roofy

102-09 44 Avenue

Queens, NY 11368BBL 4-01978-0049Map

Owner of record: Wong's Sons Realty In

102-09 44 Avenue is a warehouse built in 1931 in Queens, 11368. The owner of record is Wong's Sons Realty In. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
139
ECB violations
39
HPD complaints
0

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 139

  • High pressure boiler boiler required

    Violation issued-failure to file 2024 internal hgh pressure inspection

    Nov 14, 2025

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2024 internal hgh pressure inspection

    Nov 14, 2025

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2024 internal hgh pressure inspection

    Nov 14, 2025

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2024 internal hgh pressure inspection

    Nov 14, 2025

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2024 internal hgh pressure inspection

    Nov 14, 2025

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2024 internal hgh pressure inspection

    Nov 14, 2025

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2024 external hgh pressure inspection

    Nov 14, 2025

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2024 external hgh pressure inspection

    Nov 14, 2025

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2024 external hgh pressure inspection

    Nov 14, 2025

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2024 external hgh pressure inspection

    Nov 14, 2025

    Dob violation - active
Show 40 more ↓
  • High pressure boiler boiler required

    Violation issued-failure to file 2024 external hgh pressure inspection

    Nov 14, 2025

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2024 external hgh pressure inspection

    Nov 14, 2025

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2023 internal hgh pressure inspection

    Sep 23, 2024

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2023 internal hgh pressure inspection

    Sep 23, 2024

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2023 internal hgh pressure inspection

    Sep 23, 2024

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2023 internal hgh pressure inspection

    Sep 23, 2024

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2023 internal hgh pressure inspection

    Sep 23, 2024

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2023 internal hgh pressure inspection

    Sep 23, 2024

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2023 external hgh pressure inspection

    Sep 23, 2024

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2023 external hgh pressure inspection

    Sep 23, 2024

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2023 external hgh pressure inspection

    Sep 23, 2024

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2023 external hgh pressure inspection

    Sep 23, 2024

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2023 external hgh pressure inspection

    Sep 23, 2024

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2023 external hgh pressure inspection

    Sep 23, 2024

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2021 internal hgh pressure inspection

    Jun 30, 2023

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2020 external hgh pressure inspection

    Jun 30, 2023

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2021 internal hgh pressure inspection

    Jun 30, 2023

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2021 internal hgh pressure inspection

    Jun 30, 2023

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2021 internal hgh pressure inspection

    Jun 30, 2023

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2021 internal hgh pressure inspection

    Jun 30, 2023

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2021 external hgh pressure inspection

    Jun 30, 2023

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2021 external hgh pressure inspection

    Jun 30, 2023

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2021 external hgh pressure inspection

    Jun 30, 2023

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2021 external hgh pressure inspection

    Jun 30, 2023

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2021 external hgh pressure inspection

    Jun 30, 2023

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2020 internal hgh pressure inspection

    Jun 30, 2023

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2020 internal hgh pressure inspection

    Jun 30, 2023

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2020 internal hgh pressure inspection

    Jun 30, 2023

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2020 internal hgh pressure inspection

    Jun 30, 2023

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2020 internal hgh pressure inspection

    Jun 30, 2023

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2020 internal hgh pressure inspection

    Jun 30, 2023

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2020 external hgh pressure inspection

    Jun 30, 2023

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2020 external hgh pressure inspection

    Jun 30, 2023

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2021 external hgh pressure inspection

    Jun 30, 2023

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2020 external hgh pressure inspection

    Jun 30, 2023

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2020 external hgh pressure inspection

    Jun 30, 2023

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2020 external hgh pressure inspection

    Jun 30, 2023

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2021 internal hgh pressure inspection

    Jun 30, 2023

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2018 external hgh pressure inspection

    Jun 20, 2023

    Dob violation - active
  • High pressure boiler boiler required

    Violation issued-failure to file 2018 internal hgh pressure inspection

    Jun 20, 2023

    Dob violation - active

ECB violations · 39

  • Class - 2

    Failure to maintain building in walls or appurtenances. noted; at front wall visible step cracks on brick facade, missing bricks on wall., maintain exterior building wall

    Apr 18, 2023 · Penalty $1,250

    Resolve
  • Class - 1

    B154,51,18a,b,24b,48b. fulton high pressure gas fired boiler nb 49695built 1986; 51-high level of carbon monoxide from upper hand hole sleave cause by corrosion.replace sleeve around hand hole. boiler seal

    May 31, 2017 · Penalty $1,030

    Resolve
  • Class - 2

    Failure to maintain bldg walls. note: brick work & large steel lintel displaced w/o adequate support/mortar at front facade above right side rool up door. (at ground floor level). remedy: maintain bldg wall.

