roofy

182 Graham Avenue

Brooklyn, NY 11206BBL 3-03053-0008Map

Owner of record: Port Rich Realty INC

182 Graham Avenue is a mixed residential and retail building built in 1920 in Brooklyn, 11206. It has 6 residential units across 4 floors. The owner of record is Port Rich Realty INC. HPD has recorded 222 housing violations here, most recently on October 8, 2026. 44 of the 50 most recent violations are still open.

HPD violations
222
DOB violations
26
ECB violations
116
HPD complaints
147

What to know

Concern
10 open Class C

Immediately hazardous issues among recent violations are still open.

Watch
Last violation Oct 8, 2026

Date of the most recent HPD inspection that found a problem.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 222

  • C

    Provide ready access to buildings heating system door locked yard

    Oct 8, 2026

    Open — Nov sent out
  • C

    Provide hot water at all hot water fixtures in the entire apartment located at apt 2, 3rd story, 1st apartment from north at east

    Oct 8, 2026 · Apt 2

    Open — Nov sent out
  • A

    Properly repair with similar material the broken or defective wood floor in the kitchen located at apt 2, 3rd story, 1st apartment from north at east

    Oct 8, 2026 · Apt 2

    Open — Nov sent out
  • B

    Repair, replace or provide an approved and operational smoke detecting device, installed in accordance with department of buildings rules and regulations that is missing in the entire apartment located at apt 2, 3rd story, 1st apartment from north at east

    Oct 8, 2026 · Apt 2

    Open — Nov sent out
  • B

    Repair, replace or provide an approved and operational carbon monoxide detecting device, installed in accordance with applicable law and rules that is missing in the entire apartment located at apt 2, 3rd story, 1st apartment from north at east

    Oct 8, 2026 · Apt 2

    Open — Nov sent out
  • C

    Abate the infestation consisting of mice in the entire apartment located at apt 2, 3rd story, 1st apartment from north at east

    Oct 8, 2026 · Apt 2

    Open — Notice of issuance sent to tenant
  • C

    Abate the infestation consisting of roaches in the entire apartment located at apt 2, 3rd story, 1st apartment from north at east

    Oct 8, 2026 · Apt 2

    Open — Notice of issuance sent to tenant
  • C

    Immediately provide a fire guard as directed by the nyc dept. of housing preservation & development (hpd) and/or the nyc dept. of buildings (dob) to protect against fire hazards observed by hpd and/or dob. fire hazards observed by hpd have resulted in the following additional hpd violation(s): 19289579 in order to protect public safety against imminent fire hazards observed, a fire guard must be provided forthwith for continuous 24 hour coverage, notwithstanding the correction and certification dates set forth above (the correction and certification dates set forth above are applicable for purposes of civil penalties that may be assessed pursuant to nyc administrative code § 27-2115, but do not reflect the date by which a fire guard must be provided). a fire guard must be provided immediately due to the exigency of the dangerous fire hazard conditions observed. the violation requiring a fire guard to be provided will remain open until such time as the fire hazards resulting in the hpd violation(s) referenced above and/or the fire hazards resulting in related dob violation(s) have been dismissed.

    Oct 8, 2026

    Open — Nov sent out
  • C

    Provide a safe and adequate supply of electric service to the fixtures at ceiling on all stories at public hall

    Oct 8, 2026

    Open — Nov sent out
  • C

    Provide a safe and adequate supply of electric service to the fixtures at ceiling in the public halls on all stories of the building, to restore illumination required for first means of egress.

    Jun 16, 2026

    Closed — Violation dismissed
Show 40 more ↓
  • B

    Remove all encumbrances consisting of household items at public hall, 4th story

    Jun 16, 2026

    Open — Nov sent out
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    May 4, 2026

    Open — Nov sent out
  • B

    Replace with new the missing door in the bathroom located at apt 3a, 4th story, 1st apartment from north at east

    Apr 24, 2026 · Apt 3A

    Open — Nov sent out
  • B

    Trace and repair the source and abate the visible mold condition... less than 10 sq ft at the ceiling in the bathroom located at apt 3a, 4th story, 1st apartment from north at east original violation 18811015 issued 24-apr-26 has been upgraded to class b per administrative code 27-2017.3a(3)(a) or (b).

