5102 11 Avenue
Brooklyn, NY 11219BBL 3-05653-0041Map
Owner of record: Cong Genath Shaul
5102 11 Avenue is a religious facility built in 2016 in Brooklyn, 11219. The owner of record is Cong Genath Shaul. HPD has no housing violations on record for this property.
- HPD violations
- 0
- DOB violations
- 15
- ECB violations
- 10
- HPD complaints
- 0
What to know
No open immediately-hazardous violations among recent records.
HPD has not cited this building.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 0
No HPD violations on record
DOB building violations · 15
- Low pressure boiler boiler required
Violation issued-failure to file 2023 external low pressure inspection
Sep 23, 2024
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2023 external low pressure inspection
Sep 23, 2024
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2020 external low pressure inspection
Jun 30, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2020 external low pressure inspection
Jun 30, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2021 external low pressure inspection
Jun 30, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2021 external low pressure inspection
Jun 30, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2019 external low pressure inspection
Jun 20, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2019 external low pressure inspection
Jun 20, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2022 external low pressure inspection
Apr 25, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2022 external low pressure inspection
Apr 25, 2023
Dob violation - active
Show 5 more ↓
- Construction other optional
Failure to comply w/vacate order issued on 1/23/15, partial vacate of all except construction workers, as per iad inspection on 3/28/17& 3/31/17 multiple males entering and leaving the bldg not involved in the construction of the new bldg.remedy:comply with vacate order
Mar 28, 2017
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Aug 12, 2015
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
May 21, 2014
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Nov 20, 2013
Dob violation - dismissed - Construction other optional
"peer review" on 10/28/13 feu visited the site & observed 2 stories partially constructed of a 4 story steel framed structure.structurally deficient/not conformed to approved drawing. provide new peer review by 11/29 structural integrity key element analysis: lateral stability diaphragm,foundation/superstructure gravity.final review by 12/13/13
Nov 14, 2013
Dob violation - dismissed
ECB violations · 10
- Class - 2
Bc28.1604.1/building structures and parts there of sheall be designed and constructed in accordance with strenght design,load and resistancefact or design.at time of inspection 07/28/17 found metal ramp at grad
Sep 12, 2017
Resolve - Class - 1
Unlawful acts.failure to comply w/an order of the commisioner on vacate.noticed at time of inspection complaint.site on partial vacate#3504465 only to allow gc on site.at time of inspection noticed rabbhi pries
May 23, 2017 · Penalty $2,400
Resolve - Class - 2
1rcny 3301-02(d):failure to have construction site super log book, noticed at time of inspection several workers on site working various trades no super log book on site.rem:stop all work,provide log book
May 23, 2017 · Penalty $400
Resolve - Class - 2
Work does not conform to approved construction documents. noted:at roof top as observed from exp1,a newly constructed bulkhead was obser ved framed that is not shown on approved construction documents.rmdy:
Dec 2, 2015 · Penalty $2,500
Resolve - Class - 1
Unlawfully continued to work whil eon notice of stop work order.noted:a construction site,work at north wall underpinning was observed as well as erection of 1st flr structural steel.all this work is contrary
May 13, 2015 · Penalty $24,000
Resolve - Class - 2
Work does not conform to approved construction documents and/or approved amendments. noted: underpinning being done at north wall is being performed contrary to plans for app#320822035.approach pits and box pit
May 13, 2015 · Penalty $2,500
Resolve - Class - 1
28-212.1 removal of posted order of the commissioner swo & vacate order removed from contractor sign. at time of inspection i observed swo sticker removed from contractor sign that i placed on sign on 10/18/13
Feb 25, 2014
Resolve - Class - 1
Unlawfully continued work while on notice of a stop work order. noted:on 10/18/13 location was placed on a full swo by () for no approved plans on site ecb #35002156n was issued; this location is also under vie
Feb 18, 2014 · Penalty $4,800
Resolve - Class - 2
Work does not conform to approved construction documents and/or approved amendments:noted: 1-permit #320409483 exp 5/3/13 was active,men working;2-the structural drawing are contrary to what is built;1-steal i-
Oct 18, 2013 · Penalty $500
Resolve - Class - 1
Failure to safeguard all persons & property affected by const operations in that at 3rd fl there are no railings installed around perimeter of bldg,workers installing piping - wire mesh. at 2nd fl missing
Aug 29, 2013
Resolve
Complaints
No HPD complaints in our records
Sales history
No recorded sales in our data
Building details
- Building type
- Religious facility (M1)
- Year built
- 2016
- Floors
- 3
- Residential units
- —
- Building area
- 15,960 ft²
- Lot area
- 5,018 ft²
- Zoning
- R6
- Community board
- 312
- Council district
- 44
- Block / lot
- 5653 / 41
- Assessed value
- $792,000
- Landmark / historic district
- No
Questions about 5102 11 Avenue
Who owns 5102 11 Avenue?
The owner of record in NYC Department of City Planning PLUTO data is Cong Genath Shaul.
Does 5102 11 Avenue have violations?
NYC HPD has no housing violations on record for this property.
Is 5102 11 Avenue rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 5102 11 Avenue built?
City records list 2016 as the year it was built.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.