41-12 77 Street
Queens, NY 11373BBL 4-01496-0013Map
Owner of record: Green Manor Of Usa, LLC
41-12 77 Street is an office building built in 2019 in Queens, 11373. The owner of record is Green Manor Of Usa, LLC. HPD has recorded 6 housing violations here, most recently on October 23, 2018.
- HPD violations
- 6
- DOB violations
- 4
- ECB violations
- 24
- HPD complaints
- 8
What to know
No open immediately-hazardous violations among recent records.
Date of the most recent HPD inspection that found a problem.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 6
- IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Oct 23, 2018
Closed — Violation closed - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Dec 4, 2017
Closed — Violation closed - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Nov 18, 2016
Closed — Violation closed - CImmediately hazardous
M/d law abate the nuisance consisting of key operated lock installed at door leading to fire escape window. in the 2nd room from east at north located at apt 3, 3rd story, 1st apartment from east at south
Feb 27, 2015 · Apt 3
Closed — Violation closed - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Feb 26, 2015
Closed — Violation dismissed - BHazardous
Abate the nuisance consisting of bedbugs in the entire apartment located at apt 2f, 2nd story, 1st apartment from east at south
Jul 6, 2014 · Apt 2F
Closed — Violation closed
DOB building violations · 4
- Construction other optional
C-construction other optional
Feb 10, 2020
Vp*-violation unserved ecb- dismissed - Construction other optional
C-construction other optional
Feb 10, 2020
Vp*-violation unserved ecb- dismissed - Construction other optional
C-construction other optional
Oct 16, 2018
Vpw*-violation unserved ecb-work without permit-dismissed - Construction other optional
C-construction other optional
Feb 24, 2010
Dob violation - dismissed
ECB violations · 24
- Class - 2
Jobsite fence not constructed or maintained pursuant to subsection.at the time of inspection,this was a 4 story building.construction site was closed and there was no exterior work observed as per perimeter ins
Jul 19, 2021 · Penalty $1,030
Resolve - Class - 2
Bc 3303.7.2 fire extinguishers shall be provided in accordance with new york city fire code.at the time of my inspection of an active nb project i observed portable fire fighting equipment(fire extinguishers)un
Sep 30, 2020 · Penalty $1,250
Resolve - Class - 2
Failure to maintain adequate housekeeping per section requirements.at the time of my inspection of an active nb project i observed a lack offloor numbering and the accumulation of bagged and loose debris garbag
Sep 30, 2020 · Penalty $1,250
Resolve - Class - 2
Bc 3301.13.12 construction superintendent failed to designate a competent person and ensure such person is present at the designated site atall times active work occurs.at the time of my inspection of an active
Sep 30, 2020 · Penalty $1,250
Resolve - Class - 2
At time of inspection,observed ongoing construction activities contrary to mayor's emergency executive order 120 & subsequent orders incorporating requirements of governors executive order 202.34 & subsequent
Aug 5, 2020 · Penalty $5,000
Resolve - Class - 1
Contractor failed to ensure that each construction or demolition worker working/engaged at the site successfully completed the required training under bc #3321.1. at time of inspection on an active 4 story nb c
Mar 10, 2020
Resolve - Class - 1
Competent person.at time of inspection of an active jobsite w/approx 8 workers on site,i requested from several workers throughout building it the construction super or the designated comp person was present on
Feb 10, 2020 · Penalty $10,000
Resolve - Class - 1
Bc3301.6 design drawings.at the time of inspection i observed a make shift pully system at the fourth floor terrace,the system consisted of rotted 2"x4" wood material and a seriously frayed rope.upon requesting
Feb 10, 2020 · Penalty $2,500
Resolve - Class - 1
Bc3314.4.8 scaffold maintenance.at time of inspection of an active jobsite i observed a supported scaffold installed at exposure 3.scaffold's debris netting was loose and unsecured(3314.8.2)and planks were not
Feb 10, 2020 · Penalty $2,500
Resolve - Class - 2
Pedestrian protection does not meet code specification-sidewalk shed light. note: at time of my inspection of a 4 sty bldg at roof level under construction work in progress. i observed that the sidewalk shed in
Dec 6, 2019 · Penalty $5,000
Resolve
Show 14 more ↓
- Class - 2
Pedestrian protection oes not meet code specification #3307.6.4.8: note at the time of my inspection i observed a sidewalk shed erected at exposure on eand all light bulbs are not operating during inspection at