    Apr 24, 2026 · Apt 3A

    Open — Notice of issuance sent to tenant
  • B

    Properly repair with similar material the broken or defective wood floor in the kitchen located at apt 3a, 4th story, 1st apartment from north at east

    Apr 24, 2026 · Apt 3A

    Open — Nov sent out
  • C

    Provide adequate supply of hot water for the fixtures .. in the entire apartment located at apt 3a, 4th story, 1st apartment from north at east

    Apr 24, 2026 · Apt 3A

    Open — Nov sent out
  • B

    Repair, replace or provide an approved and operational smoke detecting device, installed in accordance with department of buildings rules and regulations defective in the entire apartment located at apt 3a, 4th story, 1st apartment from north at east

    Apr 24, 2026 · Apt 3A

    Open — Nov sent out
  • B

    Repair, replace or provide an approved and operational carbon monoxide detecting device, installed in accordance with applicable law and rules defective in the entire apartment located at apt 3a, 4th story, 1st apartment from north at east

    Apr 24, 2026 · Apt 3A

    Open — Nov sent out
  • C

    Abate the infestation consisting of roaches in the entire apartment located at apt 3a, 4th story, 1st apartment from north at east

    Apr 24, 2026 · Apt 3A

    Open — Notice of issuance sent to tenant
  • B

    Repair the broken or defective plastered surfaces and paint in a uniform color the east wall, south wall and ceiling in the bathroom located at apt 3a, 4th story, 1st apartment from north at east

    Apr 24, 2026 · Apt 3A

    Open — Nov sent out
  • B

    Repair the roof so that it will not leak over the ceiling in the bathroom located at apt 3a, 4th story, 1st apartment from north at east

    Apr 24, 2026 · Apt 3A

    Open — Nov sent out
  • B

    Replace with new the missing glass at lower sash at the 1st window from north at east in the 1st room from north located at apt 3a, 4th story, 1st apartment from north at east

    Apr 24, 2026 · Apt 3A

    Open — Nov sent out
  • B

    Repair the broken or defective plastered surfaces and paint in a uniform color the ceiling in the 1st room from north located at apt 3a, 4th story, 1st apartment from north at east

    Apr 24, 2026 · Apt 3A

    Open — Nov sent out
  • B

    Repair the roof so that it will not leak over the ceiling in the 1st room from north located at apt 3a, 4th story, 1st apartment from north at east

    Apr 24, 2026 · Apt 3A

    Open — Nov sent out
  • B

    Repair the broken or defective plastered surfaces and paint in a uniform color the ceiling in the kitchen located at apt 3a, 4th story, 1st apartment from north at east

    Apr 24, 2026 · Apt 3A

    Open — Nov sent out
  • B

    Repair the roof so that it will not leak over the ceiling in the kitchen located at apt 3a, 4th story, 1st apartment from north at east

    Apr 24, 2026 · Apt 3A

    Open — Nov sent out
  • B

    Properly repair and abate unsafe electric wiring condition consisting of exposed electrical wires at the east wall in the bathroom located at apt 3a, 4th story, 1st apartment from north at east

    Apr 24, 2026 · Apt 3A

    Open — Nov sent out
  • A

    Trace and repair the source and abate the visible mold condition... less than 10 sq ft at the ceiling in the bathroom located at apt 3a, 4th story, 1st apartment from north at east

    Apr 24, 2026 · Apt 3A

    Closed — Violation closed
  • B

    Provide a safe and adequate supply of electric service to the fixtures .. in the entire apartment located at apt 3, 4th story, 1st apartment from north at east

    Jan 16, 2026 · Apt 3

    Open — Nov sent out
  • A

    Properly repair with similar material the broken or defective wood floor in the kitchen located at apt 3, 4th story, 1st apartment from north at east

    Jan 16, 2026 · Apt 3

    Open — Nov sent out
  • B

    Properly repair and abate unsafe electric wiring condition consisting of exposed wiring from basement and public hall light fixture leading to the kitchen and bedroom in the entire apartment located at apt 3, 4th story, 1st apartment from north at east

