113 South 2 Street
Brooklyn, NY 11249BBL 3-02405-7501Map
Owner of record: Unavailable Owner
113 South 2 Street is a condominium built in 2005 in Brooklyn, 11249. It has 8 residential units across 4 floors. The owner of record is Unavailable Owner. HPD has recorded 13 housing violations here, most recently on November 15, 2022. 2 of the 13 most recent violations are still open.
- HPD violations
- 13
- DOB violations
- 0
- ECB violations
- 20
- HPD complaints
- 2
What to know
Immediately hazardous issues among recent violations are still open.
Date of the most recent HPD inspection that found a problem.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 13
- IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Nov 15, 2022
Closed — Violation dismissed - BHazardous
Properly repair the broken or defective wall light fixture at building front south yard
May 14, 2019
Closed — Violation closed - CImmediately hazardous
Remove the illegal fastening consisting heavy duty magnetic lock installed at building vestibule door , 1st story
May 14, 2019
Open — Not complied with - BHazardous
Provide heavy duty mortise lock at building vestibule door , 1st story
May 14, 2019
Open — Not complied with - ANon-hazardous
Post and maintain a proper sign on wall of entrance story showing the registration number assigned by the department and the address of the building. at public hall, 1st story
May 14, 2019
Closed — Violation closed - ANon-hazardous
Post, in a form approved by the commissioner, and maintain a notice in a common area of the building regarding the procedures that should be followed when a gas leak is suspected at public hall, 1st story
May 14, 2019
Closed — Violation closed - ANon-hazardous
Post a proper notice of carbon monoxide detecting device requirements, in a form approved by the commissioner, in a common area of a class a multiple dwelling near inspection certificate or provide notice to tenants in a private dwelling. at public hall, 1st story
May 14, 2019
Closed — Violation closed - ANon-hazardous
§ 329, m/d law and dept. rules and regs. provide a completed certificate of inspection visits in a proper frame at or near mailboxes, bottom edge of frame between 48-62 inches above floor , at public hall, 1st story
May 14, 2019
Closed — Violation closed - ANon-hazardous
Post a proper notice of smoke detector requirements, in a form approved by the commissioner, at or near the mail box , at public hall, 1st story
May 14, 2019
Closed — Violation closed - ANon-hazardous
Post and maintain a proper notice on wall of the entrance story in english and spanish on the availability of the agencys housing information guide. a sample notice can be found at www.nyc.gov/hpd. at public hall, 1st story
May 14, 2019
Closed — Violation closed
Show 3 more ↓
- CImmediately hazardous
Post notice, in form approved by the department, stating the name and location of the person designated by the owner to have key to buildings heating system , at public hall, 1st story
May 14, 2019
Closed — Violation closed - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Oct 26, 2018
Closed — Violation dismissed - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Oct 20, 2015
Closed — Violation dismissed
DOB building violations · 0
No DOB violations on record
ECB violations · 20
- Class - 1
Unlawfully continued work while on a notice of a stop work order. notethe inspection revealed that a 4 sty bldg was complete contrary to an existing stop work order. on the above mentioned premises. remedy: com
Aug 2, 2016
Resolve - Hazardous
Failure to use panic hardware where required by law.noted:both bulkhead doors have no panic hardware.remedy:provide panic hardware immediately
Apr 6, 2007
Resolve - Hazardous
New bldg occupied w/o a valid c of o.noted:bldg observed w/tenants,furniture,personal effects,pet living in bldg.remedy:obtain a valid c of o forthwith.
