38-09 28 Street
Queens, NY 11101BBL 4-00385-0009Map
Owner of record: Realty 38 LLC
38-09 28 Street is an elevator apartment building built in 2023 in Queens, 11101. It has 50 residential units across 7 floors. The owner of record is Realty 38 LLC. HPD has recorded 3 housing violations here, most recently on October 31, 2019.
- HPD violations
- 3
- DOB violations
- 8
- ECB violations
- 17
- HPD complaints
- 0
What to know
No open immediately-hazardous violations among recent records.
Date of the most recent HPD inspection that found a problem.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 3
- IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Oct 31, 2019
Closed — Violation closed - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Oct 22, 2018
Closed — Violation closed - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Nov 16, 2016
Closed — Violation dismissed
DOB building violations · 8
- Failure to benchmark none
Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4
May 2, 2024
Dob violation - dismissed - Construction other optional
Submittal of construction documents.provide mean and method by bor for repair
Oct 27, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2020 external low pressure inspection
Jun 30, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2021 external low pressure inspection
Jun 30, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2019 external low pressure inspection
Jun 20, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2022 external low pressure inspection
Apr 25, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2010 inspection report
Dec 13, 2011
Dob violation - dismissed - Construction other optional
C-construction other optional
May 25, 1994
Dob violation - dismissed
ECB violations · 17
- Class - 2
Failure to file required annual boiler inspection reports for low-pressure boiler 40000160674n0001 in accordance with rules of the department. 1rcny 103-01(d)(1) requires that an annual inspection report for lo
Sep 27, 2024
Resolve - Class - 2
Protection of adj prop- bc 3309.1. obsvd 2fl setback with unfinished parapet wall, with the exp#2 adj prop (38-10 29th st) yard & stairs below not protected as reqd. also obsvd netting protn on the exp#2 adj pr
Dec 26, 2023 · Penalty $625
Resolve - Class - 2
Bc 3307.4.7- work or storage zones. obsvd a storage zone in the roadway at exp#1 with 7 pallets of brick stored & a storage zone in the roadway at exp#6 (l-shaped bldg) with a debris container placed within it.
Dec 26, 2023 · Penalty $2,500
Resolve - Class - 2
Obsvd sup scaf at exp#1 with exp#1 footing at sws/2ft frame connection placed on additional beam placed parallel to sws (not on dwg). exp#3,4 frames spaced far apart bc of balconies, with decks extending betwee
Dec 26, 2023 · Penalty $625
Resolve - Class - 1
Bc 3305.3.6.1.2 failure to secure re-shores in proximity to unenclosed perimeters as noted: at time of inspection on an active construction site of a proposed 7 story building concrete cast-in-place new buildin
Nov 9, 2023
Resolve - Class - 1
Failure to institute/maintain safety equipment measures or temporary construction and guardrails. as noted: at time of inspection at an active jobsite for a proposed 7 story building observed at the rooftop lev
Nov 9, 2023 · Penalty $5,000
Resolve - Class - 2
Bc 3301.7 failure to provide means and method by p.e for concrete repair. as noted: at time of inspection at an active jobsite for a proposed 7 story building concrete cast-in-place already at the rooftop level
Nov 9, 2023
Resolve - Class - 2
Condition of new buildings permit.as noted:at time of inspection on active construction site observed under new building permit #421133883 doc 1 line #13 building characteristics primary structural system liste
Sep 22, 2023
Resolve - Class - 1
Failure to provide masonry cmu block wall construction bracing accodance with tms 602/4ci 530.1/ asce6 section.as noted at time of inspection on active job site observed cmu work on 1st fl equire for bracing dr
Sep 22, 2023 · Penalty $625
Resolve - Class - 2
I observed work contrary to the site safety plan. as per ssp a 4 foot fence with wire mesh on top should be installed along the shed in compliance with bc 3307.4.7 as well as a fully enclosed storage/work zone
Sep 11, 2023
Resolve
Show 7 more ↓
- Class - 2
Upon inspection of an active construction site i observed a sidewalk shed installed at exposure 1&4 contrary to approved drawings. missing double cross brace bays (installed single only) missing approx. 4ft hi
Sep 11, 2023
Resolve - Class - 2
At time of inspection for class1 vio#39517356x , unable to verify correction of violating condition, upon reviewing department records no certificate of correction on file associated with the above mentioned su
Jul 27, 2023 · Penalty $625
Resolve - Class - 1
Observed workers performing concrete operations, upon review the preshift meeting, observed pre-shift meeting did not indicate any topics for concrete operations or risks associated and safety concerns with th
Jun 2, 2023
Resolve - Class - 2
Observed workers pouring concrete with concrete pump over public sidewalk with no protection for pedestrian, sidewalk is closed with barriers with no warning signs, or watch persons(flag persons) to prevent pub
Jun 2, 2023 · Penalty $2,400
Resolve - Class - 2
3301.2 failure to provide safety measures.at the time of my inspectionto respond a complaint observed demolition completed,debris all over the site.observed at expos#3 with adj building provided ohp and fence,
Sep 28, 2019
Resolve - Class - 3
15,50,50a-c.(50)seal around oil burner blast tube to boiler chamber.(50a)reseal front boiler chamber door w/ new gasket.(50b)water feed line fed directly into boiler,must pipe into the return line.(50c)missing
Jun 30, 2010 · Penalty $500
Resolve - Hazardous
Exit passage total obstruction. fire exit passage way on 38-09 28st property for use in fire emergency for 38-10 29 st is blocked by roofin g material and equipment (ladders) remedy: remove all obstructions.
May 9, 1994 · Penalty $475
Resolve
Complaints
No HPD complaints in our records
Sales history
No recorded sales in our data
Building details
- Building type
- Elevator apartment building (D7)
- Year built
- 2023
- Floors
- 7
- Residential units
- 50
- Building area
- 75,772 ft²
- Lot area
- 13,250 ft²
- Zoning
- M1-2/R6A
- Community board
- 401
- Council district
- 26
- Block / lot
- 385 / 9
- Assessed value
- $8,946,000
- Landmark / historic district
- No
HPD registration #434574, last renewed Sep 26, 2025.
Questions about 38-09 28 Street
Who owns 38-09 28 Street?
The owner of record in NYC Department of City Planning PLUTO data is Realty 38 LLC.
Does 38-09 28 Street have violations?
Yes. NYC HPD has recorded 3 housing violations at this property.
Is 38-09 28 Street rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 38-09 28 Street built?
City records list 2023 as the year it was built.
How many apartments are in 38-09 28 Street?
It has 50 residential units and 51 units in total.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.