60 Kingsland Avenue
Brooklyn, NY 11211BBL 3-02867-0001Map
Owner of record: NYC Housing Authority
60 Kingsland Avenue is an elevator apartment building built in 1950 in Brooklyn, 11211. It has 700 residential units across 8 floors. The owner of record is NYC Housing Authority. HPD has recorded 16 housing violations here, most recently on October 26, 2018. 11 of the 16 most recent violations are still open.
- HPD violations
- 16
- DOB violations
- 108
- ECB violations
- 64
- HPD complaints
- 71
What to know
Immediately hazardous issues among recent violations are still open.
Date of the most recent HPD inspection that found a problem.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 16
- IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Oct 26, 2018
Closed — Violation dismissed - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Dec 11, 2017
Closed — Violation dismissed - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Nov 29, 2016
Closed — Violation dismissed - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Oct 20, 2015
Closed — Violation dismissed - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Mar 5, 2015
Closed — Violation dismissed - CImmediately hazardous
Correct the lead-based paint hazard - presumed lead paint that is peeling or on a deteriorated subsurface using work practices set forth in 28 rcny §11-06(b)(2) ceiling, north wall, east wall in the bathroom located at apt 7g, 7th story, 1st apartment from south at west
Mar 21, 2010 · Apt 7G
Open — Nov sent out - CImmediately hazardous
Correct the lead-based paint hazard - presumed lead paint that is peeling or on a deteriorated subsurface using work practices set forth in 28 rcny §11-06(b)(2) 1st door from west at north wall in the 2nd room from north at west located at apt 7g, 7th story, 1st apartment from south at west
Mar 21, 2010 · Apt 7G
Open — Nov sent out - CImmediately hazardous
Correct the lead-based paint hazard - presumed lead paint that is peeling or on a deteriorated subsurface using work practices set forth in 28 rcny §11-06(b)(2) south wall in the 1st room from north at west located at apt 7g, 7th story, 1st apartment from south at west
Mar 21, 2010 · Apt 7G
Open — Nov sent out - CImmediately hazardous
Correct the lead-based paint hazard - presumed lead paint that is peeling or on a deteriorated subsurface using work practices set forth in 28 rcny §11-06(b)(2) 1st radiator from south at west wall in the kitchen located at apt 7g, 7th story, 1st apartment from south at west
Mar 21, 2010 · Apt 7G
Open — Nov sent out - CImmediately hazardous
Correct the lead-based paint hazard - presumed lead paint that is peeling or on a deteriorated subsurface using work practices set forth in 28 rcny §11-06(b)(2) east wall, west wall in the foyer located at apt 7g, 7th story, 1st apartment from south at west
Mar 21, 2010 · Apt 7G
Open — Nov sent out
Show 6 more ↓
- CImmediately hazardous
Correct the lead-based paint hazard - presumed lead paint that is peeling or on a deteriorated subsurface using work practices set forth in 28 rcny §11-06(b)(2) north wall, west wall in the 2nd room from north at east located at apt 7g, 7th story, 1st apartment from south at west
Mar 21, 2010 · Apt 7G
Open — Nov sent out - CImmediately hazardous
Correct the lead-based paint hazard - presumed lead paint that is peeling or on a deteriorated subsurface using work practices set forth in 28 rcny §11-06(b)(2) south wall in the private hallway located at apt 7g, 7th story, 1st apartment from south at west
Mar 21, 2010 · Apt 7G
Open — Nov sent out - BHazardous
D26-16.01 adm code remove all obstructions and repair all defects in bathtub 2 sty apt 2f. located at apt 2f
May 18, 1982 · Apt 2F
Open — Nov sent out - BHazardous
D26-10.01 adm code repair the broken or defective plastered surfaces and paint in a uniform color clg bathroom 4 sty apt 4l. , section '' ''
May 18, 1982 · Apt 4L
Open — Nov sent out - BHazardous
D26-16.01 adm code repair the leaky and/or defective water supply pipe bottom of water tank bathroom 4 sty apt 4l. , section '' ''
May 18, 1982 · Apt 4L
Open — Nov sent out - BHazardous
D26-16.01 adm code remove all obstructions and repair all defects in bathtub 4 sty apt 4l. , section '' ''
May 18, 1982 · Apt 4L
Open — Nov sent out
DOB building violations · 108
- Construction other optional
Borough commissioner has ordered all work stopped under permit #b00448967-i1 on 11/13/25 due to special inspector withdrawal.
