roofy

209 Jackson Street

Brooklyn, NY 11211BBL 3-02875-0030Map

Owner of record: 209 Jackson LLC

209 Jackson Street is a walk-up apartment building built in 1910 in Brooklyn, 11211. It has 7 residential units across 4 floors. The owner of record is 209 Jackson LLC. HPD has recorded 19 housing violations here, most recently on February 25, 2022. 1 of the 19 most recent violations are still open.

HPD violations
19
DOB violations
8
ECB violations
16
HPD complaints
4

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
Last violation Feb 25, 2022

Date of the most recent HPD inspection that found a problem.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 19

  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Feb 25, 2022

    Closed — Violation dismissed
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Apr 9, 2021

    Closed — Violation dismissed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Oct 30, 2019

    Closed — Violation dismissed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Oct 18, 2018

    Closed — Violation dismissed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 24, 2017

    Closed — Violation dismissed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 9, 2016

    Closed — Violation dismissed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Oct 9, 2015

    Closed — Violation dismissed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Feb 23, 2015

    Closed — Violation dismissed
  • B

    D26-19.05 adm code provide adequate light of not less than 60 watts incandescent or equivalent illumination public halls all stys.

    May 20, 1987

    Closed — Violation closed
  • A

    D26-21.03 adm code paint or post a sign indicating floors public halls all stys.

    May 20, 1987

    Closed — Violation closed
Show 9 more ↓
  • B

    D26-32.01 adm code discontinue unlawful cooking space or file plans and application with this department to legalize same, if lawfully feasible, gas range in cellar.

    May 20, 1987

    Closed — Violation closed
  • A

    D26-20.08,20.09 adm code file certification of satisfactory installation of smoke detecting device in accordance with h.p.d. rules and regulations.

    May 20, 1987

    Closed — Violation closed
  • B

    D26-10.01 adm code properly repair with similar material the broken or defective plasterboard clg cellar front.

    May 20, 1987

    Closed — Violation closed
  • A

    § 300 m/d law file plans and application and legalize the following alteration or restore to the legal condition existing prior to the making of said alteration wood partitions & paneling erected creating recreation room cellar thru out.

    May 20, 1987

    Open — Not complied with
  • B

    D26-19.07 adm code provide adequate lighting at or near the outside of the front entranceway of the building and keep same burning from sunset every day to sunrise on the day following 50 watts night inspection.

    May 20, 1987

    Closed — Violation closed
  • A

    D26-10.01 adm code properly repair the broken or defective mailboxes vestibule 1 sty.

    May 20, 1987

    Closed — Violation closed
  • B

    D26-10.01 adm code repair the broken or defective plastered surfaces and paint in a uniform color ceiling 1 sty public hall rear.

    May 20, 1987

    Closed — Violation closed
  • A

    D26-12.01 adm code paint with light colored paint to the satisfaction of this department walls & ceilings 1 & 2 sty public halls.

    May 20, 1987

    Closed — Violation closed
  • C

    D26-17.10 adm code post notice, in form approved by the department, stating the name and location of the person designated by the owner to have key to building's heating system 1 sty public hall & on boiler room door.

    May 20, 1987

    Closed — Violation closed

DOB building violations · 8

  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jan 9, 2019

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jan 9, 2019

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Nov 14, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Nov 14, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Nov 14, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Nov 14, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Nov 14, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Nov 14, 2018

    Dob violation - dismissed

ECB violations · 16

  • Class - 2

    Failure to meet interior lighting power requirements. alt job #321186211 during an energy code compliance inspection i observed that interior lighting fixtures on all floors have been installed in excess of and

    Feb 26, 2019

    Resolve
  • Class - 1

    Bc3301.5 unsafe condition and equipment. it was discovered that during a hoisting operation of steel, 16 hour rigging worker, wilmer dejesus rodriguez castellon was using contruction equipment in an unsafe mann

    Aug 24, 2018 · Penalty $6,250

    Resolve
  • Class - 1

    Supervision or use of power-operated hoisting machine without a hoisting machine operator's license. at time of inspection, it was discovered that yovcho d. argirov was erecting steel by use of a knuckle boom c

    Aug 24, 2018 · Penalty $5,000

    Resolve
  • Class - 1

    Operating an articulating boom crane w/o a certificate of operation atthe time observed. at time of inspection, it was discovered that a knuckleboom crane (pm 210028 sp;serial#614400111635)was being used to ere