    Jan 16, 2026 · Apt 3

    Open — Nov sent out
  • C

    Properly repair or replace the broken or defective window glass pane at lower sash, first window from north at east in the 1st room from east at north located at apt 3, 4th story, 1st apartment from north at east

    Jan 16, 2026 · Apt 3

    Closed — Violation closed
  • B

    Repair the roof so that it will not leak over the ceiling in the 1st room from east at north located at apt 3, 4th story, 1st apartment from north at east

    Jan 16, 2026 · Apt 3

    Open — Nov sent out
  • B

    Repair the roof so that it will not leak over the ceiling in the bathroom located at apt 3, 4th story, 1st apartment from north at east

    Jan 16, 2026 · Apt 3

    Open — Nov sent out
  • B

    Properly repair the source and abate the evidence of a water leak at ceiling in the kitchen located at apt 3, 4th story, 1st apartment from north at east

    Jan 16, 2026 · Apt 3

    Open — Nov sent out
  • C

    Provide adequate supply of hot water for the fixtures inadequate hot water in the entire apartment located at apt 3, 4th story, 1st apartment from north at east

    Jan 16, 2026 · Apt 3

    Open — Nov sent out
  • B

    Repair or replace the carbon monoxide detecting device(s). ,missing in the entire apartment located at apt 3a, 4th story, 1st apartment from east at south

    Jun 13, 2025 · Apt 3A

    Open — Nov sent out
  • B

    Repair or replace the smoke detector ,missing in the entire apartment located at apt 3a, 4th story, 1st apartment from east at south

    Jun 13, 2025 · Apt 3A

    Open — Nov sent out
  • C

    Provide a safe and adequate supply of electric service to the fixtures , at electric outlets and ceiling light fixture throughout in the entire apartment located at apt 3a, 4th story, 1st apartment from east at south

    Jun 13, 2025 · Apt 3A

    Open — Nov sent out
  • B

    Repair the broken or defective plastered surfaces and paint in a uniform color at ceiling in the 1st room from east at north located at apt 3a, 4th story, 1st apartment from east at south

    Jun 13, 2025 · Apt 3A

    Open — Nov sent out
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Jun 9, 2025

    Closed — Violation dismissed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 25, 2024

    Closed — Violation dismissed
  • B

    M/d law abate the nuisance consisting of plexiglass at vestibule door at public hall, 1st story

    Jul 22, 2024

    Open — Nov sent out
  • B

    Replace with new the missing glass at vestibule door at public hall, 1st story

    Jul 22, 2024

    Open — Nov sent out
  • B

    Remove all encumbrances consisting of household items at public hall, 3rd story

    Jul 22, 2024

    Open — Nov sent out
  • C

    Repair the broken or defective plastered surfaces and paint in a uniform color at ceiling in the kitchen located at apt 3a, 3rd story, 1st apartment from north at east

    Jul 22, 2024 · Apt 3A

    Closed — Violation closed
  • B

    Repair the roof so that it will not leak at ceiling in the kitchen located at apt 3a, 3rd story, 1st apartment from north at east

    Jul 22, 2024 · Apt 3A

    Open — Nov sent out
  • B

    Repair the broken or defective plastered surfaces and paint in a uniform color at ceiling in the bathroom located at apt 3a, 3rd story, 1st apartment from north at east

    Jul 22, 2024 · Apt 3A

    Open — Nov sent out
  • B

    Repair the roof so that it will not leak at ceiling in the bathroom located at apt 3a, 3rd story, 1st apartment from north at east

    Jul 22, 2024 · Apt 3A

    Open — Nov sent out
  • B

    Repair or replace the carbon monoxide detecting device(s). that is defective in the entire apartment located at apt 3a, 3rd story, 1st apartment from north at east

    Jul 22, 2024 · Apt 3A

    Open — Nov sent out

DOB building violations · 26

  • Immediate emergency anythingoptional

    Imegncy-immediate emergency anythingoptional

    Jun 8, 2026

    Dob violation - active
  • Immediate emergency anythingoptional

    Full dismantle and repair/replace approximately 120 ft of sidewalk shed as per code requirements

    Jun 8, 2026

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued-failure to file 2024 external low pressure inspection