Apr 21, 2026
Dob violation - active - Failure to submit eer none
Failure to submit an eer per ad. code sec. 28-308.4 - multiple years (2023)
Jun 23, 2024
Dob violation - dismissed - Failure to submit eer none
Failure to submit an eer per ad. code sec. 28-308.4 - multiple years (2022)
Apr 22, 2023
Dob violation - dismissed - No report and / or late filing (facade) facade required
Failed to file fisp cycle 9b technical report by 2/21/2023
Feb 22, 2023
Dob violation - active - No report and / or late filing (facade) facade required
Failed to file fisp cycle 9b technical report by 2/21/2023
Feb 22, 2023
Dob violation - active - No report and / or late filing (facade) facade required
Failed to file fisp cycle 9b technical report by 2/21/2023
Feb 22, 2023
Dob violation - active - No report and / or late filing (facade) facade required
Failed to file fisp cycle 9b technical report by 2/21/2023
Feb 22, 2023
Dob violation - active - No report and / or late filing (facade) facade required
Failed to file fisp cycle 9b technical report by 2/21/2023
Feb 22, 2023
Dob violation - active - No report and / or late filing (facade) facade required
Failed to file fisp cycle 9b technical report by 2/21/2023
Feb 22, 2023
Dob violation - active - No report and / or late filing (facade) facade required
Failed to file fisp cycle 9b technical report by 2/21/2023
Feb 22, 2023
Dob violation - active
Show 40 more ↓
- No report and / or late filing (facade) facade required
Failed to file fisp cycle 9b technical report by 2/21/2023
Feb 22, 2023
Dob violation - active - No report and / or late filing (facade) facade required
Failed to file fisp cycle 9b technical report by 2/21/2023
Feb 22, 2023
Dob violation - active - No report and / or late filing (facade) facade required
Failed to file fisp cycle 9b technical report by 2/21/2023
Feb 22, 2023
Dob violation - active - No report and / or late filing (facade) facade required
Failed to file fisp cycle 9b technical report by 2/21/2023
Feb 22, 2023
Dob violation - active - Failure to submit eer none
Failure to submit an eer per ad. code sec. 28-308.4 - multiple years (2021)
Aug 21, 2022
Dob violation - dismissed - Nycha elevator periodic inspection/test elevatorrequired
Failure to perform category 5 inspection
Dec 17, 2021
Dob violation - dismissed - Nycha elevator periodic inspection/test elevatorrequired
Failure to perform category 5 inspection
Dec 17, 2021
Dob violation - dismissed - Nycha elevator periodic inspection/test elevatorrequired
Failure to perform category 5 inspection
Dec 17, 2021
Dob violation - dismissed - Nycha elevator periodic inspection/test elevatorrequired
Failure to perform category 5 inspection
Dec 17, 2021
Dob violation - dismissed - Nycha elevator periodic inspection/test elevatorrequired
Failure to perform category 5 inspection
Dec 17, 2021
Dob violation - dismissed - Nycha elevator periodic inspection/test elevatorrequired
Failure to perform category 5 inspection
Dec 17, 2021
Dob violation - dismissed - Nycha elevator periodic inspection/test elevatorrequired
Failure to perform category 5 inspection
Dec 17, 2021
Dob violation - dismissed - Nycha elevator periodic inspection/test elevatorrequired
Failure to perform category 5 inspection
Dec 17, 2021
Dob violation - dismissed - Nycha elevator periodic inspection/test elevatorrequired
Failure to perform category 5 inspection
Dec 17, 2021
Dob violation - dismissed - Nycha elevator periodic inspection/test elevatorrequired
Failure to perform category 5 inspection
Dec 17, 2021
Dob violation - dismissed - Nycha elevator periodic inspection/test elevatorrequired
Failure to perform category 5 inspection
Dec 17, 2021
Dob violation - dismissed - Nycha elevator periodic inspection/test elevatorrequired
Failure to perform category 5 inspection
