280 Linden Boulevard is a walk-up apartment building built in 2019 in Brooklyn, 11226. It has 8 residential units across 4 floors. The owner of record is 280 Linden Blvd LLC. HPD has recorded 30 housing violations here, most recently on November 24, 2025.

HPD violations
30
DOB violations
14
ECB violations
42
HPD complaints
27

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
Last violation Nov 24, 2025

Date of the most recent HPD inspection that found a problem.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 30

  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 24, 2025

    Closed — Violation closed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Dec 4, 2024

    Closed — Violation closed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 28, 2023

    Closed — Violation closed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 17, 2022

    Closed — Violation closed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Mar 16, 2022

    Closed — Violation closed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Apr 21, 2021

    Closed — Violation closed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 8, 2019

    Closed — Violation closed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Oct 31, 2018

    Closed — Violation closed
  • C

    Provide seal up of all accessible opening (vacant building open to general public)

    May 24, 2015

    Closed — Violation closed
  • C

    Provide temporary seal at all accessible opennings

    Apr 16, 2015

    Closed — Violation closed
Show 20 more ↓
  • I

    The premises or apts. have been vacated by the department and cannot be reoccupied until so ordered after proof of compliance for 1st story apartment ( vacate # 121648)

    Apr 13, 2015

    Closed — Violation closed
  • C

    Replace with new the missing 4 windows upper and lower sash at apt 2 , 2nd story

    Mar 29, 2015

    Closed — Violation closed
  • B

    Provide an approved and operational carbon monoxide detecting device, installed in accordance with applicable law and rules. in the entire apartment located at apt 1stfl, 1st story

    Mar 29, 2015 · Apt 1STFL

    Closed — Violation closed
  • C

    Provide an adequate supply of heat for the apartment in the entire apartment located at apt 1stfl, 1st story

    Mar 29, 2015 · Apt 1STFL

    Closed — Violation dismissed
  • C

    Provide adequate supply of hot water for the fixtures ... in the entire apartment located at apt 1stfl, 1st story

    Mar 29, 2015 · Apt 1STFL

    Closed — Violation closed
  • C

    Provide adequate supply of cold water for the fixtures ... in the entire apartment located at apt 1stfl, 1st story

    Mar 29, 2015 · Apt 1STFL

    Closed — Violation closed
  • C

    Repair the broken or defective plastered surfaces and paint in uniform color the ceiling in the bathroom located at apt 1stfl, 1st story

    Mar 29, 2015 · Apt 1STFL

    Closed — Violation closed
  • B

    Repair the broken or defective plastered surfaces and paint in uniform color the ceiling in the kitchen located at apt 1stfl, 1st story

    Mar 29, 2015 · Apt 1STFL

    Closed — Violation closed
  • C

    § 27-2028, 2032 admin.code: provide an adequate supply of heat from an approved central heating system or an approved system of gas or electrical heating in good operating condition for the dwelling unit in the entire apartment located at apt 1fl, 1st story

    Jan 22, 2015 · Apt 1FL

    Closed — Violation dismissed
  • C

    Provide an adequate supply of gas to the fixtures .. in the entire apartment located at apt 1fl, 1st story

    Jan 22, 2015 · Apt 1FL

    Closed — Violation closed
  • C

    Properly repair the source and abate the evidence of a water leak concealed water leak at ceiling at kitchen 1st floor apartment , 1st story

    Jan 22, 2015

    Closed — Violation closed
  • C

    Properly repair the source and abate the evidence of a water leak concealed water leak at ceiling at bathroom 1st floor apartment , 1st story

    Jan 22, 2015

    Closed — Violation closed
  • C

    Cleanse and disinfect to the satisfaction of this department after removing the accumulation of rubbish and water/sewage at basement

    Jan 22, 2015

    Closed — Violation closed
  • C

    Provide hot water at all hot water fixtures in the entire apartment located at apt 1fl, 1st story