    Nov 14, 2025

    Dob violation - active
  • Immediate emergency anythingoptional

    Replace all damaged mudsills, secure all pipe girts and cross bracings

    Sep 16, 2025

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued-failure to file 2023 external low pressure inspection

    Sep 23, 2024

    Dob violation - active
  • Low pressure boiler boiler required

    Violation issued-failure to file 2020 external low pressure inspection

    Jun 30, 2023

    Dob violation - active
  • Low pressure boiler boiler required

    Violation issued-failure to file 2021 external low pressure inspection

    Jun 30, 2023

    Dob violation - active
  • Low pressure boiler boiler required

    Violation issued-failure to file 2018 external low pressure inspection

    Jun 20, 2023

    Dob violation - active
  • Low pressure boiler boiler required

    Violation issued-failure to file 2022 external low pressure inspection

    Apr 25, 2023

    Dob violation - active
  • Construction other optional

    Comply w/vacate order

    Jan 15, 2022

    Dob violation - active
Show 16 more ↓
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Oct 14, 2020

    Dob violation - active
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Sep 2, 2020

    Dob violation - active
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Sep 2, 2020

    Dob violation - active
  • Immediate emergency anythingoptional

    Install a total of approximately 120 linear feet of sidewalk shed along the entire graham avenue (exposure 1) side and meserole street sside (exposure 2) of the four story building

    Jul 24, 2020

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Feb 19, 2020

    Dob violation - active
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Mar 6, 2019

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    May 4, 2011

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    May 4, 2011

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Jan 6, 2006

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Jan 31, 2005

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Mar 19, 2003

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Mar 26, 2002

    Dob violation - dismissed
  • Construction other optional

    C-construction other optional

    Jun 20, 2001

    Dob violation - active
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Feb 27, 2001

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Mar 16, 1999

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    May 4, 1998

    Dob violation - dismissed

ECB violations · 116

  • Class - 2

    Atoi observed parapet info panel with wrong address, property is 182 graham bin#3327943 info panel states 184 graham bin# 3071005 creating hazardous conditions to the public and emergency services attempting to

    Sep 25, 2026 · Penalty $1,250

    Active
  • Class - 1

    Failure to maintain building in code compliant manner. observed at exposure 1 around to exposure 2 under 4th floor windows. facade in disrepair, with missing lentils, missing decorative paneling and shingles. h

    Sep 18, 2026 · Penalty $2,500

    Active
  • Class - 2

    Temporary constructionequipment or installation on site -expired permit. shed permit expired 9/8/2021 under job #b00380266-i1 and and was signed off 5/10/2023 to be removed. sidewalk currently still remains on

    Sep 18, 2026 · Penalty $1,250

    Active
  • Class - 1

    Failure to maintain building in code compliant manner for violation #39160353l. observed at exposure 1 on graham avenue shed post are not plumb and are leaning forward., repair and/replace

    Sep 18, 2026 · Penalty $6,250

    Active
  • Class - 1

    Failure to safeguard public and property per bc3307. noted: sidewalk shed erected prior to obtaining permit. sidewalk shed had a parapet panel displaced earlier today. additional parapet panel has been displace

    Jun 7, 2026 · Penalty $25,000

    Active
  • Class - 1

    B3307.6.5.1 b3307.6.5.3 at time of inspection observed sidewalk shed installed at exp# 1 and exp#4. exp# 4 sidewalk shed missing parapet panel. parapet panel was observed lean along the vertical post note multi

    Jun 7, 2026 · Penalty $25,000

    Active
  • Class - 2

    Note: at time of inspection, i observed a sidewalk shed in place with the parapet panels at expo#2 leaning outward toward the roadway creating a unsafe condition for the vehicular traffic and pedestrians in the

    May 11, 2026 · Penalty $10,000

    Active
  • Class - 2

    I observed a sidewalk shed installed at expo# 1-2 with missing information panel as required by code (3301.9.2) which includes the building address and name of contractor and the statement "for more info with t

    May 11, 2026 · Penalty $6,250

    Active
  • Class - 2

    Note: at time of inspection, i observed a sidewalk shed in place at expo# 1-2, upon review of the department records it was noted that the last sidewalk shed was signed-off, and no new permit was issued for the