Jul 24, 2019 · Penalty $2,400
Resolve - Class - 2
Bc3309.10 failure to protect adjoining properties (missing roof pro tection). at time of inspection i observed nb 4 stories a roof level framing structures completed both wall at exp2,4 extends vertically
Jul 17, 2019 · Penalty $625
Resolve - Class - 2
Bc3301.2 failure to safeguard (no overhead protection) at time of inspection, i observed nb framing structures at roof level 4 stories high with bulkhead the driveway at exp4 is active and missing overhead
Jul 17, 2019 · Penalty $625
Resolve - Class - 2
Failure to provide approved/accepted construction documetns at jobsiteat time of inspection (no soe plans for retaining wall) at time of in spection i observed lagging and wood piles (2x10) installed at exp2
Jul 17, 2019
Resolve - Class - 2
Fence maintenance/expired fence permit. at time of inspection i observed the jobsite fence caving inward and not plumb,plexiglass was shattered and viewing port was not covered. also,as per bis+dob now,fence pe
Apr 19, 2019
Resolve - Class - 1
Bc3301.13.1.site safety plan.at time of inspection on a proposed 4 story bldg at foundation phase requested to view site safety plan and wasinformed that there was none.for jobs that require the destination of
Mar 26, 2019 · Penalty $2,500
Resolve - Class - 2
Work does not conform to approved construction documents and or amendments.at time of inspection on a proposed 4-story building at foundation phase observed soldier piles at exposure #2 and #4.upon review of so
Mar 26, 2019
Resolve - Class - 2
3304.7 required means of egress-missing/inadequate egress. at time of inspection on site w/ gc and subcontractor,observed that there were noadequate means of egress from foundation level to grade level being ma
Mar 11, 2019 · Penalty $625
Resolve - Class - 2
Fence not constructed to code. at time of inspection w/ gc and subcontractor on site,observed construction fence out of plumb and leading into site and out of site. fence made of random 2x4 and seem to be unsta
Mar 11, 2019 · Penalty $400
Resolve - Class - 1
Failure to maintain safety operation-inadequate guardrails. observed at time of inspection w/ gc and subcontractor on site,inadequate installed guardrails at exp#1. guardrail at exp#1 consist of random place
Mar 11, 2019 · Penalty $2,500
Resolve - Class - 2
Work w/o permit.work noted:@ front of premises enclosed entire front porch.enclosure has(12)windows 7 (1)entry door with side lights & approx.6'x3' canopy with columns.bases of columns not adequate supported.ex
May 10, 2014 · Penalty $800
Resolve - Hazardous
Work without permits. work noted: at cellar erected partitions creating 3 rooms and a bathroom, installed water and waste lines for a 3pc bathroom (tub) and a residential sink. also installed a gas line for a s
Nov 28, 2003
Resolve - Hazardous
Failure to provide two means of egress at cellar, no second means of egress one entrance at rear of premises. remedy: provide 2 means of egress if feasible
Nov 28, 2003 · Penalty $480
Resolve - Hazardous
Residence altered for occupancy as a dwelling for more than the legally approved # of families building dept records which indicate residence legally approved for 2 families and a store. residence now occupied
Nov 27, 2003 · Penalty $3,050
Resolve
Complaints
- Heat/hot water
Entire building
Feb 26, 2017 · Apt BLDG
Close - Heat/hot water
Entire building
Dec 7, 2016 · Apt 2
Close - Heat/hot water
Entire building
Feb 23, 2015 · Apt 3
Close - Unsanitary condition
Pests
Jun 30, 2014 · Apt 2F
Close - Electric
No lighting
Jun 21, 2014 · Apt 1FL
Close - Door/window
Door
Jun 21, 2014 · Apt 1FL
Close - General
Ventilation system
Jun 21, 2014 · Apt 1FL
Close - Unsanitary condition
Garbage/recycling storage
May 8, 2014 · Apt PH
Close
Sales history
No recorded sales in our data
Building details
- Building type
- Office building (O7)
- Year built
- 2019
- Floors
- 4
- Residential units
- —
- Building area
- 10,429 ft²
- Lot area
- 4,000 ft²
- Zoning
- R6B
- Community board
- 404
- Council district
- 25
- Block / lot
- 1496 / 13
- Assessed value
- $967,500
- Landmark / historic district
- No
HPD registration #406388, last renewed Jul 29, 2015.
Questions about 41-12 77 Street
Who owns 41-12 77 Street?
The owner of record in NYC Department of City Planning PLUTO data is Green Manor Of Usa, LLC.
Does 41-12 77 Street have violations?
Yes. NYC HPD has recorded 6 housing violations at this property.
Is 41-12 77 Street rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 41-12 77 Street built?
City records list 2019 as the year it was built.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.