Owner of record: Congregation Yetev Lev D'satmar INC.

152 Rodney Street is a religious facility built in 1968 in Brooklyn, 11211. The owner of record is Congregation Yetev Lev D'satmar INC.. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
17
ECB violations
14
HPD complaints
1

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 17

  • Low pressure boiler boiler required

    Violation issued for failure to file annual boiler 2010 inspection report

    Dec 13, 2011

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Dec 2, 2010

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Lblvio-low pressure boiler boiler required

    Dec 31, 2009

    Dob violation - active
  • Low pressure boiler boiler required

    Lblvio-low pressure boiler boiler required

    Dec 31, 2009

    Dob violation - active
  • Construction other optional

    C-construction other optional

    Aug 22, 2008

    Dob violation - active
  • Construction other optional

    C-construction other optional

    Jul 30, 2008

    Dob violation - dismissed
  • Construction other optional

    Stop all work,make safe,call the dob at 718-802-3685 before further co nstruction

    Jul 29, 2008

    Vw*-violation - work w/o permit dismissed
  • Construction other optional

    Stop all work,make safe,obtain approval & permit,call dob at 718-802-3 707 prior to further construction

    Nov 16, 2007

    Vw*-violation - work w/o permit dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Jan 19, 2007

    Dob violation - active
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Jan 19, 2007

    Dob violation - active
Show 7 more ↓
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Mar 19, 2003

    Dob violation - active
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Mar 19, 2003

    Dob violation - active
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Mar 16, 1999

    Dob violation - active
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Mar 16, 1999

    Dob violation - active
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Jun 1, 1994

    Dob violation - active
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Aug 16, 1993

    Dob violation - active
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Jun 1, 1993

    Dob violation - active

ECB violations · 14

  • Class - 2

    Failure to comply with the commissioner's order to file a certificate of correction with the department of buildings. at time of inspection,contractor has failed to file a certificate of correction for violatio

    Dec 22, 2025 · Penalty $1,250

    Active
  • Class - 1

    During my inspection of 2 story alteration. upon review reference complaint# 3a29149 it reveals gc fail to comply with the commissioner's order and work against stop work order issued 09-12-2025. i observed ext

    Oct 7, 2025 · Penalty $10,000

    Active
  • Class - 1

    Gc failed to designite a licensed construction superintendent on a project that is desgnated as other, and structural work reflected on approved dob plans. stop all work the entire site. provide & designate a

    Sep 12, 2025 · Penalty $10,000

    Resolve
  • Class - 2

    Observed diesel fueled generator street lvl of active jobsite and large amount of material storage not adequately enclosed, fully exposed to pedestrian vehicular traffic. upon review of dot database, there is n

    Sep 12, 2025 · Penalty $2,400

    Resolve
  • Class - 2

    Observed active construction operations on jobsite. access was denied for inspection from site by onsite security and project manager. stop all work entire jobsite provide access to department for construction

    Sep 12, 2025 · Penalty $2,500

    Active
  • Class - 2

    Failure to file c/c w/dob pursuant to 28-204.2 for vio 34860009h - forfailure to safeguard. remedy: file c/c.

    Dec 16, 2010 · Penalty $400

    Resolve
  • Class - 1

    Failure to safeguard all persons & property affected by construction operations.defect is:a wood structure was ereceted on public walkway infront of above location w/o design & instructions.sections have collap

    Sep 2, 2010 · Penalty $2,400

    Resolve
  • Hazardous

    Operations of public assembly w/o current permit noted bldg currently occupied as a synogogue with over 75 individuals obeserved occupying space and seating for over 600 people with no public assembly permit on

    Jan 17, 2008

    Resolve
  • Non-hazardous

    50d 36 50a 50b 50c (50a) remove manuel reset pressure trol from safety relief unlue (50b)manuel rest not wired in (50c) remove threaded end from safety relief valve discharge (50d) flue pipe not properly sealed

    Sep 22, 2004 · Penalty $680

    Resolve
  • Non-hazardous

    19b 50a 50b (50a) remove thrended end from safety relief discharge (50b) flue pipe not properly sealed to chimmey base

    Sep 22, 2004 · Penalty $180

    Resolve
Show 4 more ↓
  • Non-hazardous

    49.49 no check value (back flow preventer)on water feed line to boiler(feederal boiler).

    Mar 30, 2001

    Resolve
  • Non-hazardous

    49a,49b. 49a no check value (back flow preventer)on water feed line to boiler well machain boiler)49b pipe relief value down.

    Mar 30, 2001

    Resolve
  • Non-hazardous

    49 - 49) no rating plate -unknown make gas fired boiler with whirl power burner fhw.

    Aug 15, 2000 · Penalty $350

    Resolve
  • Non-hazardous

    19b/36/49 49)weil mclain gas fired - steam boiler installed w/o permit. (bg9) (27-147)

    Aug 15, 2000 · Penalty $850

    Resolve

Complaints

  • Electric

    Lighting

    Jun 6, 2004 · Apt BLDG

    Close

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Religious facility (M1)
Year built
1968
Floors
2
Residential units
—
Building area
21,470 ft²
Lot area
16,300 ft²
Zoning
R6
Community board
301
Council district
33
Block / lot
2193 / 18
Assessed value
$2,691,900
Landmark / historic district
No

Questions about 152 Rodney Street

Who owns 152 Rodney Street?

The owner of record in NYC Department of City Planning PLUTO data is Congregation Yetev Lev D'satmar INC..

Does 152 Rodney Street have violations?

NYC HPD has no housing violations on record for this property.

Is 152 Rodney Street rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 152 Rodney Street built?

City records list 1968 as the year it was built.