    May 11, 2026 · Penalty $6,250

    Active
  • Class - 2

    At time of inspection, observed sidewalk shed installed at exposure numbers 1 and 2. upon review of the department records, no active permit was found on file for the installed sidewalk shed, contrary to code r

    Mar 17, 2026 · Penalty $6,250

    Active
Show 40 more ↓
  • Class - 2

    At the time of inspection, a sidewalk shed was observed in place, but no shed parapet information panel was provided as required by the building code. this condition creates a hazardous condition by causing a d

    Mar 17, 2026 · Penalty $6,250

    Active
  • Class - 1

    Observe sws that was installed at exp #1(graham ave) &#2( meserole st ). vertical members not plumb, mudsill rotten unsupported and parapet panel leaning., repair and/replace

    Sep 15, 2025 · Penalty $12,500

    Active
  • Class - 2

    Observe at exp 1 and 2 sws was installed under permit b00380266-i1-sh permit expiration date 09/08/2021 and has not been renewed., renew permit; renewed permit for sws

    Sep 15, 2025 · Penalty $6,250

    Active
  • Class - 2

    At time of inspection observed: sidewalk shed installed at expo# 1-2 missing project information panel contrary to bc 3301.9.2. creating an unsafe condition for public and occupied adjoining properties, safety

    Sep 15, 2025 · Penalty $6,250

    Active
  • Class - 2

    Failure to file required annual boiler inspection reports for low-pressure boiler 30000067830y0001 in accordance with the rules of the department. 1rcny 103-01(d)(1) requires that an annual inspection report fo

    Jul 1, 2025 · Penalty $3,125

    Active
  • Class - 2

    Failure to obtain a temporary construction permit prior to installation/use of temporary construction equipment; noted: observed temporary sidewalk shed erected & in place at the building exterior along graham

    Apr 2, 2025 · Penalty $6,250

    Active
  • Class - 2

    At time of inspection observed: 4 stories building, no work, sidewalk shed in place expo# 1-2 vertical members not plumb, mudsill rotten unsupported, electrical conduits broke discontinued, not permit, owner fa

    Apr 2, 2025 · Penalty $10,000

    Active
  • Class - 2

    Bc3307.6.@4story building with no active exterior construction activity/permit observe sidewalk shed in place at exposures#1&2,&building owner failed to ensure safe sidewalk shed for all-vertical members not pl

    Nov 18, 2024 · Penalty $10,000

    Active
  • Class - 2

    Sidewalk shed bc3307.6.@4story building with no active exterior construction activity/permit observe sidewalk shed in place at exposures#1&2,&building owner failed to ensure safe sidewalk shed for all-vertical

    Oct 3, 2024 · Penalty $2,400

    Active
  • Class - 2

    Sidewalk shed. observe sidewalk shed in place@exposure#1&2 &the most recent sidewalk shed job(b00380266)&permit in departments records (bis/dob now) had expired since 09/08/2021&job signed off/letter of complet

    Oct 3, 2024 · Penalty $1,250

    Active
  • Class - 2

    Responding a complaint observed: sidewalk shed place installed at expo# 1-2. upon review department record it appear sidewalk shed permit expired on 09/08/2021, creating an unsafe condition for pedestrians.for

    Jun 18, 2024 · Penalty $6,250

    Active
  • Class - 2

    3307.6.5.3 at time of inspection observed: sidewalk shed with wood blocking rotted on vertical components, creating an unsafe condition for public, equipment could collapse seriously injuring pedestrians.. main

    Jun 18, 2024 · Penalty $10,000

    Active
  • Class - 2

    During inspection of a sidewalk shed, research of dob database showed that the sidewalk shed permit expired on 09/08/2021 b00380266-l1-sh with no renewal in the system. as per code all temporary equipment must

    Mar 25, 2023 · Penalty $1,250

    Active
  • Class - 2

    Inspection of a sidewalk shed that had missing bolt caps, which could cause snags and cuts to pedestrians. there was electrical conduit pipe that was broken, hanging and had exposed electrical cables to the pub

    Mar 25, 2023 · Penalty $2,400

    Active
  • Class - 2

    Temporary construction equipment onsite-expired permit.observed sidewalk shed in place at exp1 and 2 with an expired permit.permit in dob now/bis expired on 9/8/2021.remedy:renew permit.

