132-53 Pople Avenue
Queens, NY 11355BBL 4-05102-0039Map
Owner of record: Snz INC.
132-53 Pople Avenue is an elevator apartment building built in 2014 in Queens, 11355. It has 8 residential units across 5 floors. The owner of record is Snz INC.. HPD has no housing violations on record for this property.
- HPD violations
- 0
- DOB violations
- 12
- ECB violations
- 21
- HPD complaints
- 0
What to know
No open immediately-hazardous violations among recent records.
HPD has not cited this building.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 0
No HPD violations on record
DOB building violations · 12
- Construction other optional
Failure to maintain building in a code compliant manner.as noted:at the time of inspection i observed missing window & roof from exposure #1.these condition can become hazardous .remedy: repair or replace all hazardous conditions
Oct 31, 2023
Dob violation - dismissed - Construction other optional
Failure to maintain building in a code compliant manner.observed bldg envelope open to the elements on exposure south elevation.remedy: repair or replace
Jun 27, 2023
Dob violation - dismissed - Construction other optional
Failure to maintain building in code compliant manner.since the last inspection was conducted building has the same condition existing missing windows ,doors and roof remedy:repair and/replace
Mar 30, 2023
Dob violation - dismissed - Construction other optional
Failure to maintain building in code compliant manner. at time of inspection building were missing windows doors and roof. remedy: repair and/or replace window roof walls per code
Sep 28, 2022
Dob violation - dismissed - Construction other optional
Emergency wor order:the following work to be done immed under continuous serv of nyspe: bracing all freestanding cmu wall on 4fl or partially demo to have cmu wall can stand w/out bracing. remove all loose & dilapiated materials & debis incl but not limited to roof protect & loose plywood. remedy:submit progress reports.file w/in 48hr
Jun 3, 2022
Dob violation - dismissed - Immediate emergency anythingoptional
Remove and erect approximately linear 135 ft of tight-board fence at exposures 1,2,3 and 4
May 13, 2022
Dob violation - dismissed - Construction other optional
During site inspection on may 12, 2022, ceu observed at the stalled construction site, there are no fall protection at all unfinished windows, doors at bldg perimeter on all floor levels. the bldg also has no fire protection detection or suppression & adequate egress remedy: construction site to be vacated fully
May 13, 2022
Dob violation - dismissed - Construction other optional
The department has issued a notice to revoke application #420788268 du e to license(s) suspension of the general contractor. all work in conn ection with this application has been ordered stopped immediately appr oximately 65% of work is completed at this time
Mar 18, 2019
Dob violation - dismissed - Construction other optional
Underpinning work done without plan. ceu was told that underpinning was done at underside of exp 2 foundation of 132-59 pople ave between 6/25/13 and 10/22/13 followed by the foundation at 132-53 pople avenue thereafter subsequent filing of underpinning plan was done on 8/30/18 remedy:verify dimension of underpinning done as per probe plan
Nov 14, 2018
Dob violation - dismissed - Construction other optional
Underpinning work done without plan:ceu was told that underpinning was done at underside of exp 4 foundation of 132-51a pople ave between 6/25/13 and 10/22/13 followed by the foundation of nb at 132-53 pople ave.thereafter subsequent filing of underpinning plan was done on 8/30/18.remedy:verify dimension of underpinning done as per probe plan
Nov 14, 2018
Dob violation - dismissed
Show 2 more ↓
- Construction other optional
Bc has issued letter of intent to revoke permit # 420788268
Feb 7, 2017
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Dec 4, 2013
Dob violation - dismissed
ECB violations · 21
- Class - 2
Job site fence not constructed or maintained pursuant to subsection. at time of inspection, observed, inadequate/no/over-height view panels at the fence's front &/or side., comply with code
Aug 24, 2023 · Penalty $500
Resolve - Class - 2
Pedestrian protection does not meet code specifications.observed exposure 2 of parapet wall of sidewalk shed is rotted parapet wall of sidewalk shed on exposure 2 is unsecured.rem:comply to code specifications.
Mar 30, 2023
Resolve - Class - 2
Pedestrian protection doesnt meet code specs.as noted atoi sws footings were damaged in several locations.(broken wood, split wood) comply w/code specs
Dec 2, 2021 · Penalty $625
Resolve - Class - 2
Pedestrian protection does not meet code specification. failure to maintain sidewalk shed. note:at time of my inspection observed sws installed at exposure 1 on walkway and was not maintain as required. the sws
May 1, 2020
Resolve - Class - 2
Temporary construction equipment on site-expired permit. sidewalk shedpermit expired. note:at time of my inspection observed sws installed at exposure w/ expired permit 2/29/2020 was not required as required. p
May 1, 2020 · Penalty $625
Resolve - Class - 2
3307.6.5 failure to maintain adequate illumination beneath sidewalk shed as required by code. noted: sidewalk shed erected under job#420861767 along exp1 has inoperable bulbs rendering affected area visibly dar
Jan 10, 2016
Resolve - Class - 2
Sec. 3307.3 no over head protection. noticed: at time of inspection nbin progress. noticed at exp 2 & 4 no overhead protection provided for front door walkways on adjoining property. remedy: stop all work and
Jan 21, 2015
Resolve - Class - 2
Job site fence not painted hunter green. at time of inspection noticedjob site fence erected no painted hunter green. remedy: paint fence huter green.