    Aug 24, 2018 · Penalty $5,000

    Resolve
  • Class - 1

    Bc3301.5 unsafe conditions and equipment. it was discovered that during a steel erection operation (hoisting by use of knuckleboom), 16 hour rigging worker, wilmer dejesus rodriguez castellon was using construc

    Aug 24, 2018

    Resolve
  • Class - 1

    Inadequate safety measures; operation of crane hoisting equipment in an unsafe manner. at time of inspection, a knuckleboom crane was discovered erecting steel in an unsafe manner. the knuckleboom's passenger s

    Aug 24, 2018 · Penalty $10,000

    Resolve
  • Class - 1

    Inadequate safety measures; operation of crane hoisting equipment in an unsafe manner. at time of inspection, a knuckleboom crane was discovered erecting steel in an unsafe manner. the knuckleboom's passenger s

    Aug 24, 2018 · Penalty $10,000

    Resolve
  • Class - 1

    Operating an articulating boom crane without a certificate of operation. at the time observed, it was discovered that a knuckleboom was being used to erect steel without a valid certificate of operation. the kn

    Aug 24, 2018 · Penalty $5,000

    Resolve
  • Class - 2

    Operation of crane/derrick without a certificate of onsite inspection. at time of inspection, it was discovered that a knuckleboom crane was being used to erect steel (construction operation) without a certific

    Aug 24, 2018 · Penalty $5,000

    Resolve
  • Class - 1

    Supervision or use of power-operated hoisting machine w/o a hoisting machine operator's license. at time of inspection, it was discovered that yovcho d. argirov was erecting steel by use of a knuckleboom crane

    Aug 24, 2018 · Penalty $5,000

    Resolve
Show 6 more ↓
  • Class - 1

    Supervision or use of power-operated hoisting machine without a hoisting machine operator's license. at time of inspection, it was discovered that yovhco d. argirov was erecting steeel by use of a knuckleboom c

    Aug 24, 2018

    Resolve
  • Class - 1

    Supervision or use of power-operated hoisting machine without a hoisting machine operator's license. at time of inspections it was discovered that yovcho d. argirov was erecting steel by use of a knuckleboom cr

    Aug 24, 2018 · Penalty $5,000

    Resolve
  • Class - 1

    Bc3301.5 unsafe conditions and equipment. it was discovered that during a hoisting operation of steel, 16 hour rigging worker, wilmer dejesus rodriguez castellon was using construction equipment in an unsafe ma

    Aug 24, 2018 · Penalty $2,500

    Resolve
  • Class - 1

    Operating on articulating boom crane without a certificate of operation. at the time observed, it was discovered that a knuckleboom was being used to erect steel without a valid certificate of operation. the kn

    Aug 24, 2018 · Penalty $5,000

    Resolve
  • Class - 2

    Work does not conform to approved construction documents.noted:at the time of inspection approved only specify removal of partitions & wallsjobsite currently under a full gut renovation throughout.no specs on s

    Feb 23, 2018 · Penalty $250

    Resolve
  • Class - 2

    Bc3303.3;bc3307.4/no flag person/no certificate.noted:at the time of inspection observed street closure with no flag man in place,during knuckle boom truck delivery at expo#1.rem:provide flag person/obtain cert

    Feb 23, 2018

    Resolve

Complaints

  • Unsanitary condition

    Pests

    Feb 24, 2020 · Apt 1A

    Close
  • Unsanitary condition

    Pests

    Feb 24, 2020 · Apt 1A

    Close
  • Unsanitary condition

    Pests

    Feb 24, 2020 · Apt 1A

    Close
  • Unsanitary condition

    Pests

    Jan 28, 2020 · Apt 1A

    Close

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Walk-up apartment building (C1)
Year built
1910
Floors
4
Residential units
7
Building area
4,955 ft²
Lot area
2,500 ft²
Zoning
R6B
Community board
301
Council district
34
Block / lot
2875 / 30
Assessed value
$688,050
Landmark / historic district
No

HPD registration #343503, last renewed Jul 15, 2025.

Questions about 209 Jackson Street

Who owns 209 Jackson Street?

The owner of record in NYC Department of City Planning PLUTO data is 209 Jackson LLC.

Does 209 Jackson Street have violations?

Yes. NYC HPD has recorded 19 housing violations at this property.

Is 209 Jackson Street rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 209 Jackson Street built?

City records list 1910 as the year it was built.

How many apartments are in 209 Jackson Street?

It has 7 residential units.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.