection of above premises,demolition of 32'high building was in progress, using heavy machinary (excavator with grabler jaw). building was standing on the line with

    Mar 29, 2005

    Resolve
  • Non-hazardous

    Violation of parking regulations in a commercial district. noted: at the time inspection at front of premises illegal use as dead storage of vehicles with no license plates: (1) red toyota, (2) blue toyota

    Nov 1, 2004 · Penalty $240

    Resolve
  • Hazardous

    Failure to maintain defect is loose bricks collapsed from face of retaining wall on to sidewalk remedy maintain bricks on retaining wall

    Feb 4, 2004 · Penalty $800

    Resolve
  • Non-hazardous

    36-49-51 (1)2nd valve in water column to install and drain be not reduced(2)barometric damper in breeching improperly installed.3-breeching sections be sealed gas tight.do not use boiler is sealed

    Apr 6, 2001 · Penalty $650

    Resolve
  • Non-hazardous

    Work without a permit. work noted: in cellar built partitions & doors to created office rooms on east side of the bldg. also on 1st floor installed door & partitions. remedy: obtain a permit if it feasible or

    Aug 18, 1999 · Penalty $500

    Resolve
  • Non-hazardous

    Occupancy contrary to that allowed by the building department records.illegal in cellar on east side occupied as a office purpose & divided in small rooms. according to building records cellar for commercial

    Aug 18, 1999 · Penalty $400

    Resolve
  • Non-hazardous

    36

    Aug 24, 1994

    Resolve
  • Non-hazardous

    Occupancy contrary to that allowed by the certificate of occupancy #q202838 from accessory parking spaces for 60 cars- to parking spaces for approx. 80 cars as indicated by painted stripes. remedy- obtain a cer

    Jan 20, 1993

    Resolve
  • Non-hazardous

    Occupancy contrary to that allowed by the certificate of occupancy c/o q 202838 states,from legal off street addesory parking for 60 carsin lot to illegal approx. 95 accessory parking spaces for car in lot.

    Nov 17, 1992 · Penalty $350

    Resolve
  • Non-hazardous

    Failing to maintain chain links fence at west side at lot defects noted: ports broken missing. remedy: make repairs forthwiht.

    Jun 24, 1988

    Resolve

Complaints

No HPD complaints in our records

Complaint data is still being backfilled from NYC Open Data.

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Vacant lot (V1)
Year built
—
Floors
—
Residential units
—
Building area
—
Lot area
396 ft²
Zoning
R3-1
Community board
411
Council district
20
Block / lot
7067 / 15
Assessed value
$8,370
Landmark / historic district
No

Questions about 183 Street

Who owns 183 Street?

The owner of record in NYC Department of City Planning PLUTO data is Cung, Jonathan.

Does 183 Street have violations?

NYC HPD has no housing violations on record for this property.

Is 183 Street rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.