roofy

1502 Newkirk Avenue

Brooklyn, NY 11226BBL 3-05236-0001Map

Owner of record: 601 Marlborough, LLC

1502 Newkirk Avenue is a miscellaneous property built in 1933 in Brooklyn, 11226. The owner of record is 601 Marlborough, LLC. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
6
ECB violations
22
HPD complaints
0

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 6

  • Construction other optional

    The borough commission has ordered all work stop under application # 340794297 on 5/13/2025 immediately due to superintendent withdrawal stop all work and make site safe.

    May 14, 2025

    Dob violation - active
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Dec 23, 2020

    Dob violation - active
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Dec 23, 2020

    Dob violation - dismissed
  • Retaining wall none

    Failed to file cycle 1 technical report by 12/31/2018 per rcny 103-09

    Oct 1, 2019

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Oct 31, 2018

    Dob violation - dismissed
  • Construction other optional

    Emerg wrk.prem is 1 stry detach wood&steel framed w/masonry perim wall comm bldg on corn lot.bldg been part demo&some steel framing erect on site.rear cmu wall along subway track has cracks&left freestand due to removal of roof joists.remedy:brace rear cmu wall.pe dir&oversee wrk on site.file perm w/2days of start of work.wrk start no later 8/29/18

    Aug 27, 2018

    Dob violation - active

ECB violations · 22

  • Class - 2

    Failure to comply with the commissioner's order contained in summons/violation#39029098j issued on 9/23/2020 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01.unlawfully continued wo

    Sep 17, 2021 · Penalty $3,125

    Resolve
  • Class - 1

    Failure to comply w/the comm's order contained in summons/vio#39029099l issued on 09/23/20 & to file a cert of correction pursuant to 28-201.1 & 1rcny 102-01. for work w/o a permit. remedy: comply w/comm's orde

    Sep 14, 2021 · Penalty $2,500

    Active
  • Class - 2

    Failure to comply w/the comm's order contained in summons/vio#39029098j issued on 09/23/20 & to file a cert of correction pursuant to 28-201.1 & 1rcny 102-01. unlawfully continued work while on notice of a stop

    Jul 27, 2021 · Penalty $1,250

    Resolve
  • Class - 1

    Failure to comply with the commissioner's order contained in summons/violation#39029099l issued on 9/23/2020 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01.work without a permit.

    Jul 12, 2021 · Penalty $12,500

    Resolve
  • Class - 1

    Failure to comply w/commissioner's order contained in summons/v35333820z issued 8/6/18 &to file c/c pursuant to28-201.1&1rcny102-01.for b101:work w/o permit...partial demo of structure&red steel frame ibeam...c

    Jul 1, 2021 · Penalty $6,250

    Active
  • Class - 2

    Failure to comply w/the comm's order contained in summons/vio#39029098j issued on 09/23/20 & to file a cert of correction pursuant to 28-201.1 & 1rcny 102-01. unlawfully continued work. remedy: comply w/comm's

    May 18, 2021 · Penalty $1,250

    Resolve
  • Class - 1

    Failure to comply w/the comm's order contained in summons/vio#39029099l issued on 09/23/20 & to file a cert of correction pursuant to 28-201.1 & 1rcny 102-01. work w/o a permit. remedy: comply w/comm's order &/

    May 18, 2021 · Penalty $2,500

    Active
  • Class - 2

    Failure to comply w/ commissioner's order contained in summons/violation#39029098j issued 9/23/20 & to file certificate of correction pursuant to 28-201.1&1rcny102-01 for unlawfully continued work while on noti

    Jan 11, 2021 · Penalty $1,250

    Resolve
  • Class - 1

    Failure to comply with the commissioners order contained in sumons.violation #35333820z issued on 08-06-18 and to file a certificate of correction pursuant to 28-201.1 and 102-01 work without a permit for 14ft

    Nov 18, 2020 · Penalty $12,500

    Resolve
  • Class - 1

    Unlawfully continued work while on notice of a stop work order. since fswo, additional demo of roof, cmu wall at exp 1, installation of new structural steel, and corrugated metal decking at roof. new bracing at