    Jan 22, 2015 · Apt 1FL

    Closed — Violation closed
  • C

    Provide sealed up all accecible openings at 2nd story apartment

    Jan 22, 2015

    Closed — Violation closed
  • B

    Provide an approved and operational carbon monoxide detecting device, installed in accordance with applicable law and rules. in the entire apartment located at apt 1fl, 1st story

    Jan 4, 2015 · Apt 1FL

    Closed — Violation closed
  • C

    Provide hot water at all hot water fixtures in the entire apartment located at apt 1fl, 1st story

    Jan 4, 2015 · Apt 1FL

    Closed — Violation closed
  • C

    Provide an adequate supply of heat for the apartment in the entire apartment located at apt 1fl, 1st story

    Jan 4, 2015 · Apt 1FL

    Closed — Violation dismissed
  • B

    Abate the nuisance consisting of vermin bedbugs in the entire apartment located at apt 2ndfl, 2nd story

    Jul 1, 2009 · Apt 2NDFL

    Closed — Violation closed
  • B

    Abate the nuisance consisting of vermin bedbegs in the entire apartment located at apt 3, 2nd story

    May 29, 2009 · Apt 3

    Closed — Violation closed

DOB building violations · 14

  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Oct 4, 2023

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Oct 4, 2023

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Oct 4, 2023

    Dob violation - dismissed
  • Construction other optional

    Stop all work immediately make site safe contact borough comm. office at 718 802-3677 for info

    Mar 26, 2019

    Dob violation - dismissed
  • Construction other optional

    C-construction other optional

    Feb 27, 2019

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jul 12, 2017

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jul 12, 2017

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jun 28, 2017

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jun 28, 2017

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jun 28, 2017

    Dob violation - dismissed
Show 4 more ↓
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jun 28, 2017

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jun 1, 2016

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jun 1, 2016

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jun 1, 2016

    Dob violation - dismissed

ECB violations · 42

  • Class - 1

    At the time of my inspection of a 4 story-building active job site, exterior work at exposure 4 was observed partially completed prior to the stop work order issued on 01/07/2026 under reference #3a43847. this

    Apr 13, 2026 · Penalty $10,000

    Resolve
  • Class - 2

    Bc 3314.1: at the time of inspection of a four-story building undergoing facade work, pipe scaffold at exposures 3 and 4 was not maintained. loose planks, unsecured planks, and missing pins were observed, cre

    Apr 13, 2026 · Penalty $2,500

    Resolve
  • Class - 1

    Unlawfully continued work while on notice of a stop work order.workingagainst a pswo issued on 01/07/26 under play number 3a43847 stop all exterior work at exposure 4 rear yards.observed pipe scaffold erected a

    Mar 18, 2026 · Penalty $10,000

    Resolve
  • Class - 2

    Permit holder failed to provide and maintain a construction super for the site with a valid license. super license expired 12/11/25 and workers are still on site working. expired license equate to no super assi

    Jan 5, 2026 · Penalty $2,500

    Resolve
  • Class - 2

    Observed at expo#4 rear of the building facade work in the process. styrofoam and stucco work operations to be completed. respondent failed to provide adequate overhead protection for the adjoining property yar

    Jan 5, 2026 · Penalty $2,500

    Resolve
  • Class - 1

    Active site. observed workers throughout the site working. construction supers log stated framing and drywall to be installed. upon checking department records construction supers on file, license expired 12/11

    Jan 5, 2026 · Penalty $5,000

    Resolve
  • Class - 1

    Proposing vertical extension to 8 family dweling .observed active site ,cp present upon inspection noted missing roof protection on exposure 2 rear back exp 2,4 and inadequate roof protection on exposure 4 (p

    Jul 29, 2025 · Penalty $5,030

    Resolve
  • Class - 2

    Proposing vertical extension to 8 family dweling .observed active site currently work on interior framing upon request for c joints manufacturer specification and special inspections report none was provide

    Jul 29, 2025 · Penalty $1,250

    Resolve
  • Class - 1

    Proposing vertical extension to 8 family dweling .observed active site ,cp present upon inspection noted on exposure 1 ,and 3 adjacent properties missing ohp contrary to building code bc3301.2 and creating ha

    Jul 29, 2025

    Resolve
  • Class - 2

    At time of inspection, upon reviewing bis, i observed job site fence permit was expired on 06/12/2019.