    May 29, 2010

    Resolve
  • Class - 2

    18a,18b.

    May 11, 2010 · Penalty $250

    Resolve
  • Class - 1

    Failure to maintain. noted : sweat shop in warehouse bldg. 2nd fl w/o sprinkler which req'd by labor law. ( automatic dry sprinkler 512 of rs-1 ( 27-954(g)) textiles. combustible material. remedy: install dry

    Dec 7, 2009 · Penalty $1,000

    Active
  • Class - 2

    Occupancy contrary to that allowed by the bldg dept. records noted: sweat shop in 2nd fl warehouse bldg. bldg record show warehouse textilesindustrial occupancy bldg - group 0 - 1 when req'd by labor law ( auto

    Dec 7, 2009 · Penalty $1,200

    Active
  • Class - 1

    Work w/o a permit. noted: a wood structure was created approx 20ft wide by 30ft long & 8ft high with 1 door,1 window & staircase,creating anadditional flr/flr space. door was locked at time of inspection & entr

    Sep 3, 2009 · Penalty $1,600

    Resolve
  • Non-hazardous

    B4a/18a/32a/32b/44a/48a/48b/50a/50b/50c/50d/50e/50f/.50a-boiler room fire door defective.50b-remove threads from safety or relief valve discharge pipe at end.50c-slow opening valve missing on boiler blowdown

    May 8, 2007 · Penalty $2,500

    Resolve
  • Non-hazardous

    B4a,18a,48a,48b,50a.50a-holes on the boiler room walls.

    May 1, 2007 · Penalty $2,500

    Active
  • Non-hazardous

    50a/50b fuction v.t. boiler,10hp,nb60392,gds,1990 50 @ no discharge pipe on the safety valve.50b improper arrangement of the blowdown valves.install a screw-type slow valve at the outlet end of the blowdown lin

    Jul 26, 2005 · Penalty $350

    Active
Show 29 more ↓
  • Hazardous

    Required 2nd means of egress from all floors. door totally obstructed by lock roll down gate. more than 30 sewing machine operators @ 1st floor and same at 3rd floor. remedy: remove obstruction immediately.

    May 30, 2002 · Penalty $2,500

    Resolve
  • Hazardous

    Occupancy contrary to that allowed by the bldg dept. records. alteration type i #401066163 from warehouse 1st, 2nd, 3rd flrs. to illegal sewing and textile factory. @ 1st and 3rd fl with 2nd means of egress blo

    May 30, 2002 · Penalty $2,500

    Resolve
  • Non-hazardous

    36/ 49

    Aug 7, 2001 · Penalty $350

    Resolve
  • Non-hazardous

    49. water column drain reduced boiler id fulton nb698754r94 .

    Mar 7, 2001 · Penalty $180

    Resolve
  • Non-hazardous

    16,49.water column drain reduced.2.proof of registeration(900-a)to this boiler fulton 33055 year 1984 to submit 3. low water eat-out manual reset switch in the panel not conected.4.proof of internal inspection

    Mar 7, 2001 · Penalty $2,500

    Resolve
  • Non-hazardous

    49 (49)no check valve/backflow preventer

    Nov 24, 2000

    Resolve
  • Hazardous

    Exit door total obstruction. boxes and garments on stairs all floors. all exit floors. all exit doors are not self closing all floors. panichardware inoperative all floors fire stair located at rear south of bu

    Feb 1, 2000 · Penalty $2,500

    Resolve
  • Non-hazardous

    Occupancy contrary to that allowed by the building department records.from a legal e/9 ware house to an illegal cellar for wood working first and second and third floors. garment manufactoring companies. remedy

    Feb 1, 2000 · Penalty $2,500

    Resolve
  • Non-hazardous

    No fire alarm system -basement wood working shop. 2nd floor -clothing manufacture. 3rd floor -clothing manufacture. -all floors occupied. remedy: vacate premises forthwith. conform to building codes regarding

    Jan 27, 2000 · Penalty $400

    Resolve
  • Non-hazardous

    36- boiler not registered. 49- bq9- installed boiler without pernits and operated boiler without equipment use permit

    Dec 23, 1999 · Penalty $2,500

    Resolve
  • Non-hazardous

    Occupancy contrary to that allowed by the building department records:legal warehouse bldg occupied illegaly on 2nd floor clothing manufacture co and in cellar wood working shop for wood cabinet.

