Lefferts Place
Brooklyn, NY 11238BBL 3-02014-0053Map
Owner of record: 21 Lefferts Place LLC
Lefferts Place is a walk-up apartment building built in 2020 in Brooklyn, 11238. It has 6 residential units across 6 floors. The owner of record is 21 Lefferts Place LLC. HPD has no housing violations on record for this property.
- HPD violations
- 0
- DOB violations
- 11
- ECB violations
- 14
- HPD complaints
- 0
What to know
No open immediately-hazardous violations among recent records.
HPD has not cited this building.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 0
No HPD violations on record
DOB building violations · 11
- Construction other optional
Borough commissioner has ordered all work stopped under application #321925725 on 5/24/22 due to construction superintendent withdrawal
May 27, 2022
Dob violation - dismissed - Construction other optional
Borough commissioner has ordered all work stopped under application #321925725 on 5/24/22 due to construction superintendent withdrawal.
May 27, 2022
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Mar 17, 2021
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Mar 17, 2021
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Mar 17, 2021
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Mar 17, 2021
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Mar 17, 2021
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Mar 17, 2021
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Mar 17, 2021
Dob violation - dismissed - Construction other optional
Borough commissioner has ordered all work stopped under application #321925725 on 2-22-21 due to construction superintendent withdrawal
Feb 24, 2021
Dob violation - dismissed
Show 1 more ↓
- Construction other optional
Notice from borough commissioner'sorderd to stop work immediately due to construction superintendent withdrawal. application # 321925725.
Feb 24, 2021
Dob violation - dismissed
ECB violations · 14
- Class - 2
At the time of my inspection of an active 4 story nb construction site i observed a construction fence installed at exposure 1. after reviewing dob records it was determined the temp construction fence permit h
Nov 9, 2022
Resolve - Class - 2
Temporary construction equipment onsite expired permit.as noted at time of my inspection observed no fence permit posted on further researchof the dob records shows that permit#b00273586-l1-fn was issue 9/23/20
Jun 17, 2022
Resolve - Class - 2
Failure to safeguard all persons & property affected by construction operations.note-at the time of inspection of a 4 story new bldg construction in progress.i observed they have failed to safeguard adjacent pr
Dec 15, 2020 · Penalty $5,000
Resolve - Class - 1
Design,sizes & capacity of materials,structures,temporary construction& equipment.note-at the time of inspection i observed work platforms over stair opening created of plywood & 2x4s.upon request for design
Dec 15, 2020 · Penalty $2,500
Resolve - Class - 1
Permit holder failed to ensure workers receive site safety orientationnote:at the time of my inspection of a 4 story new bldg construction in progress,upon request for records of site safety orientation none wa
Dec 15, 2020 · Penalty $5,000
Resolve - Class - 2
Failure to provide approved/accepted construction documents.note-at time of inspection of a 4 story new bldg construction in progress.upon request for approved structural drawings for site none was provided(bc
Dec 15, 2020 · Penalty $312
Resolve - Class - 1
Bc3314.1 unsafe supported scaffold.note-at the time of inspection.i observed supported pipe scaffold in place at exp#3.(1)missing gravity pins in stairs (2)platform not cleared of debris creating a tripping haz
Dec 15, 2020 · Penalty $2,500
Resolve - Class - 1
Work does not conform to approved construction documents.note-at the time of inspection upon review of site safety plan for site operations i observed the work did not conform there was no sidewalk shed in plac
Dec 15, 2020 · Penalty $2,500
Resolve - Class - 1
Failure to provide sidewalk shed where required.note-at the time of inspection of a 4 story new bldg construction in progress at overall height of approx. 50 ft.i observed there was no sidewalk shed in place to
Dec 15, 2020
Resolve - Class - 1
Bc3309.10 protection of roofs.note-at the time of inspection of a 4 story new bldg construction in progress.i observed there was no roof protection in place at exp.#4 & adjoining roof.this creates an unsafe con
Dec 15, 2020 · Penalty $2,500
Resolve
Show 4 more ↓
- Class - 1
Failure to institute & maintain safety equipment measures & temporary construction.note-at the time of inspection of a 4 story new bldg construction i observed multiple locations w/no guard rails in place.this
Dec 15, 2020 · Penalty $5,000
Resolve - Class - 2
Sec. 3314.11 unsafe supported pipe scaffold. note: at the time of inspection,i observed supported pipe scaffold at exp#1,i observed unsafe planks at the top of scaffold approx 42 feet in height. this creates a
Dec 12, 2020 · Penalty $620
Resolve - Class - 1
Required means of egress as per site safety plan. note: at time of my inspection of a 4 sty bldg at excavation & pile drying stage,construction work in progress. i observed 3 mechanical machines an excavation,
Jul 22, 2020 · Penalty $625
Resolve - Class - 1
Housekeeping. note: at time of my inspection of a 4 sty bldg at excavation & pile driving stage construction work in progress,i observed machinery & equipments materials & debris throughout site. these conditio
Jul 22, 2020 · Penalty $625
Resolve
Complaints
No HPD complaints in our records
Sales history
No recorded sales in our data
Building details
- Building type
- Walk-up apartment building (C2)
- Year built
- 2020
- Floors
- 6
- Residential units
- 6
- Building area
- 4,693 ft²
- Lot area
- 2,250 ft²
- Zoning
- —
- Community board
- 302
- Council district
- 35
- Block / lot
- 2014 / 53
- Assessed value
- $569,250
- Landmark / historic district
- No
Questions about Lefferts Place
Who owns Lefferts Place?
The owner of record in NYC Department of City Planning PLUTO data is 21 Lefferts Place LLC.
Does Lefferts Place have violations?
NYC HPD has no housing violations on record for this property.
Is Lefferts Place rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was Lefferts Place built?
City records list 2020 as the year it was built.
How many apartments are in Lefferts Place?
It has 6 residential units.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.