725 Saratoga Avenue
Brooklyn, NY 11212BBL 3-03569-0028Map
Owner of record: Dear, Charles
725 Saratoga Avenue is a walk-up apartment building built in 2009 in Brooklyn, 11212. It has 3 residential units across 3 floors. The owner of record is Dear, Charles. HPD has recorded 13 housing violations here, most recently on May 8, 2026. 6 of the 13 most recent violations are still open.
- HPD violations
- 13
- DOB violations
- 2
- ECB violations
- 11
- HPD complaints
- 0
What to know
No open immediately-hazardous violations among recent records.
Date of the most recent HPD inspection that found a problem.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 13
- ANon-hazardous
File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.
May 8, 2026
Open — Nov sent out - ANon-hazardous
File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.
Jun 13, 2025
Open — Nov sent out - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Nov 26, 2024
Closed — Violation dismissed - ANon-hazardous
File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.
Apr 17, 2024
Open — Nov sent out - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Nov 20, 2023
Closed — Violation dismissed - ANon-hazardous
File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.
Mar 31, 2023
Open — Nov sent out - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Nov 7, 2022
Closed — Violation dismissed - ANon-hazardous
File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.
Mar 10, 2022
Open — Nov sent out - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Mar 10, 2022
Closed — Violation dismissed - ANon-hazardous
File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.
Apr 20, 2021
Open — Nov sent out
Show 3 more ↓
- IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Apr 20, 2021
Closed — Violation dismissed - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Nov 6, 2019
Closed — Violation dismissed - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Oct 29, 2018
Closed — Violation dismissed
DOB building violations · 2
- Construction other optional
Stop all work work does not conform to approval construction docs. and /or approval amendments at time of inspection at exp.1 across entire l ength was a cut approved 10' deep no protection remedy: stop all work. conform to appproved docs. or amends. call f or reinpsection
Aug 12, 2009
Dob violation - dismissed - Construction other optional
Work does not conform to the approved construction documents and amend ments. contractor neglected to install shoring at rear of exp. 2 whic h is clearly shown drawing remedy: stop all work except to backfill and install shoring
Jul 30, 2009
Dob violation - dismissed
ECB violations · 11
- Class - 2
Failure to safeguard all persons & property affected by construction operations "no smoking" signs w/i construction site not visible or inadequate in violation of nyc fire code 1404.1 & fc 310. at time of inspe
Aug 12, 2009 · Penalty $1,200
Resolve - Class - 2
Sec. bc 3301.4.4;27-1032b failure to provide 3'ft - 6'inch guardrail or solid enclosure around open & accessible sides of excavation. at time of inspection i did observe foundation approx 8'deep w/o guardrail.
Aug 12, 2009
Resolve - Class - 2
Sec. bc 1805.3;27-657 design fails to consider the influence of new footing on adjoining footing at different elevations. at time of inspection i did observe(undermining)of adjoining property foundation w/o
Aug 12, 2009
Resolve - Class - 2
Sec. bc 3304.7;26-229a failure to provide adequate means of exit from excavation. at time of inspection i did observe 80' of 8' foundation wall & 25' of sheer cut with 1 inadequate ladder being used as only mea
Aug 12, 2009
Resolve - Class - 2
Sec. bc 3307.7;27-1021 failure to provide an adequate construction fence at time of inspection i did observed or exp #2 at rear fence down. remedy: comply with notice of violation call 212-442-1698 for inspecti
Aug 12, 2009
Resolve - Class - 2
Sec. bc 1814.1.1;bc 3309.4;27-1032 failure to take adequate measure toprevent the vertical or(lateral) displacement of adjoining structure being underpinning. at time of inspection i did observe underpinning
Aug 12, 2009
Resolve - Class - 2
Failure to notify d.o.b. with 24-48hrs of start of excavation. at time of inspection no conformation # on file for rule 52. remedy: obtain confirmation # from d.o.b. by calling 212-227-4416.
Aug 12, 2009
Resolve - Class - 2
Failure to safeguard all persons & property affected by construction operations. at time of inspection i did observe material & debris at exp #1 r/s causing a tripping hazard & rebar w/o protection caps through
Aug 12, 2009 · Penalty $1,200
Resolve - Class - 2
Failure to preserve and protect adjoining structure affected by excavation operations. during installation of remedial shoring damage has been done to porch area or adj premises at rear adj exp 2. remedy: prote
Aug 4, 2009 · Penalty $800
Resolve - Class - 2
Work does not conform to approved plans and amendments. shoring installed is no according to drawing which calls for w8x31 however w4x13 hasbeen installed. remedy: amend plans to show this change can sustain lo
Aug 4, 2009
Resolve
Show 1 more ↓
- Class - 1
Failure to preserve and protect adjoining structure affected by excavation operations at rear of exp 2 contractor failed to install shoring at area were bldg was still within line of influence to excavation.
Jul 30, 2009 · Penalty $1,600
Resolve
Complaints
No HPD complaints in our records
Sales history
No recorded sales in our data
Building details
- Building type
- Walk-up apartment building (C0)
- Year built
- 2009
- Floors
- 3
- Residential units
- 3
- Building area
- 3,402 ft²
- Lot area
- 2,100 ft²
- Zoning
- R6
- Community board
- 316
- Council district
- 41
- Block / lot
- 3569 / 28
- Assessed value
- $56,340
- Landmark / historic district
- No
HPD registration #388040, last renewed Aug 25, 2025.
Questions about 725 Saratoga Avenue
Who owns 725 Saratoga Avenue?
The owner of record in NYC Department of City Planning PLUTO data is Dear, Charles.
Does 725 Saratoga Avenue have violations?
Yes. NYC HPD has recorded 13 housing violations at this property.
Is 725 Saratoga Avenue rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 725 Saratoga Avenue built?
City records list 2009 as the year it was built.
How many apartments are in 725 Saratoga Avenue?
It has 3 residential units.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.