    Feb 16, 2024 · Penalty $6,250

    Resolve
Show 32 more ↓
  • Class - 2

    . at time of inspection, i observed job site fence / gate leaning towards active side walk. also, the fence is being defaced with graffiti at exposure #1.

    Feb 16, 2024 · Penalty $2,500

    Resolve
  • Class - 2

    Temporary construction equipment on site-expired permit. fence or sidewalk shed. exist permit #320908336-01-eq-fn have expired at 06/12/2019., renew permit

    Dec 13, 2023 · Penalty $3,125

    Resolve
  • Class - 3

    Failure to maintain building in code compliant manner. noted, at time of inspection construction temporary fence at the bi plywood entry door for loading and unloading are leaning outward to pedestrian walkway

    Dec 13, 2023 · Penalty $250

    Resolve
  • Class - 2

    At time of inspection observe 2 unstable sub section of plywood construction fence at front of premises, leaning towards sidewalk in danger of collapsing and is a potential danger to public, comply with code

    Jul 26, 2023 · Penalty $2,500

    Resolve
  • Class - 1

    At time of inspection observed stalled/abandoned construction site with construction fence not maintained as per code. job site fence gate at exp#1 is leaning toward sidewalk. fence gate has with wide gaps and

    Mar 1, 2023 · Penalty $12,500

    Resolve
  • Class - 2

    At time of inspection for class1 vio#39503231p issued on 07-08-22. for failure to maintain site as per code, site is closed. upon checking department records no certificate of correction on file associated with

    Jan 30, 2023 · Penalty $3,125

    Resolve
  • Class - 2

    At time of inspection of class 1 violation #39506512p issued on 09/20/2022 for construction fence leaning not maintained with large gaps at exp. #1. observed unsafe/violating condition has not been corrected. u

    Dec 20, 2022 · Penalty $3,125

    Resolve
  • Class - 2

    At time of inspection for class1 vio#39503231p issued on 07-08-22 for failure to place a site specific safety monitoring plan and maintain the site per code, observed site is closed. unable to confirm complianc

    Dec 9, 2022 · Penalty $3,125

    Resolve
  • Class - 2

    At the time of inspection on a non active job site , i observed that project information panel with general contractors info and other inquiries was not posted on fence job permit # 320908336 was expired since

    Dec 5, 2022 · Penalty $3,125

    Resolve
  • Class - 2

    At the time of inspection on a non active job site , i observed a construction fence at premises upon my review through bis fence permit # 320908336-01-eq-fn was expired since 06-12-2022 and no new permit was

    Dec 5, 2022 · Penalty $3,125

    Resolve
  • Class - 2

    At the time of inspection on a non active job site, i observed construction fence at premises not at adequate height of 8 feet & missing panels at exposure 4,viewing panel not cover with plexi or similar mater

    Dec 5, 2022 · Penalty $2,500

    Resolve
  • Class - 1

    Construction fence leaning not maintained with large gaps & observed large pile of debris at expo# 1maintain the construction fence & housekeeping at expo #1

    Sep 20, 2022 · Penalty $6,250

    Resolve
  • Class - 2

    Atoi, i observed that the permit for the construction fence permit # 320908336 had expired on 06-12-19. the fence is concaving toward public walkway at exp#1. section of panels are missing at exp# 4 at front ya

    Sep 9, 2022 · Penalty $3,125

    Resolve
  • Class - 1

    During inspection of a site that has been on a stop work order since 2019, i observed that the grass was over grown, the fence was not maintained, dislodged and leaning, with garbage piled up in front. there ap

    Jul 8, 2022 · Penalty $6,250

    Resolve
  • Class - 2

    During inspection i observed that the construction fence was leaning into the pedestrian walkway at exposure #1, #2 and the fence panels at the exposure #4 had collapsed next to the adjacent driveway, giving e