Jan 21, 2015
Resolve - Class - 2
Sec. 3309.10 no protection for balconys. noticed at time of inspectionnb in progress noticed at exp 4 adjoining property balcony not protected. remedy: stop all work & protect balconys.
Jan 21, 2015
Resolve - Class - 2
Project information panel. noticed at time of inspection nb in progress no project information panel provided. remedy: provide project information panel as per code.
Jan 21, 2015
Resolve
Show 11 more ↓
- Class - 2
Failure to post dot permit for street closing of owe lane & sidewalk obstruction. as noted: at time of inspection at an active construction site,observed at exposure #1 (pople ave) a flatbed truck under loading
Sep 11, 2013
Resolve - Class - 2
Failure to provide field storage(curring) box at construction site. asnoted: at time of inspection on an active construction site,observed at exposure #2 5 4"x8" strength (tert) cylinders stored outside on
Sep 11, 2013 · Penalty $1,600
Resolve - Class - 1
Sec. 3303.4.1 failure to maintain sidewalk free from equipment. as noted: at time of inspection on an active construction site,observed at exposure #1 pople ave a flatbed truck unloading cmu block to floor #4
Sep 11, 2013 · Penalty $1,600
Resolve - Class - 1
Failure to provide a sidewalk shed where required. as noted: at time of inspection on an active construction site,observed at exposure #1 a flat bed truck unloading cmu block hoisting over an open sidewalk onto
Sep 11, 2013 · Penalty $4,800
Resolve - Class - 2
Failure to provide approved/accepted structural plans at construction site.as noted:at time of inspection at an active construction site newbuilding is 4 stories in height and placement of cmu block and brick.
Sep 10, 2013
Resolve - Class - 2
Sec. 28-116.2.3 failure to provide an adequate inspection program tr-3. as noted: at time of inspection on an active construction site,concrete placement at floor #4 of light weight concrete at slab of balconie
Sep 10, 2013
Resolve - Class - 2
Sec. 28-104.7 submittal of construction documents. as noted: at time of inspection on an active construction site (a) observe at floor #2 to#4,exposure #1 & #3 balconies mtl railing attachment to concrete slab
Sep 10, 2013
Resolve - Class - 1
Work does not conform to approved construction documents or approved amendments. as noted: at time of inspection out on acctive constructionsite,(a) observed at floor #4,exposure #1 balconies erect w/o a moment
Sep 10, 2013 · Penalty $1,000
Resolve - Class - 1
Failure to institute/maintain safety equipment or temporary construction,no guardrails. as noted: at time of inspection on an active construction site,observed placement of cmu block & bricks at floor #3 & #4,
Sep 10, 2013 · Penalty $1,200
Resolve - Class - 1
Sec. 3309.1 failure to provide roof protection at adjoining property. as noted: at time of inspection at an active construction site,observed at floor #3 & #4,exposure #2 & #4 cmu block & brick placement. failu
Sep 10, 2013 · Penalty $1,600
Resolve - Class - 2
Bc3303.4.1 failure to maintain areas used by public - upon inspection demolition commenced,building is down, site closed, no activity at sit at time of inspection noted, approximately 10'x6'area of concrete sl
Jun 4, 2013 · Penalty $400
Resolve
Complaints
No HPD complaints in our records
Sales history
No recorded sales in our data
Building details
- Building type
- Elevator apartment building (D6)
- Year built
- 2014
- Floors
- 5
- Residential units
- 8
- Building area
- 9,011 ft²
- Lot area
- 2,500 ft²
- Zoning
- R6
- Community board
- 407
- Council district
- 20
- Block / lot
- 5102 / 39
- Assessed value
- $548,550
- Landmark / historic district
- No
Questions about 132-53 Pople Avenue
Who owns 132-53 Pople Avenue?
The owner of record in NYC Department of City Planning PLUTO data is Snz INC..
Does 132-53 Pople Avenue have violations?
NYC HPD has no housing violations on record for this property.
Is 132-53 Pople Avenue rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 132-53 Pople Avenue built?
City records list 2014 as the year it was built.
How many apartments are in 132-53 Pople Avenue?
It has 8 residential units and 9 units in total.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.