Owner of record: Qi Deng Huang

148-18 59 Avenue is a two-family home built in 1945 in Queens, 11355. It has 2 residential units across 2.5 floors. The owner of record is Qi Deng Huang. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
8
ECB violations
12
HPD complaints
0

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 8

  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Feb 21, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Feb 21, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Feb 21, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Feb 21, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Oct 4, 2017

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Oct 4, 2017

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Oct 4, 2017

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Oct 4, 2017

    Dob violation - dismissed

ECB violations · 12

  • Class - 1

    Unlawfull acts. failure to comply w/a law,rule or commissioners order involving construction & or safety equipment operations. at the time of inspection it was observed an construction site where contractor was

    Nov 22, 2017

    Resolve
  • Class - 1

    Unlawfully continued wokr while on notice of a stop work order. at thetime of inspection it was observed an active construction site where new foundation wall was poured at exp#2&1 also new concrete steps were

    Nov 22, 2017 · Penalty $24,000

    Resolve
  • Class - 1

    Work does not conform to approved construction documents &/or approvedamendments. at the time of inspection it was observed an construction site where contractor newly poured foundation wall while working again

    Nov 22, 2017

    Resolve
  • Class - 2

    Failure to perform proper concrete washout water procedures at construction site. at the time of inspection it was observed an active site where contractor poured foundation wall at exp#1&2 & did not provide an

    Nov 22, 2017 · Penalty $1,200

    Resolve
  • Class - 1

    Sidewalk not maintained,consisting of large cracks,holes,& voids,uneven due to construction activities creating a trip hazard for pedestrians. at the time of inspection it was observed an active construction

    Nov 22, 2017 · Penalty $1,600

    Resolve
  • Class - 1

    Work w/o a permit. on 07/11/17 at apprx 1:45pm i observed the removal of water/sanitary, gas and storm piping and fittings throughout the proerpty. all removal of work was done w/o permits on file. partial stop

    Jul 11, 2017 · Penalty $1,630

    Resolve
  • Class - 1

    Work does not conform to approved construction documents. at time of inspection observed an active construction site at foundation stage. during inspection observed that the contractor was working on demolition

    Jul 11, 2017 · Penalty $1,000

    Resolve
  • Class - 1

    Construction superintendent failed to perform duties per rule. at timeof inspection observed an active construction site at foundation stage. during inspection noted several violating condition. 1)work does not

    Jul 11, 2017 · Penalty $1,600

    Resolve
  • Class - 1

    Failure to designated &/or have construction superintendent present at site as required. at time of inspection responding to a incident observed an active construction site w/foundation footing work in progress

    Jul 11, 2017 · Penalty $1,600

    Resolve
  • Class - 1

    No guardrails. at time of inspection observed an active construction site at foundation stage. during inspection noted that the contractor excavated for footing approx 8'-10'depth w/o protection or guardrails

    Jul 11, 2017

    Resolve
Show 2 more ↓
  • Class - 2

    Job site fence not constructed pursuant to subsection. at time of inspection observed an active construction site at foundation stage. during inspection noted that the fence is damage at exp#3. remedy: comply w

    Jul 11, 2017

    Resolve
  • Class - 1

    Failure to safeguard all persons & property affected by construction operations. at time of inspection responding to a incident where the contractor damaged a server gas pipe. fdny con edison & nypd was on site

    Jul 11, 2017 · Penalty $25,000

    Resolve

Complaints

No HPD complaints in our records

Complaint data is still being backfilled from NYC Open Data.

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Two-family home (B3)
Year built
1945
Floors
2.5
Residential units
2
Building area
3,531 ft²
Lot area
4,000 ft²
Zoning
R4A
Community board
407
Council district
20
Block / lot
6424 / 48
Assessed value
$110,400
Landmark / historic district
No

Questions about 148-18 59 Avenue

Who owns 148-18 59 Avenue?

The owner of record in NYC Department of City Planning PLUTO data is Qi Deng Huang.

Does 148-18 59 Avenue have violations?

NYC HPD has no housing violations on record for this property.

Is 148-18 59 Avenue rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 148-18 59 Avenue built?

City records list 1945 as the year it was built.