49-18 Vernon Boulevard is an elevator apartment building built in 2017 in Queens, 11101. It has 15 residential units across 5 floors. The owner of record is V & F 4918 LLC. HPD has no housing violations on record for this property.
- HPD violations
- 0
- DOB violations
- 12
- ECB violations
- 47
- HPD complaints
- 1
What to know
No open immediately-hazardous violations among recent records.
HPD has not cited this building.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 0
No HPD violations on record
DOB building violations · 12
- Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Apr 3, 2019
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Mar 7, 2018
Dob violation - dismissed - Construction other optional
C-construction other optional
Jul 12, 2016
Dob violation - active - Construction other optional
C-construction other optional
Aug 18, 2015
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Aug 12, 2015
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Aug 12, 2015
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Aug 12, 2015
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Aug 12, 2015
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Aug 12, 2015
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Aug 12, 2015
Dob violation - dismissed
Show 2 more ↓
- Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Mar 11, 2015
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Dec 17, 2014
Dob violation - dismissed
ECB violations · 47
- Class - 2
Observed sidewalk shed parapet panel at exposure 1 & 2 with unlawful posting, poster (advertising unrelated to the jobsite affixed to the shed panel protective structure as per code 3301.9.7 (no sign, informat
Jul 26, 2025 · Penalty $2,500
Resolve - Class - 2
Bc3301.6 work not conform to engineer designed protection@nb site active 4th fl working deck observe @1st fl shaft cover with ladder on top for only single means of access for upper levels not constructed¬ c
Oct 2, 2024 · Penalty $2,530
Resolve - Class - 2
Observed construction fence surrounding property, upon inspecting fence, observed partial collapse in rear @ exposure #3, hole in fence @ exp.#2 approx. 12 x 6 inches also observed multiple fence panels dislodg
Nov 29, 2022
Resolve - Class - 2
Temporary construction equipment on site -expired permit. at time of inspection observed construction fence installed and permit# 421171840 expired on 11/23/2021., renew permit
Jul 11, 2022 · Penalty $1,250
Resolve - Class - 2
Work with permit/expired permit : observed job site fence installed under job#421171840, permit expired on 11-23-21., obtain all permits
Mar 2, 2022 · Penalty $1,250
Resolve - Class - 2
Job site fence not constructed pursuant to subsection: observed at exp# 2 fence in disrepair condition., comply with code
Mar 2, 2022 · Penalty $2,500
Resolve - Class - 2
Failure to comply w/commissioner's order contained in summons/violation #35408706z issued on 8/16/2019,& to file a certificate of correctionpursuant to 28.201.1 & 1rcny 102-01(d)(2).an acceptible certificate ha
Sep 28, 2020 · Penalty $3,125
Resolve - Class - 2
Work w/o a permit (const plywood fence permit expired).as noted: @timeof expansion const site was closed. observed const plywood fense has expired on 08/07/2019 permit #421171840-01-eq-fn.rem: comply with code.
Aug 16, 2019 · Penalty $1,250
Resolve - Class - 2
Work with expired permit.as noted:at time of inspection,active construction site first floor level failure to renew nb permit #420602324-01-nb was expired on 11/15/2018.rem:stop work entire site.renew permit.em
Jan 11, 2019 · Penalty $1,250
Resolve - Class - 1
Failure to file evidence of compliance with workers compiant and/or disability benefits law.as noted:at time of inspection,active site firstfloor level failure to file evidence of workers compensation.policy #w
Jan 11, 2019 · Penalty $5,000
Resolve
Show 37 more ↓
- Class - 2
Jobsite fence not constructed or maintained pursuant to subsection.at time of inspection observed jobsite fence at exp#3 out of plumb and (lewing).fence is improperly secured and not maintained in a solied cond
Nov 2, 2018 · Penalty $2,000
Resolve - Class - 2
Work without a permit (construction temporary plywood fence permit expired). as noted: at time of inspection, construction plywood fence permit has expired on 02/01/2018 permit #421171840-01-eq-fn and permit #4
Jul 24, 2018 · Penalty $620
Resolve - Class - 2
Housekeeping walkway at time of inspection observed tripping hazard along 50th ave walkway used by pedestrians while sidewalk closed. remedymaintain walkway free of tripping hazards.
