roofy

28-19 119 Street

Queens, NY 11354BBL 4-04316-0008Map

Owner of record: Ferazzoli Equities LLC

28-19 119 Street is a warehouse built in 2009 in Queens, 11354. The owner of record is Ferazzoli Equities LLC. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
3
ECB violations
13
HPD complaints
0

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 3

  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Mar 22, 2017

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Nov 16, 2016

    Dob violation - dismissed
  • Construction other optional

    No plans on site for support of excavation at 6' 2" deep below grade wall footings. no details for constuction of approximately 14 each structural columns at permeter walls (note: ftgs adjacent exposure 4 new construction are not located where detailed job#/permit #410091467 nb remedy: stop all work amend plans call 212 676-2918

    Jun 4, 2008

    Dob violation - dismissed

ECB violations · 13

  • Class - 2

    Failure to comply w/the comm's order contained in summons/vio#35197289j issued on 8-24-16 & to file a c of c pursuant to 28-201.1 & 1rcny 102-01. for work w/o a permit note: job#421418834 signed off.

    Jun 3, 2017 · Penalty $400

    Resolve
  • Class - 2

    Failure to comply w/the comm's order contained in summons/vio#35221701j issued on 12/21/16 & to file a c of c pursuant to 28-201.1 & 1rcny 102-01. note: no document file for work w/o a permit for removal of wo

    May 21, 2017 · Penalty $400

    Resolve
  • Class - 2

    Failure to comply w/the comm's order contained in summons/vio#35197289j issued on 08/24/16 & to file a c of c pursuant to 28-201.1 & 1rcny 102-01. remedy: comply w/comm's order &/or file a c of c.

    May 6, 2017 · Penalty $800

    Resolve
  • Class - 1

    Failure to comply with the commissioner's order contained in summons/violation#35197289j issued on 08/24/16 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01.for work without permit

    Apr 1, 2017 · Penalty $800

    Resolve
  • Class - 1

    Failure to comply w/the comm's order contained in summons/vio#35221701j issued on 12-21-16 & to file a c of c pursuant to 28-201.1 & 1rcny 102-01. no compliance recorded. remedy: comply w/comm's order &/or file

    Mar 22, 2017 · Penalty $2,400

    Resolve
  • Class - 1

    Work w/o permit. failure to comply w/commissioner's order contained insummons/violation #35197289j issued on 08/24/16 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01.for work noted

    Feb 2, 2017 · Penalty $2,400

    Resolve
  • Class - 1

    Work w/out a permit. noted: @ time of insp plumbing lines (gas & water) & electrical lines are being removed along w/ mezzanine level w/out a permit, said work was installed w/out a permit & is now being remove

    Dec 21, 2016 · Penalty $800

    Resolve
  • Class - 1

    Failure to comply w/ the commissioner's order contained in nov# 35197289j issued on 8/24/16 & to file a c of c pursuant to 28-201.1, 28-204.4 & 1rcny 102-01. for work w/out permit. mezzanine created w/in wareho

    Dec 7, 2016 · Penalty $2,400

    Resolve
  • Class - 1

    Work w/o permit. noted: mezzanine created w/i warehouse consisting as 2 offices,bathroom,meeting room,& storage. said space is made of combustible wood having no sprinklers on premises. remedy: obtain permit or

    Aug 24, 2016 · Penalty $1,600

    Resolve
  • Class - 1

    Failure to safeguard all persons and prop affected by const operationsnoted: debris & dust falling from top of scaffold approx 30' above grade. platform of top of platform is over loaded w/masonry units & debri

    Nov 24, 2008 · Penalty $2,400

    Resolve
Show 3 more ↓
  • Class - 2

    Failure to provide post sig at job site pursuant to subsection at ime of inspection work in progress on new bldg permitted under job 410091467 has failed to post sign that meets the requirement of bc 3301.9 &

    Oct 27, 2008

    Resolve
  • Class - 1

    Failure to safeguard all persons and prop affected by const operationsdefects noted: at time of insp no protection for adjacent property at 28-15 119st. mortar droppings are observed all over roof, garage & rea

    Oct 25, 2008 · Penalty $2,400

    Resolve
  • Non-hazardous

    27-201 failure to conform to approved plans noted work ongoing under nb permit #410091467 pouring 5 foot high concrete walls above grade at exposure 2 and 3 footing along exposure 4 existing new construction ar

    Jun 4, 2008 · Penalty $130

    Resolve

Complaints

No HPD complaints in our records

Complaint data is still being backfilled from NYC Open Data.

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Warehouse (E9)
Year built
2009
Floors
1
Residential units
—
Building area
4,000 ft²
Lot area
4,000 ft²
Zoning
M1-1
Community board
407
Council district
19
Block / lot
4316 / 8
Assessed value
$290,250
Landmark / historic district
No

Questions about 28-19 119 Street

Who owns 28-19 119 Street?

The owner of record in NYC Department of City Planning PLUTO data is Ferazzoli Equities LLC.

Does 28-19 119 Street have violations?

NYC HPD has no housing violations on record for this property.

Is 28-19 119 Street rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 28-19 119 Street built?

City records list 2009 as the year it was built.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.