roofy

886 Broadway

Brooklyn, NY 11206BBL 3-01582-0015Map

Owner of record: 886 Broadway LLC

886 Broadway is an office building built in 2020 in Brooklyn, 11206. The owner of record is 886 Broadway LLC. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
3
ECB violations
22
HPD complaints
2

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 3

  • Failure to submit eer none

    Failure to submit an eer per ad. code sec. 28-308.4 in 2022

    Apr 22, 2023

    Dob violation - dismissed
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Feb 25, 2008

    Dob violation - active
  • Construction other optional

    C-construction other optional

    Aug 7, 1995

    Vpw*-violation unserved ecb-work without permit-dismissed

ECB violations · 22

  • Class - 2

    1) provide illumination in elevator pit. 2) in-car communication inoperative. 3) hoistway door rubbing on fechar in lobby. 4) floors locked out from 3-6th floor provide access for proper elevator inspection. 5)

    Sep 16, 2026 · Penalty $625

    Active
  • Class - 1

    Physical culture establishment "puregym" is in operation and occupied at time of inspection. pa #b00902922-i1-pa identifies establishment name as "blink fitness" which is no longer establishment name. additiona

    Jan 12, 2026 · Penalty $12,500

    Active
  • Class - 1

    Inadequate egress. makeshift platform for exit & entrance into the jobsite.stop all use of use, provide adequate egress or provide approved drawing for any temporary make shift platform

    Nov 2, 2022 · Penalty $2,500

    Resolve
  • Class - 2

    Missing panels on construction fence in rear at exp#3, exposed materials in public passageway.fix, repair or replace, comply with code.

    Nov 2, 2022

    Resolve
  • Class - 1

    Street operations not per dot stipulations, no ada ramp for pedestrians, no 5 foot clearance in pedestrian walkway.stop all street operations , comply with all dot stipulations

    Nov 2, 2022 · Penalty $2,500

    Resolve
  • Class - 1

    Street operations contrary to ssp, multiple lanes occupied in roadway obstructing vehicular traffic at exposure #3, no chain link fence on yodocks on vehicular side, building materials not protected from public

    Nov 2, 2022 · Penalty $2,500

    Resolve
  • Class - 2

    Upon review the approved supported scaffold drawings, page eq-004-01& eq-008-01, observed that scaffold at exp#3 should start from top of sidewalk shed, while on site, observed scaffold start from top of sidew

    Apr 5, 2022

    Resolve
  • Class - 1

    Bc3309.10 protection of roofs.at time of inspection of 7 story nb active job site,observed inadequate roof protection for adjacent properties at exp.#2 & exp.#4.at exp.#2 observed missing parapet protection.als

    Apr 5, 2022

    Resolve
  • Class - 1

    Failure to comply with manufacturers specifications note:at the time of my inspection of a proposed 7 story new building under construction an active jobsite i observed on expo#1 and expo#3 plastic barricades t

    Jun 16, 2021

    Resolve
  • Class - 2

    Temporary construction equipment onsite with expired permit note:at the time of my inspection of a proposed 7 story new building under construction an active jobsite upon review of departmential records it reve

    Jun 16, 2021

    Resolve
Show 12 more ↓
  • Class - 1

    Bc 3307.4.7 stop all use and work in storage zones on exp#1 and expo#3follow barricade manufactor and fence on barricade not shown onsite safety plan.follow code for netting type note:at the time of my inspecti

    Jun 16, 2021

    Resolve
  • Class - 1

    Failure to file evidence of liability for property dawnage insurence.note:at the time of my inspection of a proposed 7 story new building under construction an active jobsite.upon review of departmential record

    Jun 16, 2021 · Penalty $5,000

    Resolve
  • Class - 1

    Requirement of license-stop all work on needle beam.support scaffold and hoist.note:at the time of my inspection of a proposed 7 story building under construction an active jobsite upon review of departmential

    Jun 16, 2021 · Penalty $5,000

    Resolve
  • Class - 1

    Work does not conform to approved construction documents note:at the time of my inspection of a proposed 7 story new building under construction an active jobsite i observed on the 4 level the install of needle

    Jun 16, 2021

    Resolve
  • Class - 2

    Failure to maintain adequate housekeeping as per section requirements.note:at the time of my inspection of a proposed 7 story building new building under construction an active jobsite.i observed on multiple le

    Jun 16, 2021

    Resolve
  • Class - 2

    3303.3 watch person.at time of insection of a 7 story nb,observed no construction activities on progressing and tere was a trailer at exp#1.however according to chapter 33 bc 3303.3 a competent watch person sha

    Dec 24, 2020

    Resolve
  • Class - 1

    3301.2 safety measures and standards note:at time of my inspection of a 7 story new building under construction at excavated stage construction work in progress i observed that the walkway leading to the egress

    Nov 30, 2020

    Resolve
  • Class - 1

    Failure to notify dept prior to earthwork. at the time of my inspection at 7 sty bldg under construction,i observed excacaation(earth)work at exp#3 upon request for earthwork notification # which was provided

    Sep 21, 2020

    Resolve
  • Class - 2

    Occupancy contrary to that allowed by the certificate of occupancy or bldgs dept records observed: at time of inspection. single family dwelling is being used as an automatic social club. rmdy:discontinue illeg

    Nov 10, 2016 · Penalty $3,000

    Resolve
  • Hazardous

    Failure to maintain conco party wall in that sewage waste water from defective plumbing drain seeds through party wall foundation into 892 broadway undermining of this foundation wall is inevitable if flow is n

    Aug 9, 1995 · Penalty $800

    Resolve
  • Non-hazardous

    Occupancy contrary to that alllowed by the building dept records c/o#81681alt in that the existing first floor commercial area has been sub-divided into 4 independent stores incl.a video store b grocery stores

    Aug 9, 1995

    Resolve
  • Non-hazardous

    Work without a permit work noted rebuilding foundation at front and excavating foundation trenches on lot no approved plans on site to do inspection remedy stop all work obtain a permit and approval if feasible

    Apr 19, 1991

    Resolve

Complaints

  • Heat/hot water

    Entire building

    Dec 27, 2024 · Apt BLDG

    Close
  • Plumbing

    Water supply

    May 28, 2024 · Apt BLDG

    Close

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Office building (O6)
Year built
2020
Floors
7
Residential units
—
Building area
69,670 ft²
Lot area
11,410 ft²
Zoning
C4-4L
Community board
303
Council district
36
Block / lot
1582 / 15
Assessed value
$7,036,200
Landmark / historic district
No

Questions about 886 Broadway

Who owns 886 Broadway?

The owner of record in NYC Department of City Planning PLUTO data is 886 Broadway LLC.

Does 886 Broadway have violations?

NYC HPD has no housing violations on record for this property.

Is 886 Broadway rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 886 Broadway built?

City records list 2020 as the year it was built.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.