53-20 90 Street is a walk-up apartment building built in 2022 in Queens, 11373. It has 7 residential units across 4 floors. The owner of record is 53-20 90th Street Realty, LLC. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
0
ECB violations
21
HPD complaints
0

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 0

No DOB violations on record

ECB violations · 21

  • Class - 2

    Failure to comply with department of buildings requirement for permit sign off. respondent obtained nb permit # 440609986 which expired on 08/28/2023. permit has not been signed off within one year following it

    May 13, 2024

    Resolve
  • Class - 2

    At time of my inspection on a active jobsite of a 4 story nb,observed that housekeeping throughout the entire site were inadequate,mix material and debris creating a trip and fall hazard for workers and persona

    Apr 18, 2023

    Resolve
  • Class - 2

    At time of my inspection on active jobsite of a 4 story nb ,observed numerous areas with unsafe extension cables and damage electric. tools.this condition is very dangerous for workers to get injured or killed

    Apr 18, 2023

    Resolve
  • Class - 2

    At time of inspection on an active 4 story nb jobsite i observed fire extinguishers on site not maintained to code. inspection tags blank or missing monthly inspection on numerous fire extinguishers. maintain/i

    Apr 18, 2023

    Resolve
  • Class - 2

    At time of inspection 4 story new building open active site observed masonary work in progress on top fl. upon furter i observed pile of cmu block,bricks construction materials ,debris all over fl and jobsite c

    Mar 9, 2023

    Resolve
  • Class - 2

    At time of inspection 4 story new building open active site observed masonary work in progress on top fl and ohp installed at exp 2 and b> corner. upon request to see design drawing none was provide by competen

    Mar 9, 2023

    Resolve
  • Class - 2

    At time of inspection 4 story new building open active site observed masonary work in progress on top fl. upon review on ssp determine that no ohp at exposure 3. creating hazardous condition for workers.pswo is

    Mar 9, 2023

    Resolve
  • Class - 2

    Bc 3301.2 failure to provide safety measures and standards-(no guardrail and without fall arrest harness).as noted:at time of inspection on an active construction site,4 story new building at floor#4 level.obse

    Feb 13, 2023

    Resolve
  • Class - 2

    & 28-105.12.2 at the time of inspection observed 4 story building under construction (saturday 01/7/2023), researching dob now and bis it was noticed that after-hours permit q8971692 was only for pouring concre

    Jan 7, 2023 · Penalty $625

    Resolve
  • Class - 1

    Cmu and brickwork above the second floor are in progress. reviewing the plans and inspecting the site, it is noticed the overhead protection is missing at the perimeter of the building. ssp calls for ohp and ca

    Jan 7, 2023 · Penalty $625

    Resolve
Show 11 more ↓
  • Class - 2

    4-story building under construction, cmu work was in progress reviewing the sidewalk shed plan and field condition it was noticed that the field condition is contrary to approved plans. approved plans (sections

    Jan 7, 2023

    Resolve
  • Class - 2

    At the time of inspection, active concrete work on the 2nd floor was in progress observed concrete sediment and truck washed out into the street and sidewalk, eventually flowing to the public sewerage system, a

    Nov 19, 2022 · Penalty $2,500

    Resolve
  • Class - 2

    Construction superintendent failed to perform duties per code.concrete our in progress after-hours permit q00530763-s1-st for 11/19/22 specifies concrete operation but super failed to print that activity on log

    Nov 19, 2022

    Resolve
  • Class - 2

    Concrete pour in progress, after-hours permit q00530763-s1-st for 11/19/2022 specifies concrete operation but super failed to print that activity on the log. as the super knew they don't have a dot permit to oc

    Nov 19, 2022

    Resolve
  • Class - 1

    Active construction site observed concrete operation at the site, reviewing the site safety plans following conditions were noticed 1) no barricade for the concrete pump and concrete truck. 2) concrete pipe on

    Nov 19, 2022

    Resolve
  • Class - 2

    Active construction site observed concrete operation at the site when asked for a dot permit (bc 3307.2.1) to occupy the sidewalk, and the street competent person was not able to produce it at the time of inspe

    Nov 19, 2022

    Resolve
  • Class - 2

    Jobsite fence not constructed or maintained pursuant to subsection.observed grafitti throughout exposure#1 & 2 and missing panel at exp# 4.rem:comply with code maintain jobsite fence as per code.

    Jul 8, 2022 · Penalty $500

    Resolve
  • Class - 1

    Housekeeping.note:at time of my inspection observed active jobsite inadequate housekeeping has been found.a large amount of construction debris combustible materials storage at 2nd floor level approx more than

    Mar 1, 2021 · Penalty $625

    Resolve
  • Class - 1

    Failure to provide sidewalk shed where required.note:at time of my inspection observed active jobsite.the sidewalk shed not provided as required.the building under full demolitions the drawing approved show sid

    Mar 1, 2021 · Penalty $2,500

    Resolve
  • Class - 1

    3306.9.8.3 failure to provide prior to the commencement of demolition operations-all glass.note:at time of my inspection observed active jobsite the building under demolition workers demolished top floors and o

    Mar 1, 2021 · Penalty $2,500

    Resolve
  • Class - 1

    Failure to institute/maintain safety equipment measures or temporary construction-no guardrails.note:at time of my inspection observed active jobsite.i observed 2nd floor roof level top workers working weather

    Mar 1, 2021 · Penalty $2,500

    Resolve

Complaints

No HPD complaints in our records

Complaint data is still being backfilled from NYC Open Data.

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Walk-up apartment building (C1)
Year built
2022
Floors
4
Residential units
7
Building area
5,086 ft²
Lot area
2,502 ft²
Zoning
R6B
Community board
404
Council district
25
Block / lot
1839 / 34
Assessed value
$335,250
Landmark / historic district
No

Questions about 53-20 90 Street

Who owns 53-20 90 Street?

The owner of record in NYC Department of City Planning PLUTO data is 53-20 90th Street Realty, LLC.

Does 53-20 90 Street have violations?

NYC HPD has no housing violations on record for this property.

Is 53-20 90 Street rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 53-20 90 Street built?

City records list 2022 as the year it was built.

How many apartments are in 53-20 90 Street?

It has 7 residential units.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.