    Jul 8, 2022 · Penalty $2,500

    Resolve
  • Class - 2

    During inspection i observed in the dob records that the fence permit had expired on 06/12/2019 with no renewal in progress. as per dob, a permit must be maintained at all times for temporary equipment that is

    Jul 8, 2022 · Penalty $3,125

    Resolve
  • Class - 1

    Failure to safeguard all persons and property affected by constructionoperations. noted: construction site causing damage to adjacent property "278 linden blvd" walls and ceilings. inadequate roof protection th

    Sep 14, 2018

    Resolve
  • Class - 2

    Work does not conform to approved construction documents and/or approved amendments.observed roofing protection inadequate 1"inch styroform and plywood covering the entire rooof causing the roof to hold stale r

    Sep 14, 2018

    Resolve
  • Class - 1

    Construction superintendent fail to preform duties as per rule. note: the following hazardous conditions were observed & stop work order issued to this construction site of the above address-1)no logs on site

    Apr 12, 2017

    Resolve
  • Class - 1

    Failure to designated &/or have construction superintendent present at site as required. note: at the time of my inspection of a 3 sty bldg under construction at 3rd fl level,work in progress 5 workers engaged

    Apr 12, 2017 · Penalty $10,000

    Resolve
  • Class - 1

    Construction superintendent failed to preform duties per rule. note: @the time of my inspection of a 4 sty bldg at 4th fl level,work in progress-masovery,carperntry,10 workers on site. there was no construction

    Apr 12, 2017 · Penalty $10,000

    Resolve
  • Class - 2

    Failure to maintain requirement adequate housekeeping per section requirements. note: @ time of insp of a 4 story bldg @ 4th flr level, work in progress in masonery, observed that the entire site was clustered

    Mar 30, 2017 · Penalty $800

    Resolve
  • Class - 2

    Logs. note: @ time of insp of a 4 story bldg @ 4th level, work in progress in masonery. upon request for construction superintendent logs none was provided or available. rem: provide & maintain logs as required

    Mar 30, 2017 · Penalty $800

    Resolve
  • Class - 1

    Failure to safeguard all persons & property affected by construction activity. note: @ time of insp of a 4 story bldg @ 4th flr level work in progress in masonry/carpentry 10 workers on site. no overhead protec

    Mar 30, 2017 · Penalty $2,400

    Resolve
  • Class - 1

    No guardrails- failure to institute/maintain safety equipments measures or temporary construction. note: @ time of insp of a 4 story bldg @ 4th flr level, work in progress in masonery 10 workers on site, observ

    Mar 30, 2017 · Penalty $800

    Resolve
  • Class - 1

    Failure to designate &/or have construction superintendent present @ site as required. noted: @ the time of insp of a 4 story bldg @ 4th flr level, work in progress in masonery, carpentry, 10 workers on site. o

    Mar 30, 2017 · Penalty $1,600

    Resolve
  • Class - 1

    Required means of egress shall be maintain @ all times during construction or demolition. note: @ time of insp of a 4 story bldg under construction @ 4th flr level, work in progress w/ 10 workers on site engade

    Mar 30, 2017 · Penalty $1,000

    Resolve
  • Class - 2

    Smoking at construction site. nb job#320908336 at the time of inspecton i observed several smoked cigarret butts at exp#1 ground level w/i the construction site permises. remedy: comply w/code.

    Feb 2, 2017 · Penalty $1,200

    Resolve
  • Class - 1

    Failure to safeguard all persons and property affected by constructionoperations:noted: owner is observed illegally vertically enlarging this 2story building (semi-attached).all existing roofing material,struct

    Mar 9, 2016 · Penalty $2,400

    Resolve
  • Class - 1

    Failure to institute/maintain safety equipment measures of temporary construction no guardrails. noted: owner is illegally working on vertically enlarging this 2story semi-attached bldg. there are no guardrails