    Apr 4, 2022

    Resolve
  • Class - 2

    Failure to comply with commissioner's order contained in summons/violation #39015263r issued 1/06/20 and file certificate of correction pursuant to 28-201.1 and 1rcny 102-01.for failure to obey vacate order fro

    Jan 6, 2022 · Penalty $3,125

    Resolve
  • Class - 2

    Failure to comply with commissioner's order contained in summons/violation #35462278r issued 11/19/19 and file certificate of correction pursuant to 28-201.1 and 1rcny 102-01.for illegal occupancy with 3 or mor

    Jan 6, 2022 · Penalty $10,000

    Active
  • Class - 2

    Failure to comply with commissioner's order contained in summons/violation #35461176n issued 11/19/19 and file certificate of correction pursuant to 28-201.1 and 1rcny 102-01.for illegal occupancy with 3 or mor

    Jan 6, 2022 · Penalty $10,000

    Active
  • Class - 2

    Failure to comply with the commissioner's order contained in summons/violation#35461180x issued on 11/19/2019 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01.dwelling converted.rem

    Nov 19, 2021 · Penalty $6,250

    Active
  • Class - 2

    Failure to comply with the commissioner's order contained in summons/violation#35461179z issued on 11/19/2019 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01.dwelling converted.rem

    Nov 19, 2021 · Penalty $6,250

    Active
  • Class - 2

    Failure to comply with the commissioner's order contained in summons/violation#35461177p issued on 11/19/2019 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01.dwelling converted.rem

    Nov 19, 2021 · Penalty $6,250

    Active
  • Class - 2

    Failure to comply with the commissioner's order contained in summons/violation#35461181h issued on 11/19/2019 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01.dwelling converted.rem

    Nov 19, 2021 · Penalty $6,250

    Active
  • Class - 2

    Failure to comply w/the comm's order contained in summons/vio#35461176n issued on 11/19/19 & to file a cert of correction pursuant to 28-201.1 & 1rcny 102-01. remedy: comply w/comm's order &/or file a cert of c

    Oct 28, 2021 · Penalty $1,250

    Active
  • Class - 2

    Failure to comply w/the comm's order contained in summons/vio#39015263r issued on 01/06/20 & to file a cert of correction pursuant to 28-201.1 & 1rcny 102-01. remedy: comply w/comm's order &/or file a cert of c

    Oct 28, 2021

    Resolve
  • Class - 1

    Failure to comply w/the comm's order contained in summons/vio#35461182j issued on 11/19/19 & to file a cert of correction pursuant to 28-201.1 & 1rcny 102-01. remedy: comply w/comm's order &/or file a cert of c

    Oct 28, 2021 · Penalty $2,500

    Active
  • Class - 2

    Failure to comply w/the comm's order contained in summons/vio#35461178r issued on 11/19/19 & to file a cert of correction pursuant to 28-201.1 & 1rcny 102-01. remedy: comply w/comm's order &/or file a cert of c

    Oct 28, 2021 · Penalty $1,250

    Active
  • Class - 2

    Failure to comply with the commissioner's order contained in summons/violation#35460181h issued on 11/19/2019 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01.dwelling converted.rem

    Sep 16, 2021 · Penalty $6,250

    Active
  • Class - 2

    Failure to comply with the commissioner's order contained in summons/violation#35961180x issued on 11/19/2019 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01.dwelling converted.rem

    Sep 16, 2021 · Penalty $6,250

    Active
  • Class - 2

    Failure to comply with the commissioner's order contained in summons/violation#35461179z issued on 11/19/2019 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01.multiple dwelling conv

    Sep 16, 2021 · Penalty $6,250

    Active
  • Class - 2

    Failure to comply with the commissioner's order contained in summons/violation#35461177p issued on 11/19/2019 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01.dwelling converted.rem

    Sep 16, 2021 · Penalty $6,250

    Active
  • Class - 2

    Failure to comply w/the comm's order contained in summons/vio#39015263r issued on 01/06/20 & to file a cert of correction pursuant to 28-201.1 & 1rcny 102-01. for: failure to obey a vacate order from the comm's