Dec 17, 2021
Dob violation - dismissed - Nycha elevator periodic inspection/test elevatorrequired
Failure to perform category 5 inspection
Dec 17, 2021
Dob violation - dismissed - Failure to submit eer none
Failure to submit an eer per ad. code sec. 28-308.4 - multiple years (2020)
Jun 20, 2021
Dob violation - dismissed - Failure to submit eer none
Failure to submit an eer per ad. code sec. 28-308.4 - multiple years (2019)
Jun 29, 2020
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Apr 21, 2020
Dob violation - resolved - Failure to submit eer none
Failure to submit an eer per ad. code sec. 28-308.4 in 2017
Mar 27, 2018
Dob violation - dismissed - Elevator affirmation of correction elevatorrequired
Vio issued to nycha elevator - fail to correct defects on 2016 cat 1 insp/tst
Jan 26, 2018
Dob violation - dismissed - Elevator affirmation of correction elevatorrequired
Vio issued to nycha elevator - fail to correct defects on 2016 cat 1 insp/tst
Jan 26, 2018
Dob violation - dismissed - Elevator affirmation of correction elevatorrequired
Vio issued to nycha elevator - fail to correct defects on 2015 cat 1 insp/tst
Jan 3, 2017
Dob violation - dismissed - Elevator affirmation of correction elevatorrequired
Vio issued to nycha elevator - fail to correct defects on 2015 cat 1 insp/tst
Jan 3, 2017
Dob violation - dismissed - No report and / or late filing (facade) facade required
Failed to file fisp cycle 7b technical report by 08/21/2012
Aug 30, 2013
Dob violation - dismissed - No report and / or late filing (facade) facade required
Failed to file fisp cycle 7b technical report by 08/21/2012
Aug 30, 2013
Dob violation - dismissed - No report and / or late filing (facade) facade required
Failed to file fisp cycle 7b technical report by 08/21/2012
Aug 30, 2013
Dob violation - dismissed - No report and / or late filing (facade) facade required
Failed to file fisp cycle 7b technical report by 08/21/2012
Aug 30, 2013
Dob violation - dismissed - No report and / or late filing (facade) facade required
Failed to file fisp cycle 7b technical report by 08/21/2012
Aug 30, 2013
Dob violation - dismissed - No report and / or late filing (facade) facade required
Failed to file fisp cycle 7b technical report by 08/21/2012
Aug 30, 2013
Dob violation - dismissed - No report and / or late filing (facade) facade required
Failed to file fisp cycle 7b technical report by 08/21/2012
Aug 30, 2013
Dob violation - dismissed - No report and / or late filing (facade) facade required
Failed to file fisp cycle 7b technical report by 08/21/2012
Aug 30, 2013
Dob violation - dismissed - No report and / or late filing (facade) facade required
Failed to file fisp cycle 7b technical report by 08/21/2012
Aug 30, 2013
Dob violation - dismissed - No report and / or late filing (facade) facade required
Failed to file fisp cycle 7b technical report by 08/21/2012
Aug 30, 2013
Dob violation - dismissed - No report and / or late filing (facade) facade required
Failed to file fisp cycle 7b technical report by 08/21/2012
Aug 30, 2013
Dob violation - dismissed - Facade facade optional
Cycle 7 unsafe report filed
Aug 1, 2013
Dob violation - dismissed - Facade facade optional
Cycle 7 unsafe report filed
Aug 1, 2013
Dob violation - dismissed - Facade facade optional
Cycle 7 unsafe report filed
Aug 1, 2013
Dob violation - dismissed
ECB violations · 64
- Class - 2
Failure to submit an acceptable required cycle 9b report of critical examination documenting condition of exterior wall and appurtenances required by 28-302.4 for control#909612.rem:submit acceptable required t
Apr 11, 2024 · Penalty $1,250
Active - Class - 2
Failure to submit an acceptable required cycle 9b report of critical examination documenting condition of exterior wall and appurtenances required by 28-302.4 for control#909615.rem#submit acceptable required t