    Mar 9, 2016 · Penalty $2,400

    Resolve
  • Class - 1

    Work w/o permit. owner of this 2story semi-attached bldg is observed vertical extending the building.the existing roof has been removed andnew steel joist and q-decking is installed (cmu) concrete masonry unit

    Mar 9, 2016 · Penalty $1,600

    Resolve
  • Class - 1

    Failure to carr out demolition operations as required by section.notedowner of mentioned building has demolished the entire interior and roof of bldg.all sructural floor and roof numbers have demolished.the cel

    Mar 9, 2016 · Penalty $2,400

    Resolve

Complaints

  • Heat/hot water

    Apartment only

    Dec 30, 2015 · Apt 1FL

    Close
  • Door/window

    Door

    Dec 30, 2015 · Apt 1FL

    Close
  • Heat/hot water

    Entire building

    Jan 21, 2015 · Apt 1FL

    Close
  • Door/window

    Window frame

    Jan 21, 2015 · Apt 1STFL

    Close
  • Door/window

    Window pane

    Jan 21, 2015 · Apt 1STFL

    Close
  • Heat/hot water

    Entire building

    Jan 20, 2015 · Apt BLDG

    Close
  • Heat/hot water

    Entire building

    Jan 9, 2015 · Apt 1

    Close
  • Paint/plaster

    Ceiling

    Jan 9, 2015 · Apt 1FL

    Close
  • Paint/plaster

    Ceiling

    Jan 9, 2015 · Apt 1FL

    Close
  • Flooring/stairs

    Stairs

    Jan 9, 2015 · Apt 2FL

    Close
Show 17 more ↓
  • Door/window

    Window pane

    Jan 9, 2015 · Apt 2FL

    Close
  • Flooring/stairs

    Floor

    Jan 7, 2015 · Apt 1

    Close
  • Unsanitary condition

    Mold

    Jan 7, 2015 · Apt 1

    Close
  • Paint/plaster

    Ceiling

    Jan 7, 2015 · Apt 1

    Close
  • Paint/plaster

    Wall

    Jan 7, 2015 · Apt 1

    Close
  • Heat/hot water

    Apartment only

    Jan 7, 2015 · Apt 1

    Close
  • Flooring/stairs

    Floor

    Jan 7, 2015 · Apt 1

    Close
  • Plumbing

    Boiler

    Jan 7, 2015 · Apt 1

    Close
  • Heat/hot water

    Entire building

    Dec 17, 2014 · Apt 1

    Close
  • Heat/hot water

    Entire building

    Nov 13, 2014 · Apt BLDG

    Close
  • Heat/hot water

    Apartment only

    Nov 13, 2014 · Apt 1

    Close
  • Heating

    Heat related

    Nov 13, 2013 · Apt 1FL

    Close
  • Nonconst

    Vermin

    Aug 17, 2009 · Apt 2NDFL

    Close
  • Nonconst

    Janitor/super

    Aug 17, 2009 · Apt 2NDFL

    Close
  • Nonconst

    Vermin

    Jul 14, 2009 · Apt 2NDFL

    Close
  • Nonconst

    Vermin

    Jun 29, 2009 · Apt 2NDFL

    Close
  • Nonconst

    Vermin

    May 27, 2009 · Apt 3

    Close

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Walk-up apartment building (C1)
Year built
2019
Floors
4
Residential units
8
Building area
6,916 ft²
Lot area
3,150 ft²
Zoning
R7-1
Community board
317
Council district
40
Block / lot
4868 / 27
Assessed value
$280,350
Landmark / historic district
No

HPD registration #815457, last renewed Aug 9, 2017.

Questions about 280 Linden Boulevard

Who owns 280 Linden Boulevard?

The owner of record in NYC Department of City Planning PLUTO data is 280 Linden Blvd LLC.

Does 280 Linden Boulevard have violations?

Yes. NYC HPD has recorded 30 housing violations at this property.

Is 280 Linden Boulevard rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 280 Linden Boulevard built?

City records list 2019 as the year it was built.

How many apartments are in 280 Linden Boulevard?

It has 8 residential units.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.