    Aug 27, 2021 · Penalty $3,125

    Resolve
  • Class - 2

    Failure to comply w/the comm's order contained in summons/vio#35461178r issued on 11/19/19 & to file a cert of correction pursuant to 28-201.1 & 1rcny 102-01. for: dwelling converted/maintained or occupied w/3

    Aug 27, 2021 · Penalty $6,250

    Active
  • Class - 1

    Failure to comply w/the comm's order contained in summons/vio#35461182j issued on 11/19/19 & to file a cert of correction pursuant to 28-201.1 & 1rcny 102-01. for work w/o a permit. note: job#34074698z has been

    Aug 27, 2021 · Penalty $6,250

    Resolve
  • Class - 2

    Failure to comply w/the comm's order contained in summons/vio#35461176n issued on 11/19/19 & to file a cert of correction pursuant to 28-201.1 & 1rcny 102-01. for illegally occupancy w/3 or more additional dwel

    Aug 27, 2021 · Penalty $6,250

    Active
  • Class - 2

    Failure to comply w/the comm's order contained in summons/vio#35461181h issued on 11/19/19 & to file a cert of correction pursuant to 28-201.1 & 1rcny 102-01. for: illegal occupancy w/3 or more additional dwell

    Jul 30, 2021 · Penalty $6,250

    Active
  • Class - 2

    Failure to comply w/the comm's order contained in summons/vio#35461177p issued on 11/19/19 & to file a cert of correction pursuant to 28-201.1 & 1rcny 102-01. for: illegal occupancy w/3 or more additional dwell

    Jul 30, 2021 · Penalty $6,250

    Active
  • Class - 2

    Failure to comply w/the comm's order contained in summons/vio#35461180x issued on 11/19/19 & to file a cert of correction pursuant to 28-201.1 & 1rcny 102-01. for: illegal occupancy w/3 or more additional dwell

    Jul 30, 2021 · Penalty $6,250

    Active
  • Class - 2

    Failure to comply w/the comm's order contained in summons/vio#35461179z issued on 11/19/19 & to file a cert of correction pursuant to 28-201.1 & 1rcny 102-01. for: illegal occupancy w/3 or more additional dwell

    Jul 30, 2021 · Penalty $6,250

    Active
  • Class - 2

    Failure to comply w/commissioner's order contained in summons/v35461180x issued11/19/19&to file c/c pursuant to28-201.1&1rcny102-01.for illegal occupancy w/3or more additional dwelling units.comply w/commission

    May 28, 2021 · Penalty $1,250

    Active
  • Class - 2

    Failure to comply w/commissioner's order contained in summons/v35461179z issued11/19/19&to file c/c pursuant to28-201.1&1rcny102-01.dwellingconverted.comply w/commissioner's order &/or file c/c.