Dec 12, 2017 · Penalty $400
Resolve - Class - 2
Sec. 3307.2.2 temporary walkway in street. at time of inspection observed temporary walkway in street along 50th ave not maintained at 5'-0" as required by dept of transportation permit. remedy: maintain 5'-0"
Dec 12, 2017 · Penalty $400
Resolve - Class - 1
Yodocks not filled(pedestrian walkway barrier)at time of inspection observed pedestrian walkway barriers not filled as per manufacturer requirements which creates a condition where vehicular traffic could possi
Dec 12, 2017 · Penalty $4,800
Resolve - Class - 1
Failure to adequately supervisor work @ a construction site so as to maintain a safe construction site & ensure compliance w/ approved construction documents & chapter 33 & notify the dept the following hazardo
Aug 10, 2017 · Penalty $10,000
Active - Class - 2
Sec: 28-105.5. forms filed w/ dob do not have required signatures- tr3 report. as noted: @ time of insp on an active construction site, observed tr3 report missing signature & pe/ra seal on line#6 & missing sig
Aug 10, 2017 · Penalty $800
Active - Class - 1
Failure to safeguard all persons & property affected by construction operations. as noted: @ time of insp on an active construction site observed formwork failure & re shore jack failure @ 1st flr slab. re shor
Aug 10, 2017 · Penalty $10,000
Active - Class - 2
Sec: bc 28-104.7.11. additional information. as noted: @ time of insp on an active construction site observed formwork failure @ 1st flr slab location. re shore jacks broken & bent. plywood formwork pieces comp
Aug 10, 2017 · Penalty $800
Active - Class - 2
Pedestrian protection does not meet code specification.upon annual to jobsite.i obseved tht the contractor failed to maintain the sidewalk and construction frnce entrance at exp#1.cracks were visible for nearly
May 15, 2017 · Penalty $400
Resolve - Class - 2
Failure to designate and/or have construction super present at site as reqd.at time of inspection it was observed that the contractors could not provide a construction super per code.no super listed on the bis
May 15, 2017 · Penalty $2,500
Resolve - Class - 2
Bc3309.6 failure to monitor adjoining structures for movement in all directions during excavation related activities that may adversely affect adjoining structures. the respondent failed to adequately monitor
Jul 27, 2016 · Penalty $4,000
Resolve - Class - 1
3309.6 failure to monitor adjacent structures for movement in all directions during excavation related activity that my adversely affect adjoining structures.to tell if any monitors on the adjacent structures t
May 19, 2015 · Penalty $8,000
Resolve - Class - 1
Work does not conform to the approved construction documents.contractor has begun to install piles first instead of the s.o.e first subjecting workers to dangerous conditions as a result no engineering sequence
May 19, 2015 · Penalty $5,000
Resolve - Class - 1
28-116.2.3 designated special inspector not on site.when the contractor is performing pile driving subject to special inspection.during pile driving operation no engineering is on site for the installation of
May 19, 2015 · Penalty $8,000
Resolve - Class - 1
Failure to safeguard all persons & property affected by construction operations.contractor has installed pile in the zone of the influence of the adj.property walk way and excavated in the same location and as
May 19, 2015 · Penalty $12,000
Resolve - Class - 1
Failure to provide protection @ sides of excavation.near exp.#3 of the jobsite the contractor has dug a 10'hole and installed piles at this location & now has a worker inside the hole cutting @ the base of the
May 19, 2015 · Penalty $12,000
Resolve - Class - 1
3304.4.4 failure to provide 3'-6" guardrail or solid enclosure around open and accessible sides of excavation.no guardrails were placed around a hole that lead to a 10'+ drop.rem:provide guardrails forth with
May 19, 2015 · Penalty $8,000
Resolve - Class - 2
Sec. 3304.4.4 failure to provide 3 foot 6 inch guardrail or solid enclosure around open & accessible side of excavation. there was no guardrail or any form of protection at the accessible side of excavation at
Mar 4, 2015 · Penalty $800
Resolve - Class - 2
Sec. 3307.4 failure to provide road barricade lights or reflectors,perbc 3307.4 noted: road barricades installed along vernon blvd & 50 ave frontage w/no reflectors or lights. remedy: comply w/bldg ceode,provid
Jan 20, 2015 · Penalty $830
Resolve - Class - 2
Failure to post dot permit for sidewalk closing. noted: job site fenceerected under job #440149475 closes the sidewalk along verion blvd & 50 ave,no dot permit posted for sidewalk closing. remedy: post permit.
Jan 20, 2015 · Penalty $530
Resolve - Class - 1
Failure to protect public and property affected by const. operations. no dot permit for sidewalk closing per bc 33303.3- noted: const. fenceerected under job # 440149475-01-eq-fn occupied the entire sidewalk al
Dec 12, 2014 · Penalty $2,400
Resolve - Class - 2
28-105.10.1 borough commissioner has issued a letter of intent to re voke permit to application #440149475 and ordered that all work stop immediately. du eto unauthorized underpinning of 49-16 vernon blvd.