    Sep 23, 2020 · Penalty $2,500

    Active
Show 12 more ↓
  • Class - 1

    Work without a permit. observed additional demo of roof, cmu wall at exp 1, installation of new structural steel, and corrugated metal decking at roof. new bracing at exp 3 cmu wall. no permits on file with dob

    Sep 23, 2020 · Penalty $2,500

    Active
  • Class - 1

    Failure to comply w/the comm's order contained in summons/vio#35333820z issued on 08/06/18 & to file a cert of correction pursuant to 28-201.1 & 1rcny 102.01. demolition of structure & erected steel i beams w/o

    Sep 2, 2020 · Penalty $2,500

    Active
  • Class - 1

    Failure to comply with commissioners order contained in summons/violation #35333820z issued on 08-16-2018 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01.work without a permit comp

    Jan 21, 2020 · Penalty $12,500

    Resolve
  • Class - 1

    Failure to comply with the commissioner's order contained in summons/violation#35333820z issued on 08/16/18 and to file a certificate of correction pursuant to 28-201.1 and 1 rcny 102-01.for work without a perm

    Nov 22, 2019 · Penalty $12,500

    Resolve
  • Class - 1

    Failure to comply w/ the commissioner's order contained in summons/violation#35333820z issued on 8/16/18 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01. work w/o a permit. remedy:

    Sep 19, 2019 · Penalty $12,500

    Resolve
  • Class - 2

    Failure to comply w/the comm's order to file a cert of correction w/the dob's vio#3533820z dated 8-6-18 was issued w/swo for doing work w/o permit & construct fence from corrugated steel w/approx 14'in heights.

    Aug 2, 2019 · Penalty $6,250

    Active
  • Class - 1

    Failure to comply with the commissioner's order contained in summons/violation# 35333820z issued on 08/16/18 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01. work without a permit.

    Jul 12, 2019 · Penalty $12,500

    Resolve
  • Class - 1

    Failure to comply w/the comm's order contained in summons/vio#35333820z issued on 8-16-18 & to file a cert of correction pursuant to 28-201-1 & rcny 102.01. work w/o a permit. remedy: comply w/the comm's order

    Apr 27, 2019 · Penalty $12,500

    Resolve
  • Class - 1

    Failure to comply with the commissioner's order contained in summons/ violation @35333820z issued on 08/16/18 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01. no permit or applica

    Feb 19, 2019 · Penalty $12,500

    Resolve
  • Class - 1

    Failure to comply w/the comm's order contained in summons/vio#35333820z issued on 08/06/18 & to file a c of c pursuant to 28-201.1 & 1rcny 102-01. for: work w/o a permit. remedy: comply w/comm's order &/or file

    Dec 13, 2018 · Penalty $12,500

    Resolve
  • Class - 1

    Failure to comply w/ the commissioner's order contained in summons/violation#35333820z issued on 8/6/18 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01. work w/o a permit. remedy:c

    Oct 31, 2018 · Penalty $6,250

    Resolve
  • Class - 1

    Work without a permit, observed partial demoliton of structure and red steel frame ibeams and posts construction with an approx. 14ft high corrugated steel decking erected as a construction fence enclosing prop

    Aug 6, 2018 · Penalty $1,600

    Active

Complaints

No HPD complaints in our records

Complaint data is still being backfilled from NYC Open Data.

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Miscellaneous property (Z9)
Year built
1933
Floors
1
Residential units
—
Building area
4,000 ft²
Lot area
7,460 ft²
Zoning
R6A
Community board
314
Council district
45
Block / lot
5236 / 1
Assessed value
$309,600
Landmark / historic district
No

Questions about 1502 Newkirk Avenue

Who owns 1502 Newkirk Avenue?

The owner of record in NYC Department of City Planning PLUTO data is 601 Marlborough, LLC.

Does 1502 Newkirk Avenue have violations?

NYC HPD has no housing violations on record for this property.

Is 1502 Newkirk Avenue rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 1502 Newkirk Avenue built?

City records list 1933 as the year it was built.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.