    Aug 16, 1999 · Penalty $10,000

    Resolve
  • Non-hazardous

    36,49. installed boiler without permits. inspection card invalid as that was issued to fulton boiler number 46933 year 85 this fulton boilerhas natl bd number 49695 and year built is 1986.

    May 17, 1999 · Penalty $350

    Resolve
  • Non-hazardous

    36

    Mar 18, 1999 · Penalty $2,500

    Resolve
  • Non-hazardous

    36. (bq9)(27-147) boiler installed with out work permit.

    Dec 22, 1998 · Penalty $400

    Resolve
  • Non-hazardous

    36 (bq9) (27-147) boiler installed with out work permit.

    Dec 22, 1998 · Penalty $400

    Resolve
  • Non-hazardous

    49,16, 49-other:boiler room ceiling falling apart and not fined resistance. 16-boiler number/inspeftion card not displayed

    Dec 22, 1998 · Penalty $400

    Resolve
  • Non-hazardous

    49.boiler design pressure is loops existing saftey valve is set for 125 pcs.the later be replaced by new one set maximun upto 100 pcs.only (2) d&side of thr blr not accessible for inspection.

    Jan 23, 1995 · Penalty $400

    Resolve
  • Non-hazardous

    Occupancy contrary to that allowed by the building departments records no c of o for garment factory remedy obtain a calid c of o

    Feb 2, 1993

    Resolve
  • Non-hazardous

    Occupancy contrary to building department records. no c of o for garment factory. remedy: obtain a valid c of o

    Apr 29, 1992

    Resolve
  • Non-hazardous

    Occupancy contrary to building department records no c of o for factory in basement of building. remedy: obtain a valid c of o

    Apr 29, 1992

    Resolve
  • Non-hazardous

    32; design pressure of the boiler is 100 ps the esxisting safety valveis set for 125 ps1 the later to be replaced by new one set maximunm at 100 psi

    Sep 10, 1991 · Penalty $200

    Resolve
  • Non-hazardous

    17b;32; hand hole sleeves correded glass escaping in the boiler area. large glass to be fitted with stop valve and drain pipe 2nd slow valve to fit in water column drain pipe.

    Sep 10, 1991

    Resolve
  • Non-hazardous

    Exit door total obstruction in rear at factory exit door blocked with 2 by 4 and studs also debris and metal piping. completly sealed no paric hardware where required by law on exit door. dead bott.

    Jul 10, 1991

    Resolve
  • Non-hazardous

    18b,32,32 - install low water cut-off on h/w/s

    Jun 6, 1991 · Penalty $250

    Resolve
  • Hazardous

    Exit door total obstruction. no panic hardware where required by law.

    Dec 7, 1989 · Penalty $1,000

    Resolve
  • Hazardous

    Exit door total obstructionin rear of factory exit door blocked with 2 by 4 wood studs also chairs and metal piping completely sealed. no panic hardwre where reqired by law.

    Dec 7, 1989 · Penalty $1,000

    Resolve
  • Non-hazardous

    Occuapancy contrary to building dept records. no c of o for factory in basement in basement of buidling. remedy: obtain a valid c of o.

    Dec 6, 1989 · Penalty $285

    Resolve
  • Non-hazardous

    Occupancy contray to building dept records. remedy: obtai anew c of o.

    Dec 6, 1989 · Penalty $1,000

    Resolve
  • Non-hazardous

    Exit passageway on corridow, required width decreased by obstruction. remedy: remove obstructions forthwith.

    Aug 31, 1988

    Resolve

Complaints

No HPD complaints in our records

Complaint data is still being backfilled from NYC Open Data.

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Warehouse (E1)
Year built
1931
Floors
3
Residential units
—
Building area
18,520 ft²
Lot area
11,360 ft²
Zoning
M1-1
Community board
404
Council district
21
Block / lot
1978 / 49
Assessed value
$878,400
Landmark / historic district
No

Questions about 102-09 44 Avenue

Who owns 102-09 44 Avenue?

The owner of record in NYC Department of City Planning PLUTO data is Wong's Sons Realty In.

Does 102-09 44 Avenue have violations?

NYC HPD has no housing violations on record for this property.

Is 102-09 44 Avenue rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 102-09 44 Avenue built?

City records list 1931 as the year it was built.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.