    May 28, 2021 · Penalty $1,250

    Active

Complaints

  • Electric

    No lighting

    Oct 8, 2026 · Apt 2

    Close
  • Electric

    Power outage

    Oct 7, 2026 · Apt TOPFLO

    Close
  • Electric

    Power outage

    Jun 16, 2026 · Apt 2

    Close
  • Water leak

    Slow leak

    Apr 20, 2026 · Apt 3A

    Close
  • Flooring/stairs

    Floor

    Apr 20, 2026 · Apt 3A

    Close
  • Unsanitary condition

    Mold

    Apr 20, 2026 · Apt 3A

    Close
  • Electric

    Wiring

    Apr 20, 2026 · Apt 3A

    Close
  • Plumbing

    Basin/sink

    Apr 20, 2026 · Apt 3A

    Close
  • Paint/plaster

    Ceiling

    Apr 20, 2026 · Apt 3A

    Close
  • Door/window

    Door

    Apr 20, 2026 · Apt 3A

    Close
Show 40 more ↓
  • Paint/plaster

    Wall

    Apr 20, 2026 · Apt 3A

    Close
  • Heat/hot water

    Apartment only

    Jan 15, 2026 · Apt 3

    Close
  • Plumbing

    Basin/sink

    Jan 15, 2026 · Apt 3

    Close
  • Door/window

    Door

    Jan 15, 2026 · Apt 3

    Close
  • Door/window

    Window frame

    Jan 15, 2026 · Apt 3

    Close
  • Unsanitary condition

    Mold

    Jan 15, 2026 · Apt 3

    Close
  • Paint/plaster

    Ceiling

    Jan 15, 2026 · Apt 3

    Close
  • Water leak

    Heavy flow

    Jan 15, 2026 · Apt 3

    Close
  • Electric

    Wiring

    Jan 15, 2026 · Apt 3

    Close
  • Flooring/stairs

    Floor

    Jan 15, 2026 · Apt 3

    Close
  • Heat/hot water

    Entire building

    Dec 8, 2025 · Apt 2

    Close
  • General

    Cooking gas

    Jun 6, 2025 · Apt 3A

    Close
  • Heat/hot water

    Apartment only

    Jun 6, 2025 · Apt 3A

    Close
  • Paint/plaster

    Ceiling

    Jun 6, 2025 · Apt 3A

    Close
  • Electric

    No lighting

    Jun 6, 2025 · Apt 3A

    Close
  • Paint/plaster

    Ceiling

    Jul 6, 2024 · Apt 3A

    Close
  • Unsanitary condition

    Mold

    Jul 6, 2024 · Apt 3A

    Close
  • Water leak

    Slow leak

    Jul 6, 2024 · Apt 3A

    Close
  • Water leak

    Slow leak

    Apr 2, 2024 · Apt 2B

    Close
  • Paint/plaster

    Ceiling

    Apr 2, 2024 · Apt 2B

    Close
  • Heat/hot water

    Entire building

    Dec 12, 2023 · Apt 2B

    Close
  • Paint/plaster

    Ceiling

    Dec 12, 2023 · Apt 2B

    Close
  • Paint/plaster

    Ceiling

    Dec 12, 2023 · Apt 2B

    Close
  • Heat/hot water

    Entire building

    Dec 12, 2023 · Apt 2B

    Close
  • Paint/plaster

    Ceiling

    Nov 13, 2023 · Apt 2B

    Close
  • Paint/plaster

    Ceiling

    Oct 27, 2023 · Apt 2B

    Close
  • Water leak

    Heavy flow

    Oct 27, 2023 · Apt 2B

    Close
  • Paint/plaster

    Ceiling

    Sep 25, 2023 · Apt 4

    Close
  • Water leak

    Heavy flow

    Apr 23, 2023 · Apt 3A

    Close
  • Electric

    No lighting

    Apr 17, 2023 · Apt 3A

    Close
  • Electric

    No lighting

    Nov 1, 2022 · Apt 3A

    Close
  • Electric

    No lighting

    Oct 28, 2022 · Apt 3A

    Close
  • Heat/hot water

    Entire building

    Oct 28, 2022 · Apt BLDG

    Close
  • Door/window

    Window frame

    Feb 27, 2021 · Apt 2B

    Close
  • Paint/plaster

    Wall

    Feb 27, 2021 · Apt 2B

    Close
  • General

    Cabinet

    Feb 27, 2021 · Apt 2B

    Close
  • Flooring/stairs

    Floor

    Feb 27, 2021 · Apt 2B

    Close
  • Paint/plaster

    Ceiling

    Feb 27, 2021 · Apt 2B

    Close
  • Flooring/stairs

    Floor

    Feb 27, 2021 · Apt 2B

    Close
  • Water leak

    Slow leak

    Feb 27, 2021 · Apt 2B

    Close

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Mixed residential and retail building (S5)
Year built
1920
Floors
4
Residential units
6
Building area
6,250 ft²
Lot area
2,500 ft²
Zoning
R6
Community board
301
Council district
34
Block / lot
3053 / 8
Assessed value
$562,050
Landmark / historic district
No

HPD registration #311454, last renewed Jul 8, 2025.

Questions about 182 Graham Avenue

Who owns 182 Graham Avenue?

The owner of record in NYC Department of City Planning PLUTO data is Port Rich Realty INC.

Does 182 Graham Avenue have violations?

Yes. NYC HPD has recorded 222 housing violations at this property.

Is 182 Graham Avenue rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 182 Graham Avenue built?

City records list 1920 as the year it was built.

How many apartments are in 182 Graham Avenue?

It has 6 residential units and 7 units in total.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.