147-26 Sanford Avenue
Queens, NY 11355BBL 4-05377-0022Map
Owner of record: Js 14726 LLC
147-26 Sanford Avenue is an elevator apartment building built in 2025 in Queens, 11355. It has 4 residential units across 4 floors. The owner of record is Js 14726 LLC. HPD has no housing violations on record for this property.
- HPD violations
- 0
- DOB violations
- 0
- ECB violations
- 14
- HPD complaints
- 0
What to know
No open immediately-hazardous violations among recent records.
HPD has not cited this building.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 0
No HPD violations on record
DOB building violations · 0
No DOB violations on record
ECB violations · 14
- Class - 2
Work without a permit. at time of inspection, observed mechanical work being performed without renewing permit filed on dob system., obtain all permits; please submit permit to [email protected]
Apr 15, 2026
Resolve - Class - 2
Observed: active site upon inspection noted few piles of debris materials like metal, debris netting styrofoam in black plastic bags ,wood palets and others creating hazards for workers and fire hazards contrar
Mar 23, 2026
Resolve - Class - 2
Observed: active site upon inspection noted missing fire extinguishers on cellar ,2,3,& 4 floor noted: existing fire extinguishers are inadequate missing tags and pins or , placed on floor contrary to nyc fire
Mar 23, 2026
Resolve - Class - 2
Observed : active site with supported scaffold on all exposures upon inspection was requested installation or periodic inspection letter for pipe scaffold but none was provided contrary to building code / provi
Mar 23, 2026 · Penalty $1,250
Resolve - Class - 2
At time of inspection, i observed yodock system set up on the roadway not filled with water/sand or with connecting plastic "bone" allowing unintended movement of the barriers increasing the risk of displacemen
Nov 17, 2025 · Penalty $1,250
Resolve - Class - 2
Temporary construction equip or installation onsite expired permit.as noted:at time of inspection construction site of a proposed 4 story building was already at the rooftop level observed construction plywood
Nov 12, 2025 · Penalty $1,250
Resolve - Class - 1
Failure to institute/maintain safety equip measures/temporary construction no handrail.as noted:at time of inspection at an active jobsite of a proposed 4 story building already at the rooftop level observed fr
Nov 12, 2025
Resolve - Class - 2
28-103.8 failure to maintain embeded safety straps installation inspection logbook onsite.as noted:at time of inspection on an active construction site of a 4 story concrete last in place building concrete plac
Nov 12, 2025
Resolve - Class - 2
Active construction work taking place. workers working on a supported scaffold performing exterior work while the scaffold is not completely installed. creating unsafe conditions for the workers using the scaff
Sep 27, 2025 · Penalty $2,500
Resolve - Class - 2
Active construction site. multiple workers working. few of them on the supported scaffold working. upon inspecting the supported scaffold installed on expo#2 and expo#4, 7 scaffold frames are installed making t
Sep 27, 2025 · Penalty $1,250
Resolve
Show 4 more ↓
- Class - 2
Observed an active construction site. multiple workers working. upon checking department record site was never issued a permit to work during after hours. creating unsafe liability for the workers and noisy co
Sep 27, 2025 · Penalty $1,250
Resolve - Class - 1
Failure to institute/maintain safety equipment measures or temporary construction-no guardrails. as noted at time of inspection on an activeconstruction site 4 story new building rebar working at 3rd to 4th flo
Jun 30, 2025 · Penalty $5,030
Resolve - Class - 1
Failure to institute/maintain safety equipment measures or temporary construction-no guardrails. as noted at time of inspection on an activeconstruction site 4 story new building rebar working at 3rd to 4th flo
Jun 30, 2025 · Penalty $12,500
Resolve - Class - 2
Work does not conform to approved construction documents and/or approved amendments. as noted at time of inspection 4 story new building, rebar working 3rd to 4th floor. observed at 1st floor shear wall elevato
Jun 30, 2025
Resolve
Complaints
No HPD complaints in our records
Sales history
No recorded sales in our data
Building details
- Building type
- Elevator apartment building (D7)
- Year built
- 2025
- Floors
- 4
- Residential units
- 4
- Building area
- 7,995 ft²
- Lot area
- 5,683 ft²
- Zoning
- R4-1
- Community board
- 407
- Council district
- 20
- Block / lot
- 5377 / 22
- Assessed value
- $236,250
- Landmark / historic district
- No
Questions about 147-26 Sanford Avenue
Who owns 147-26 Sanford Avenue?
The owner of record in NYC Department of City Planning PLUTO data is Js 14726 LLC.
Does 147-26 Sanford Avenue have violations?
NYC HPD has no housing violations on record for this property.
Is 147-26 Sanford Avenue rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 147-26 Sanford Avenue built?
City records list 2025 as the year it was built.
How many apartments are in 147-26 Sanford Avenue?
It has 4 residential units and 5 units in total.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.