Feb 1, 2007
Resolve - Hazardous
Failure to maintain bldg.noted:openings in sheetrock ceilings around bx electrical cables & gas lines in electric & gas lines in electric &gas meter rooms water damage in stairwell,below skylight apt ceiling
Feb 1, 2007
Resolve - Hazardous
Failure to provide/maintain fire stopping where required.noted:at cellar level,bx electric cables & gas pipes pass through openings in sheetrock ceiling of electric & gas meter rooms.remedy:close & seal opening
Feb 1, 2007
Resolve - Hazardous
Sec.27-597.questionable construction.noted:dunnage & hvac units installed above skylights,roof drainage inadequate w/water stains starting from parapet & running down to balcony door lintel.down spout terminat
Feb 1, 2007
Resolve - Hazardous
New bldg occupied w/o a valid c of o. note:new bldg erected at above address under job#301823934. bldg dept records indicate the new bldg has yet to be signed off & no c of o has been issued. however, bldg is
Jun 20, 2006
Resolve - Hazardous
Failure to maintain adequate housekeeping. note: at front of bldg. huge pile of combustible debris such as wood crates, boxes, metal & plastic buckets, pcs of wood & black garbage bags w/other debris being
May 5, 2006 · Penalty $500
Resolve - Non-hazardous
Failure to provide approved plans at premises at time of inspection. note: new bldg being erected with job #301832934 and no approved plans submitted at time for inspection. stop all work. remedy: obtain and ma
Feb 7, 2006
Resolve - Non-hazardous
Failure to have approved plans available at construction site. defective noted: at time of inspection 2 workmen were installing metal channel for aluminum siding of front elevation of the building note said
Dec 10, 2005 · Penalty $2,500
Resolve
Show 10 more ↓
- Hazardous
Failure to safeguard public and property affected by construction operations- the following unsafe/hazardous conditions existed at construction site (1) pipe/pole scaffold erected at front of building is not to
Dec 10, 2005 · Penalty $5,000
Resolve - Non-hazardous
Week end work without a variance permit. at time of inspection two workmen were on a manlift scaffold erecting metal channels on the front elevation of building at above address. said scaffold were hoisted over
Dec 10, 2005 · Penalty $2,500
Resolve - Hazardous
Failure to maintain adequate housekeeping. at rear yard of bldg a large pile of debris (sheetrock,metal studs,wood and black garbage bags) is piled up 20 yards and at the front yard of bldg a construction fence
Nov 17, 2005 · Penalty $1,000
Resolve - Hazardous
No sidewalk shed. bldg is over 40 ft bdlg is up to roof exterior work is in progress and no sidewalk shed provided. stop all exterior work. remedy: provide sidewalk shed.
Sep 16, 2005 · Penalty $5,000
Resolve - Hazardous
No guard rails. bldg is not enclosed. double story windows at all floors have no guardrails to prevent workers from falling off the bldg. remedy: stop all work. provide guard rails.
Sep 16, 2005 · Penalty $5,000
Resolve - Hazardous
Failure to protect roofs,roof outlets or skylights of adjoining property during construction operations.note:new building being erected with permit #301832932 in which huge pieces of bricks and cinder blocks ob
Jul 18, 2005 · Penalty $2,500
Resolve - Hazardous
Job site fence defective.note plywood fence erected with permit #301832934 and fence door open towards sidewalk.remedy:repair and/or replace fence forthwith.
Jul 18, 2005 · Penalty $5,000
Resolve - Hazardous
Job site fence defective.note:plywood fence door is loose and in danger of falling onto sidewalk.also fence door open towards sidewlak.remedy:repair and/or replace fence forthwith.
Jun 15, 2005 · Penalty $5,000
Resolve - Hazardous
Failure to maintain hazardous.noted:roof on front porch is rotten plywood is missing,hanging and loose and in danger of falling.remedy:maintain roof on front porch,obtain all permits required to do repairs.
Jul 19, 2004 · Penalty $2,500
Resolve - Non-hazardous
Failure to maintain bldg. defect is: there are holes in the roof of porch at front of premises. plywood is rotted & pieces missing. remedy: repair all defects to porch roof.
Mar 11, 1999 · Penalty $2,500
Resolve
Complaints
- Electric
No lighting
May 11, 2019 · Apt BLDG
Close - Electric
Electric-supply
Dec 10, 2013 · Apt 2B
Close
Sales history
No recorded sales in our data
Building details
- Building type
- Condominium (R1)
- Year built
- 2005
- Floors
- 4
- Residential units
- 8
- Building area
- 7,620 ft²
- Lot area
- 2,500 ft²
- Zoning
- R6
- Community board
- 301
- Council district
- 34
- Block / lot
- 2405 / 7501
- Assessed value
- $1,669,951
- Landmark / historic district
- No
HPD registration #382954, last renewed Oct 10, 2025.
Questions about 113 South 2 Street
Who owns 113 South 2 Street?
The owner of record in NYC Department of City Planning PLUTO data is Unavailable Owner.
Does 113 South 2 Street have violations?
Yes. NYC HPD has recorded 13 housing violations at this property.
Is 113 South 2 Street rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 113 South 2 Street built?
City records list 2005 as the year it was built.
How many apartments are in 113 South 2 Street?
It has 8 residential units.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.