Apr 11, 2024 · Penalty $1,250
Active - Class - 2
Failure to submit an acceptable required cycle 9b report of critical examination documenting condition of exterior wall and appurtenances required by 28-302.4 for control#909624.rem:submit acceptable required t
Apr 11, 2024 · Penalty $1,250
Active - Class - 2
Failure to submit an acceptable required cycle 9b report of critical examination documenting condition of exterior wall and appurtenances required by 28-302.4 for control#909619.rem:submit acceptable required t
Apr 11, 2024 · Penalty $1,250
Active - Class - 2
Water leak on drain pipe behind boiler 03, correct violating condition& submit a certificate of correction
Mar 30, 2021 · Penalty $625
Resolve - Class - 2
Steam leak on press control manifold, valve body discharge on relief valve not piped down,bolts missing from frt access panel. correct violaing conditions & submit a certificate of correction
Jan 4, 2019
Resolve - Class - 2
Boiler inoperative ,being over-hauled.body discharge on relief valve not piped down. corr violating conditions & submit a cert. of correction
Jan 4, 2019
Resolve - Class - 2
Gas valve defective, steam leak on pressure gauge manifold. frt access panel bolts missing ,body discharge on relief valve to be piped down. correct violating conditions & submit a certificate of correction
Jan 4, 2019
Resolve - Class - 2
Boiler inoperative,being over-hauled.body discharge on relief valve to be piped down.correct violating conditions & submit a certificate of correction
Jan 4, 2019
Resolve - Class - 1
3314.15.2 suspended scaffold does not meet bldg code specifications,stop all work.noted:@ time of inspection suspended scaffold on exposure #1(jackson st)was set up in a unsafe manner.stirrup/hanger were approx
Mar 18, 2014 · Penalty $1,600
Resolve
Show 40 more ↓
- Class - 2
Failure to file an amended 6th round report acceptable to this dept indicating correction of unsafe conditions described in initial local law 11/98 report. 36013851p. remedy: file an amended report following
Dec 17, 2010
Resolve - Class - 2
Fail to file an amended 6th round report acceptable to this dept indicating correction of unsafe conditions described in initial local law 11/98 report.36009929y.rem:file an amended report following remedial re
Jul 16, 2010
Resolve - Class - 2
Fail to file an amended 6th round report acceptable to this dept indicating correction of unsafe conditions described in initial local law 11/98 report.36009930l.rem:file an amended report following remedial re
Jul 16, 2010
Resolve - Class - 2
Fail to file an amended 6th round report acceptable to this dept indicating correction of unsafe conditions described in initial local law 11/98 report.36009928m.rem:file an amended report following remedial re
Jul 16, 2010
Resolve - Class - 2
Fail to file an amended 6th round report acceptable to this dept indicating correction of unsafe conditions described in initial local law 11/98 report.36009933r.rem:file an amended report following remedial re
Jul 16, 2010
Resolve - Class - 2
Fail to file an amended 6th round report acceptable to this dept indicating correction of unsafe conditions described in initial local law 11/98 report.36009931n.rem:file an amended report following remedial re
Jul 16, 2010
Resolve - Class - 2
Fail to file an amended 6th round report acceptable to this dept indicating correction of unsafe conditions described in initial local law 11/98 report.36009932p.rem:file an amended report following remedial re
Jul 16, 2010
Resolve - Class - 2
Failure to file an amende 6th round report acceptable to this dept indcating correction of unsafe conditions described in initial local law 11/98report.rem:file an amended report following remedial repairs of t
Jun 25, 2010
Resolve - Class - 1
