33-10 38 Avenue

Queens, NY 11101BBL 4-00380-0007Map

Owner of record: 38th Ave Dev LLC

33-10 38 Avenue is an elevator apartment building built in 2024 in Queens, 11101. It has 10 residential units across 7 floors. The owner of record is 38th Ave Dev LLC. HPD has recorded 17 housing violations here, most recently on May 6, 2026. 14 of the 17 most recent violations are still open.

HPD violations
17
DOB violations
1
ECB violations
13
HPD complaints
9

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
Last violation May 6, 2026

Date of the most recent HPD inspection that found a problem.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 17

  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    May 6, 2026

    Open — Nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 21, 2025

    Open — Info nov sent out
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Jun 11, 2025

    Open — Nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 29, 2024

    Open — Info nov sent out
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Apr 12, 2024

    Open — Nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 22, 2023

    Open — Info nov sent out
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Mar 27, 2023

    Open — Nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 15, 2022

    Open — Info nov sent out
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Mar 3, 2022

    Open — Nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Mar 3, 2022

    Open — Info nov sent out
Show 7 more ↓
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Apr 14, 2021

    Open — Nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Apr 14, 2021

    Open — Info nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 1, 2019

    Open — Info nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Oct 22, 2018

    Open — Info nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 17, 2016

    Closed — Violation dismissed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Oct 15, 2015

    Closed — Violation dismissed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Feb 25, 2015

    Closed — Violation dismissed

DOB building violations · 1

  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    May 30, 2012

    Dob violation - dismissed

ECB violations · 13

  • Class - 2

    Observed inadequate storage zone on roadway with yoddock barriers not being filled with water or sand and not being interconnected. yoddock barriers need to filled and interconnected to be able to provide prote

    May 20, 2026 · Penalty $625

    Resolve
  • Class - 2

    Upon arrival of a safety compliance stop , i observed , the construction fence ,shed , & scaffolding are in place at expo 's #1 & 3,however there is an inadequate wire protection issue at expo# 1 , the wir

    Feb 13, 2026 · Penalty $2,530

    Resolve
  • Class - 2

    No en drawing approved from dob provided on the job site at the time of inspection., maintain/display required documents; please go to https://www1.nyc.gov/site/buildings/codes/energy-conservation-code.page and

    Jun 27, 2025

    Resolve
  • Class - 2

    Does not meet code specifications stipulates protection shall extend 20 feet from lead edge of building,only 13 feet of roof protection provided of jobsite with needle beams and scaffold above roof exp2,4.hazar

    May 8, 2025 · Penalty $2,500

    Resolve
  • Class - 2

    New 7 story building .observed: active site & permits cs present upon request for amended needle beam drawings none was provided stop al work on exposure 2,4 exterior and 10 feet away interior on floors 4,5,6,7

    Mar 6, 2025 · Penalty $1,250

    Resolve
  • Class - 1

    Observed inadequate housekeeping and inadequate storage of combustible material throughout site while site was under an active department-issued weather advisory

    Mar 6, 2025 · Penalty $2,500

    Resolve
  • Class - 2

    New 7 story mix use building ,observed supported scaffold erected on exposure 1 over sws installed stair tower upon request for load imposed letter none was provided contrary to bc 3314.3.4 and 3314.3.4.1 and

    Mar 6, 2025 · Penalty $2,500

    Resolve
  • Class - 2

    Proposed 7 story mix use building .observe active site, cs present upon inspection was noted supported scaffold has been erected contrary to approved drawings , using wire to secured crossing bars and missing

    Mar 6, 2025 · Penalty $625

    Resolve
  • Class - 2

    Proposed 7 story mix use building .observe active site, cs present upon inspection was noted sws has been erected contrary to approved drawings , on site have a ohp adjacent to sws contrary to approved drawin

    Mar 6, 2025 · Penalty $625

    Resolve
  • Class - 1

    Work without permit. as noted at time of my inspection at above jobsite of a proposed 7 story mixed use building observed no gc permit posted on enquiring for the gc permit work was provided with engineering wo

    Feb 6, 2025 · Penalty $1,250

    Resolve
Show 3 more ↓
  • Class - 2

    Work without permit. noted: at time of inspection observed, the inst allation of copper pipes (water lines) to the underside of ceiling at 1st fl level leading to apt2r where 2 baseboard heaters are installed

    May 8, 2023 · Penalty $3,125

    Resolve
  • Class - 1

    Work without a permit. work noted:at cellar level of premises eastern half installed water & waste lines for 3pc bathroom toilet,wash basin,shower & residential kitchen sink,plus 220v electric line for electric

    Mar 5, 2012

    Resolve
  • Class - 2

    Residence altered for more than the legally approved number of dwelling. the dob records indicates premises to be a legal 4 family;cellar boiler storage. alteration noted:the premises has now been illegally con

    Mar 5, 2012 · Penalty $1,200

    Resolve

Complaints

  • Heat/hot water

    Apartment only

    Jun 24, 2022 · Apt L1

    Close
  • Unsanitary condition

    Mold

    Jun 24, 2022 · Apt L1

    Close
  • Unsanitary condition

    Pests

    Jun 24, 2022 · Apt L1

    Close
  • Plumbing

    Radiator

    Jan 29, 2010 · Apt 1R

    Close
  • Paint/plaster

    Ceiling

    Jan 29, 2010 · Apt 1R

    Close
  • Plumbing

    Basin/sink

    Jan 29, 2010 · Apt 1R

    Close
  • Heating

    Heat related

    Jan 29, 2010 · Apt 1R

    Close
  • Electric

    Electric-supply

    Jan 29, 2010 · Apt 1R

    Close
  • Heating

    Heat related

    Feb 8, 2007 · Apt 1R

    Close

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Elevator apartment building (D7)
Year built
2024
Floors
7
Residential units
10
Building area
8,380 ft²
Lot area
2,296 ft²
Zoning
—
Community board
401
Council district
26
Block / lot
380 / 7
Assessed value
$503,100
Landmark / historic district
No

HPD registration #414376, last renewed —.

Questions about 33-10 38 Avenue

Who owns 33-10 38 Avenue?

The owner of record in NYC Department of City Planning PLUTO data is 38th Ave Dev LLC.

Does 33-10 38 Avenue have violations?

Yes. NYC HPD has recorded 17 housing violations at this property.

Is 33-10 38 Avenue rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 33-10 38 Avenue built?

City records list 2024 as the year it was built.

How many apartments are in 33-10 38 Avenue?

It has 10 residential units and 11 units in total.