Dec 10, 2014 · Penalty $400
Resolve - Class - 2
Work w/o a permit.noted:@ time of insp there was extended work done through the site from excavation to under pinning.pursuant to section(28-207.2)of the administrative code of the city of new york you are.here
Dec 8, 2014 · Penalty $400
Resolve - Class - 1
Failure to provide protection @ the sides of excavation.noted:@ exp#2 guardrails system missing not erected.site excavated to approx 4' below grade.two open pins"b"pins @ exp#4.6 workmen on site.rem:provide
Nov 24, 2014 · Penalty $2,400
Resolve - Class - 2
Job site fence not const pursuant to subsection(defective fence)noted:approx 12ft of solid 8ft.site fence missing @ vernon blvd side of site levaing partially excavated site open & unguarded.rem:repair/replace
Nov 21, 2014 · Penalty $800
Resolve - Class - 1
Failure to notify the dob within 24 to 48 hours of the start of excavation. observed excavation at the jobsite and the dob was not notified of the start of excavation.rmdy: officially notify the dob by calling
Nov 18, 2014 · Penalty $1,200
Resolve - Class - 2
Bc3303.2.4 failure to provide required temporary or permanent sanitaryfacility during construction,remodeling on demolition operation.at thetime of inspection construction site was active w/o the required san
Nov 18, 2014 · Penalty $800
Resolve - Class - 2
Work w/o a permit.work noted:8'h wooden const.fence is being erected @ expo.2(along police pct #108)with metal pipes & approx 50'fence erected & materials stored for the remaining length.rem:obtain permit
Oct 14, 2014 · Penalty $4,000
Active - Class - 1
Failure to safeguard all persons & property affected by construction operations. noted: the fence blocks the sidewalk adjacent to a subway station w/o dot or any other permission. thereby posing a substantial
Sep 19, 2014 · Penalty $12,000
Resolve - Class - 2
Failure to post dot permit for street/sidewalk closing. noted approx 185 linear feet of job site has been erected in which covers the entiresidewalk prohibiting pedestrian walkway. additionally said job site
Sep 19, 2014 · Penalty $2,500
Resolve - Class - 1
Work does not conform to approved construction documents &/or approvedamendments. stop all work immediately. noted: work does not conform tothe approved document in where job site fence installed at carb leavin
Sep 19, 2014 · Penalty $5,000
Resolve - Class - 1
Oac advertising signs not permitted in c1-5 district. "the view" total13 signs.
Sep 4, 2010
Resolve - Class - 1
Oac signs c1-5 district exceed surface area limits. "the view" total 13 signs. remedy: remove or legalize signs.
Sep 4, 2010
Resolve - Class - 1
Oac leasing or otherwise making illegal advertising sign space available to others for advertising purposes. "the view" total 13 signs. remedy: remove or legalize signs.
Sep 4, 2010
Resolve - Class - 1
Outdoor advertising company sign exceeds max surface area of 150sqft in a c1-5 district signs approx. 100ft wide x 6ft high= 600 sqft the view s remedy:remove illegal sign
Oct 24, 2009
Resolve - Class - 1
Outdoor advertising company sign exceeds max surface area of 150sqft in a c1-5 district signs approx. 40ft wide x 6ft high= 240 sqft the view s remedy:remove illegal sign
Oct 24, 2009
Resolve
Complaints
- Unsanitary condition
Garbage/recycling storage
Jun 12, 2022 · Apt BLDG
Close
Sales history
No recorded sales in our data
Building details
- Building type
- Elevator apartment building (D6)
- Year built
- 2017
- Floors
- 5
- Residential units
- 15
- Building area
- 24,025 ft²
- Lot area
- 5,625 ft²
- Zoning
- R6A
- Community board
- 402
- Council district
- 26
- Block / lot
- 32 / 1
- Assessed value
- $2,836,350
- Landmark / historic district
- No
HPD registration #434730, last renewed Jul 14, 2026.
Questions about 49-18 Vernon Boulevard
Who owns 49-18 Vernon Boulevard?
The owner of record in NYC Department of City Planning PLUTO data is V & F 4918 LLC.
Does 49-18 Vernon Boulevard have violations?
NYC HPD has no housing violations on record for this property.
Is 49-18 Vernon Boulevard rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 49-18 Vernon Boulevard built?
City records list 2017 as the year it was built.