28-302.5.local law report filed as "unsafe"by architect/engineer-no amended report was filed "unsafe conditions"require safety provisions for public as per code 27-129(d),1rcny 32-03(b)(5)(c).no sidewalk shed,f
Jan 11, 2010
Resolve - Class - 1
28-302.5.local law report filed as "unsafe"by architect/engineer-no amended report was filed "unsafe conditions"require safety provisions for public as per code 27-129(d),1rcny 32-03(b)(5)(c).no sidewalk shed,f
Jan 11, 2010
Resolve - Class - 1
28-302.5.local law report filed as "unsafe"by architect/engineer-no amended report was filed "unsafe conditions"require safety provisions for public as per code 27-129(d),1rcny 32-03(b)(5)(c).no sidewalk shed,f
Jan 11, 2010
Resolve - Class - 1
28-302.5.local law report filed as "unsafe"by architect/engineer-no amended report was filed "unsafe conditions"require safety provisions for public as per code 27-129(d),1rcny 32-03(b)(5)(c).no sidewalk shed,f
Jan 11, 2010
Resolve - Class - 1
28-302.5.local law report filed as "unsafe"by architect/engineer-no amended report was filed "unsafe conditions"require safety provisions for public as per code 27-129(d),1rcny 32-03(b)(5)(c).no sidewalk shed,f
Jan 11, 2010
Resolve - Class - 1
28-302.5.local law report filed as "unsafe"by architect/engineer-no amended report was filed "unsafe conditions"require safety provisions for public as per code 27-129(d),1rcny 32-03(b)(5)(c).no sidewalk shed,f
Jan 11, 2010
Resolve - Class - 2
Failure to file an acceptable sixth round technical report in compliance w/code provisions:periodic inspection of exterior walls and appurtenances as required by article 28.302 and the dob rules and regulations
Jan 7, 2010
Resolve - Class - 2
Failure to file an amended sixth round report acceptable to this dept indicating correction of unsafe conditions described in initial local law 11/98 report rem: file an amended report following remedial repair
Dec 23, 2009
Resolve - Class - 2
Failure to file an amended sixth round report acceptable to this department indicating correction of unsafe conditions described in initial local law 11/98 report. remedy: file an amended report following remed
Oct 23, 2009
Resolve - Class - 2
Failure to file an amended sixth round report acceptable to this department indicating correction of unsafe conditions described in initial local law 11/98 report. remedy: file an amended report following remed
Oct 23, 2009
Resolve - Class - 2
Failure to file an amended sixth round report acceptable to this department indicating correction of unsafe conditions described in initial local law 11/98 report. remedy: file an amended report following remed
Oct 23, 2009
Resolve - Class - 2
Failure to file an amended sixth round report acceptable to this department indicating correction of unsafe conditions described in initial local law 11/98 report. remedy: file an amended report following remed
Oct 23, 2009
Resolve - Class - 2
Failure to file an amended fifth round report acceptable to this dept indicating correction of unsafe conditions described in initial local law 11/98 report remedy:file an amended report following repairs of th
Oct 23, 2009
Resolve - Class - 2
Failure to file an amended sixth round report acceptable to this department indicating correction of unsafe conditions described in initial local law 11/98 report. remedy: file an amended report following remed
Oct 23, 2009
Resolve - Class - 2
Failure to file an amended sixth round report acceptable to this department indicating correction of unsafe conditions described in initial local law 11/98 report. remedy: file an amended report following remed
Oct 23, 2009
Resolve - Class - 1
97x17. (97x17) repair door operator and dust cover on hoistway door secure all call dob for reinspection prior to service 212 5665544.
