589 Halsey Street
Brooklyn, NY 11233BBL 3-01662-0082Map
Owner of record: 589 Halsey Realty LLC
589 Halsey Street is a mixed residential and retail building built in 2021 in Brooklyn, 11233. It has 2 residential units across 3 floors. The owner of record is 589 Halsey Realty LLC. HPD has no housing violations on record for this property.
- HPD violations
- 0
- DOB violations
- 2
- ECB violations
- 23
- HPD complaints
- 0
What to know
No open immediately-hazardous violations among recent records.
HPD has not cited this building.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 0
No HPD violations on record
DOB building violations · 2
- Construction other optional
C-construction other optional
Mar 2, 2020
Dob violation - dismissed - Construction other optional
C-construction other optional
Aug 20, 2019
Dob violation - dismissed
ECB violations · 23
- Class - 1
At the time of my inspection of a 3 story new building, i observed 4 workers on job site upon request for site safety orientation and refresher to be perform at job site none was presented or at the job site. t
Apr 5, 2023 · Penalty $625
Resolve - Class - 1
At the time of my inspection of a 3 story new building, i observed active job site upon request for site safety plan from the competent person none was presented or at job site. failure to provide and maintain
Mar 17, 2023 · Penalty $625
Resolve - Class - 2
At time of responding complaint observed: gc failure to provide overhead protection at expo# 4, creating a potential safety hazardous condition for adjoining occupied building; tools, material can fall, getting
Mar 8, 2023
Resolve - Class - 2
Responding complaint observed: gc failure to maintain safety measures for adjoining property at expo# 4. crack on concrete of alleyway at expo# 2 of adjoining property creating a potential safety hazardous cond
Mar 8, 2023
Resolve - Class - 2
At the time of inspection jobsite was closed. as per perimeter inspection i observed, construction fence and sws on site without having active permit for construction equipment. there was no active permit poste
Oct 25, 2022
Resolve - Class - 1
At time of inspection i observed that the roof protection at exposure #2 was inadequate, there was missing styrofoam and planks which is required by code to be in place for protection. at exposure #4 there was
Jun 25, 2022
Resolve - Class - 1
Work does not conform to approved construction documents and/or approved amendments.at time of inspection observed structural work completedat first floor level.upon review of the amended structural steel drawi
Mar 1, 2022 · Penalty $625
Resolve - Class - 1
1704.3.4 required verification and inspection of cold-form steel construction.no cold-form checked as required on tr1(technical report statement of responsibility)at time of inspection observed cold-form steel
Mar 1, 2022 · Penalty $625
Resolve - Class - 1
Bc3307.4 barriers storage near sw&on st note:ato my insp of 3stynb const work in progress.i observed on st@exp1 pallets of cmu blocks&const sand bags about 4-5' in ht not fully barricade w/yodock systems.this c
Dec 29, 2021
Resolve - Class - 2
Bc28-104.7.10 site safety plan.note:at the time of my inspection of a 3 story new bldg construction.work in progress i observed sight safetyplan that were presented to me were not seal & have no signature.this
Dec 29, 2021
Resolve
Show 13 more ↓
- Class - 1
Bc3314.1 scfs pipe supported note:ato my insp of 3stynb const work in progress.i observed inside of const site@exp2&4 supported pipe scf w/obaseplater&planks not tied down.this creates hazardous condition for f
Dec 29, 2021 · Penalty $625
Resolve - Class - 1
Bc3309.1 overhead protection adj property note:ato my insp of 3stynb const work in progress.i observed concrete splash on adj property sideyd from cmu op&there were no overhead protection@exp4&no roof protectio
Dec 29, 2021 · Penalty $625
Resolve - Class - 2
Construction superintendent job site logs not adequately maintained.at time of inspection while responding to a complaint #3817072 upon request for job site logs were provided observed construction superintende
Oct 12, 2021 · Penalty $625
Resolve - Class - 2
Failure to adequately provide job site fence as required.note:at time of inspection of active job site at excavation stage observed missing job site fence at exp #2 as required. stop all work 10 feet away and p
Oct 12, 2021
Resolve - Class - 2
Bc 3307.2.1 failure to comply with dot regulations note:at the time ofmy inspection of a 3 story new building at excavation phase.i observedone large generator on street at exp#1 with no permit on display and n
Oct 4, 2021
Resolve - Class - 1
Bc 3303.4.8 machinery note:at the time of my inspection of a 3 story new building at excavation phase.i observed a generator machinary on street not fully guarded shield or barricaded as to prevent contact from
Oct 4, 2021 · Penalty $625
Resolve - Class - 2
Fail to safeguard all person & property affected by construction operation.note:at the time of my inspection of a 3 story new bldg constructing work in progress.i observed pile driven machine driving piles at
Sep 15, 2021 · Penalty $625
Resolve - Class - 2
Bc3301.13.7 construction superintendent fail to perform his duties:note:at the time of my inspection of a 3 story new bldg construction workin progress.i observed pile driven operation at exp.#4 upon review of
Sep 15, 2021
Resolve - Class - 1
Bc3301.7 design drawing.note:at the time of my inspection of a 3 storynew bldg construction work in progress i observed pile driving operation at exp.#4 close to construction fence upon request for design drawi
Sep 15, 2021 · Penalty $625
Resolve - Class - 1
1814.3 vibration monitoring note:ato my insp of active jobste,i observed pile drilling operation in progress@exp2&3.rev of vibration monitoring system in place,reveals that theres no vibration monitoring for ad
Aug 26, 2021
Resolve - Class - 2
Temporary construction equipment on site expired permit. note: at the time of inspection,i observed construction fence in place. upon review of dept records the permit has been expired as of 10/6/2019 permit #
Aug 4, 2021
Resolve - Class - 2
Sec. bc 3307.7.3 viewing panels. note: at the time of inspection,i observed construction fence in place. i observed there were no viewing panels provided as required. viewing panels shall be 12 inches by 12 inc
Aug 4, 2021
Resolve - Class - 2
Jobsite fence not constructed or maintained pursuant to subsection. at time of inspection observed at rear right side section of construction fence missing and leaning into adjacent property. at front construct
Jul 17, 2019 · Penalty $2,000
Resolve
Complaints
No HPD complaints in our records
Sales history
No recorded sales in our data
Building details
- Building type
- Mixed residential and retail building (S2)
- Year built
- 2021
- Floors
- 3
- Residential units
- 2
- Building area
- 3,570 ft²
- Lot area
- 1,600 ft²
- Zoning
- R6A
- Community board
- 303
- Council district
- 36
- Block / lot
- 1662 / 82
- Assessed value
- $42,840
- Landmark / historic district
- No
Questions about 589 Halsey Street
Who owns 589 Halsey Street?
The owner of record in NYC Department of City Planning PLUTO data is 589 Halsey Realty LLC.
Does 589 Halsey Street have violations?
NYC HPD has no housing violations on record for this property.
Is 589 Halsey Street rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 589 Halsey Street built?
City records list 2021 as the year it was built.
How many apartments are in 589 Halsey Street?
It has 2 residential units and 3 units in total.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.