670 92 Street is a public assembly built in 2019 in Brooklyn, 11228. The owner of record is The Greek School Of Plato, Ltd.. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
2
ECB violations
24
HPD complaints
0

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 2

  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jan 24, 2018

    Dob violation - dismissed
  • Construction other optional

    The department of buiding hereby immediately suspending all permits in connection with appl#321103550 pursuant to28-105 10.2 of the administr ative code of city new york./remedy: stop all work immediately remedy; contact bor. comm. office at718 802-3677 contact construction office at 718 802-3685 prior to returning to work

    Nov 22, 2016

    Dob violation - dismissed

ECB violations · 24

  • Class - 2

    Failure to maintain/display onsite documents required by chapter 33.attime of inspection of a 3 story new building under construction,i observed an active site with multiple workers present.upon request,the fol

    May 22, 2020

    Resolve
  • Class - 1

    Bc 3314.1 supported scaffold not constructed/maintained in code-compliance-unsafe scaffold.at time of inspection of a 3 story new building under construction,i observed an interior supported scaffold at the 1st

    May 22, 2020 · Penalty $2,500

    Resolve
  • Class - 1

    Bc3309.10/no roof protection.note:at time of my inspection of a new 3 story building,construction in progress i observed a scaffold erected for facade work at exposure#4 on the building line of the adjoining p

    Oct 11, 2019

    Resolve
  • Class - 2

    Failure to maintain adequate housekeeping per section requirements.note:at time of my inspection of a new 3 storie building construction in progress i observed a large are of garbage by the front entry gate app

    Oct 11, 2019

    Resolve
  • Class - 2

    Bc3301.13.1/inadequate site safety plan.noted:at time of my inspectionof a new 3 story building construction in progress building topped offi observed the adjoining property at exp#4 had no roof protection upon

    Oct 11, 2019

    Resolve
  • Class - 2

    Bc2113.1.6.1/responsibility of taller building.noted:at time of my inspection of a new 3 stories building construction in progress i observed the chimney of the adjoining property and not been brought up with t

    Oct 11, 2019

    Resolve
  • Class - 1

    Failure to institute/maintain safety equipment measures or temporary construction(handrails). at the time of inspection i observed proposed3 sty bldg w/cellar complete to roof w/work activity present. i also

    Aug 29, 2019 · Penalty $625

    Resolve
  • Class - 1

    Failure to maintain/display on site documents required by bc chapter 33. at the time of inspection,i observed proposed 3 sty bldg w/cellar &subcellar complete to roof w/work activity present. i also observed a

    Aug 29, 2019

    Resolve
  • Class - 1

    Sec. 3314.3.3 drawings for supported scaffold contrary. at the time ofmy inspection,i observed proposed 3 sty bldg w/cellar complete to roofw/work activity present. i also observed contractor failed to construc

    Aug 29, 2019 · Penalty $2,500

    Resolve
  • Class - 2

    Failure to maintain adequate housekeeping per section requirements. attime of inspection i observed propose 3 sty bldg complete to roof w/work activity present. i also observed excessive debris throughout the

    Aug 29, 2019

    Resolve
Show 14 more ↓
  • Class - 2

    Failure to comply w/the comm's order contained in summons/vio#35362874r issued on 01-24-19 & to file a c of c pursuant to 28-201.1 & 1rcny 102-01. 3314.8.1 failure to provide safety equipment measures or tempor

    Apr 20, 2019

    Resolve
  • Class - 1

    Unsafe storage of materials during construction or demolition. at timeof inspection,building materials are being stored on scaffold and sidewalk shed contrary to dob permits and approved plans. permit dob#b0059

    Mar 12, 2019 · Penalty $2,500

    Resolve
  • Class - 1

    Work does not conform to approved construction documents and/or approved amendments. at time of inspection,sidewalk shed does conform to dobapproved plans. 20' cantilever at exposure#1 over public sidewalk,not

    Mar 12, 2019 · Penalty $2,500

    Resolve
  • Class - 1

    Failure to file evidence with workers compl law and/or disability benifits law-@time of inspection accroding to dob rec workers comp policy #12wb2 pz3784 with.

    Jan 24, 2019 · Penalty $5,000

    Resolve
  • Class - 1

    3314.8.1 failur to provide safety equip measures or temp construction guardrails and debris netting.@time of inspection missing guard rails &fall netting @sections @exp# of premises - install guardrails and ful

    Jan 24, 2019

    Resolve
  • Class - 2

    Pedestrian protection does not meet code specs.observed cracks in sidewalk.at time of inspection it was observed an active constructin site where underpinning was taking place.observed big crack approximately 1

    Nov 3, 2017

    Resolve
  • Class - 2

    Work does not conform to approved construction docs and/por amendments.at the time of inspection it was observed an active site w/underpinning operations and welding of the rakers at exp#1 and 4.after reviewing

    Nov 3, 2017

    Resolve
  • Class - 1

    Work does not conform to approved construction docs or amendments.at the time of inspection it was observed an active construction where underpinning was in progress and contractor did not follow the sequence o

    Nov 3, 2017

    Resolve
  • Class - 2

    Costruction super failed to perform duties as per rule.at the time of inspection it was observed an active site where super spiro geroulanos failed to include work contrary to approved plan in his log book(1)wo

    Nov 3, 2017

    Resolve
  • Class - 1

    Work does not conform to approved construction documents.at time of inspection observed an active construction site with soe and excavation work in progress.during inspection noted that the work does not confor

    Oct 11, 2017 · Penalty $250

    Resolve
  • Class - 2

    Bc3301.2/failure to provide monitoring report.at time of inspection observed an active construction site with soe and excavation work in progress.during inspection noted that there is no monitoring reports as r

    Oct 11, 2017

    Resolve
  • Class - 1

    Work does not conform to approved construction documents-demolition plan. noted: removal of steel beams done contrary to approved demolitionplan;columns cut to let beams done contrary tp approved demolition pla

    Oct 13, 2016 · Penalty $1,000

    Resolve
  • Class - 1

    Sec. 3301-02 failure to adequately supercvise work at a construction site,so as to maintain a safe construction site & ensure compliance w/approved construction documents & chapter 33. following hazardous condi

    Oct 13, 2016 · Penalty $1,600

    Resolve
  • Class - 1

    Sec. 3306.9.8.3 failure to remove hazards such as glass in windows. noted: active demolition site;2 workers on site. roof removed,exterior walls still in place. few windows still have glass in them removed wind

    Oct 13, 2016 · Penalty $1,600

    Resolve

Complaints

No HPD complaints in our records

Complaint data is still being backfilled from NYC Open Data.

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Public assembly (P9)
Year built
2019
Floors
3
Residential units
—
Building area
9,032 ft²
Lot area
4,520 ft²
Zoning
R4B
Community board
310
Council district
50
Block / lot
6143 / 35
Assessed value
$948,150
Landmark / historic district
No

Questions about 670 92 Street

Who owns 670 92 Street?

The owner of record in NYC Department of City Planning PLUTO data is The Greek School Of Plato, Ltd..

Does 670 92 Street have violations?

NYC HPD has no housing violations on record for this property.

Is 670 92 Street rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 670 92 Street built?

City records list 2019 as the year it was built.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.