Jul 13, 2009
Resolve - Class - 2
Failure to file an amended sixth round report acceptable to this dept indicating correction of unsafe conditions described in initial local law 11/98 report remedy:file an amended report following remedial repa
May 22, 2009
Resolve - Class - 2
Failure to file an amended sixth round report acceptable to this dept indicating correction of unsafe conditions described in initial local law 11/98 report remedy:file an amended report following remedial repa
May 22, 2009
Resolve - Class - 2
Failure to file an amended sixth round report acceptable to this dept indicating correction of unsafe conditions described in initial local law 11/98 report remedy:file an amended report following remedial repa
May 22, 2009
Resolve - Class - 2
Failure to file an amended sixth round report acceptable to this dept indicating correction of unsafe conditions described in initial local law 11/98 report remedy:file an amended report following remedial repa
May 22, 2009
Resolve - Class - 2
Failure to file an amended sixth round report acceptable to this dept indicating correction of unsafe conditions described in initial local law 11/98 report remedy:file an amended report following remedial repa
May 22, 2009
Resolve - Class - 2
Failure to file an amended sixth round report acceptable to this dept indicating correction of unsafe conditions described in initial local law 11/98 report remedy:file an amended report following remedial repa
May 22, 2009
Resolve - Class - 2
Failure to submit an acceptable sixth round technical report in compliance w/code provisions:periodic inspection of exterior walls and appurtenances as required by article 28.302 & the dob rules & regulations
Mar 27, 2009
Resolve - Class - 2
Failure to submit an acceptable sixth round technical report in compliance w/code provisions:periodic inspection of exterior walls and appurtenances as required by article 28.302 & the dob rules & regulations
Mar 27, 2009
Resolve - Class - 2
Failure to maintain exterior building east elevationn show vertical and step cracks and seperating in its parapet. extensive bowing and deteriorating in lintel facade; parapet pushed out and deteriorating in s
Dec 18, 2008
Resolve - Class - 2
100x10. 100x car exhaust fan.
Dec 17, 2008
Resolve - Class - 1
01x10,02x10. 01-x stop sw crazy glued, alarm also. cease use item 01-x
Dec 17, 2008
Resolve - Class - 2
05h11. 05h car door hanger rollers.
Dec 17, 2008
Resolve - Class - 2
Failure to file an amended sixth round report acceptable to this dept indicating correction of unsafe conditions described in initial local law 11/98 report. remedy: file an amended report following remedial
Nov 28, 2008
Resolve - Class - 2
Failure to file an amended sixth round report acceptable to this dept indicating correction of unsafe conditions described in initial local law 11/98 report. remedy: file an amended report following remedial
Nov 28, 2008
Resolve - Class - 2
Failure to file an amended sixth round report acceptable to this dept indicating correction of unsafe conditions described in initial local law 11/98 report. remedy: file an amended report following remedial
Nov 28, 2008
Resolve - Class - 2
Failure to file an amended sixth round report acceptable to this dept indicating correction of unsafe conditions described in initial local law 11/98 report. remedy: file an amended report following remedial
Nov 28, 2008
Resolve
Complaints
- Water leak
Slow leak
Aug 28, 2021 · Apt 9R
Close - Heat/hot water
Apartment only
Nov 3, 2020 · Apt 9R
Close - Heat/hot water
Apartment only
Oct 18, 2019 · Apt 7R
Close - Heat/hot water
Entire building
Jan 31, 2019 · Apt BLDG
Close - Unsanitary condition
Pests
Nov 17, 2017 · Apt 1F
Close - Unsanitary condition
Pests
Nov 17, 2017 · Apt 1F
Close - Door/window
Door
Nov 17, 2017 · Apt 1F
Close - General
Ventilation system
Sep 19, 2017 · Apt 1F
Close - Unsanitary condition
Pests
Sep 19, 2017 · Apt 1F
Close - General
Ventilation system
Sep 19, 2017 · Apt 1F
Close
Show 40 more ↓
- Electric
Lighting
Sep 19, 2017 · Apt 1F
Close - Unsanitary condition
Pests
Sep 19, 2017 · Apt 1F
Close - Unsanitary condition
Mold
Sep 19, 2017 · Apt 1F
Close - Unsanitary condition
Garbage/recycling storage
Sep 19, 2017 · Apt 1F
Close - Door/window
Door
Sep 19, 2017 · Apt 1F
Close - Door/window
Door frame
Sep 19, 2017 · Apt 1F
Close - Unsanitary condition
Pests
Sep 5, 2017 · Apt 1F
Close - Unsanitary condition
Garbage/recycling storage
Sep 5, 2017 · Apt 1F
Close - General
Ventilation system
Sep 5, 2017 · Apt 1F
Close - Unsanitary condition
Pests
Sep 5, 2017 · Apt 1F
Close - Unsanitary condition
Pests
Sep 5, 2017 · Apt 1F
Close - Door/window
Door
Sep 5, 2017 · Apt 1F
Close - Electric
Lighting
Sep 5, 2017 · Apt 1F
Close - Unsanitary condition
Mold
Sep 5, 2017 · Apt 1F
Close - General
Ventilation system
Sep 5, 2017 · Apt 1F
Close - Water leak
Slow leak
Jun 20, 2017 · Apt 7
Close - Unsanitary condition
Mold
Feb 10, 2017 · Apt 1F
Close - Door/window
Door
Feb 10, 2017 · Apt 1F
Close - Door/window
Door frame
Feb 10, 2017 · Apt 1F
Close - Unsanitary condition
Pests
Feb 10, 2017 · Apt 1F
Close - General
Ventilation system
Feb 10, 2017 · Apt 1F
Close - General
Ventilation system
Feb 10, 2017 · Apt 1F
Close - Unsanitary condition
Garbage/recycling storage
Feb 10, 2017 · Apt 1F
Close - Unsanitary condition
Pests
Feb 10, 2017 · Apt 1F
Close - Unsanitary condition
Mold
Feb 10, 2017 · Apt 1F
Close - Unsanitary condition
Pests
Feb 1, 2017 · Apt 1F
Close - Electric
Lighting
Feb 1, 2017 · Apt 1F
Close - Door/window
Door
Oct 18, 2016 · Apt 7RR
Close - Flooring/stairs
Floor
Oct 18, 2016 · Apt 7RR
Close - Flooring/stairs
Floor
Oct 18, 2016 · Apt 7RR
Close - Flooring/stairs
Floor
Oct 18, 2016 · Apt 7RR
Close - Unsanitary condition
Pests
Oct 18, 2016 · Apt 7RR
Close - Electric
No lighting
Oct 18, 2016 · Apt 7RR
Close - Heat/hot water
Apartment only
Feb 14, 2016 · Apt 1
Close - Unsanitary condition
Mold
Aug 12, 2015 · Apt 1
Close - Paint/plaster
Wall
Aug 12, 2015 · Apt 1
Close - Door/window
Door frame
Aug 12, 2015 · Apt 1
Close - General
Ventilation system
Aug 12, 2015 · Apt 1
Close - Flooring/stairs
Floor
Aug 12, 2015 · Apt 1
Close - Water leak
Heavy flow
Jun 15, 2015 · Apt 1
Close
Sales history
No recorded sales in our data
Building details
- Building type
- Elevator apartment building (D3)
- Year built
- 1950
- Floors
- 8
- Residential units
- 700
- Building area
- 611,340 ft²
- Lot area
- 510,960 ft²
- Zoning
- R6
- Community board
- 301
- Council district
- 34
- Block / lot
- 2867 / 1
- Assessed value
- $27,557,100
- Landmark / historic district
- No
Questions about 60 Kingsland Avenue
Who owns 60 Kingsland Avenue?
The owner of record in NYC Department of City Planning PLUTO data is NYC Housing Authority.
Does 60 Kingsland Avenue have violations?
Yes. NYC HPD has recorded 16 housing violations at this property.
Is 60 Kingsland Avenue rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 60 Kingsland Avenue built?
City records list 1950 as the year it was built.
How many apartments are in 60 Kingsland Avenue?
It has 700 residential units.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.