169 Empire Boulevard
Brooklyn, NY 11225BBL 3-01307-0080Map
Owner of record: Empire Prospect LLC
169 Empire Boulevard is a hotel built in 2022 in Brooklyn, 11225. The owner of record is Empire Prospect LLC. HPD has no housing violations on record for this property.
- HPD violations
- 0
- DOB violations
- 7
- ECB violations
- 26
- HPD complaints
- 0
What to know
No open immediately-hazardous violations among recent records.
HPD has not cited this building.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 0
No HPD violations on record
DOB building violations · 7
- Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Oct 4, 2023
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Oct 4, 2023
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Oct 4, 2023
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Oct 4, 2023
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Oct 4, 2023
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Oct 4, 2023
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Oct 4, 2023
Dob violation - dismissed
ECB violations · 26
- Class - 2
Temporary construction equipment onsite-expired permit as noted:at time of inspection at a proposed 5 story building observed construction facade permit had expired on 05/05/2023.permit#b00405657-1i-fn on furth
May 18, 2023
Resolve - Class - 2
Failure to comply with nyc fire code no permit. at the time of inspection on an active job site currently at roof level, i observed a 5 gallon container with gasoline at cellar to power up tools on site when i
Mar 13, 2023 · Penalty $625
Resolve - Class - 2
Fire extinguisher not as per code required. at the time of inspection on an active job site currently at roof level, i observed about 10 inadequate fire extinguishers on site throughout building with missing
Mar 13, 2023 · Penalty $625
Resolve - Class - 2
At the time of inspection on an active job site currently at roof level, i observed that no smoking signs were posted on walls throughout building as per code required.
Mar 13, 2023 · Penalty $625
Resolve - Class - 1
At time of my inspection of a 5 story building at roof level, building approximately 5040 square feet. site closed and there were no construction activity. upon shouting at perimeter and banging on fence to ale
Dec 31, 2022 · Penalty $1,250
Resolve - Class - 2
Failure to perform proper concrete washout water procedures.as noted:at time of inspection observed concrete operation take place on requesting to see washout box was shown box under pump truck on further inspe
Oct 31, 2022 · Penalty $625
Resolve - Class - 1
Failure to secure reshores in proximity to the facade:as noted at timeof my inspection observed at exposure 1,2,3,4 on 1st and 2nd floor reshores not secure as per code were reshores within 10 feet of the leadi
Oct 26, 2022 · Penalty $2,500
Resolve - Class - 1
Inspection of an 4 story building with work in progress, i observed site safety plan that indicate at exposure two and four overhead protection. upon review area there is no protection in place creating condict
Oct 20, 2022 · Penalty $625
Resolve - Class - 1
Inspection of an 5 story building at 4 floor level , i observed at exposure two and four a titan shore system in place for the use of working platform. i also observed worker have installing wood wedge between
Oct 20, 2022 · Penalty $625
Resolve - Class - 2
Failure to perform proper concrete washout water procedures:as noted ato my insp observed concrete op take place on requesting to see washout box more was provided&sign of it been dump onsite contrary to bc3303
Jul 1, 2022 · Penalty $625
Resolve
Show 16 more ↓
- Class - 2
Failure to safeguard all persons&property affected by continuous op:asnoted ato my insp observed concrete beam pour w/pump truck w/no protection in place for public walking on sidewalk&no adherence to ssp&allow
Jul 1, 2022 · Penalty $625
Resolve - Class - 1
Failure to maintain/display onsite docs requirement by ch33.as noted ato my insp of active jobsite i observed pouring of concrete footing onrequesting (1)dot permit none was provided (2)tr3 which included tr1 t
Jul 1, 2022 · Penalty $1,250
Resolve - Class - 1
Ato inspection observed missing guardrails approx.25 lf around excavation pit at corner of exp#1 & #4. observed 2 workers within the pit and others working nearby. edges of an excavation site that are 6ft or gr
Jun 6, 2022 · Penalty $2,500
Resolve - Class - 2
Ato inspection construction job site fence under permit# b00405657-i1-fn expires on 07-22-22 is inadequately constructed.at all exposure job site fence did not have any plexiglass cover on any of the viewing po
Jun 6, 2022 · Penalty $500
Resolve - Class - 1
Ato observed permitted site on going excavation. observed the only safe means of ingress and egress to the excavation pit is blocked by two wooden planks. two planks are nailed to the guardrails obstructing egr
Jun 6, 2022 · Penalty $2,500
Resolve - Class - 1
At the time of my inspection of an 5 story building with work in progress, observed dump truck at expsure one with two worker flaging . upon my request for d.o.t permit for occupying roadway and sidewalk . none
May 5, 2022 · Penalty $625
Resolve - Class - 1
Inspection of an 5 story building with work in progress , observed at exposure 3 worker proform concrete work from waterproofing, upon review work area there is no guardrail in place while work are in use of sc
May 5, 2022 · Penalty $625
Resolve - Class - 1
Inspection of an 5 story building with work in progress, observed at exposure four an construction fence in place. upon review document on site it appear construction fence is approximately 8 feet on the adjace
May 5, 2022 · Penalty $1,250
Resolve - Class - 2
Failure to obtain temporary construction permit prior to installation/use of temporary construction equipment-failure to provide/obtain construction fence permit.note:at time of inspection 5-story new building
Apr 20, 2022 · Penalty $625
Resolve - Class - 2
Condition of fence.at time of inspection observed construction fence @ exp #1,2 and 4 leaning in and out thumb nails and screws protruding in multiple locations.panels becoming dislodged from posts missing plex
Jun 16, 2021 · Penalty $500
Resolve - Class - 2
Failure to safeguard public and property.at time of inspection observed construction fence at exp #1 completely open and accessible to anyone walking by site.on site no active work being done no security person
Jun 16, 2021 · Penalty $500
Resolve - Class - 2
Failure to safeguard all persons and property affected by constructionoperation.note:at time of my inspection of demolition jobsite in responce to complaint#3788003 jobsite was closed.i asked the adjacent prope
Feb 26, 2021 · Penalty $1,250
Resolve - Class - 2
Jobsite fence not constructed or maintained pursuant to subsection @time of inspection on nonactive jobsite,i observed construction fence erected @exp1 w/ visions panels not protected w/ net or similar material
Jan 5, 2021 · Penalty $500
Resolve - Class - 2
Project info panel/construction fence/sidewalk shed parapet panel construction sign not provided or not in compliance w/ section.@time of inspection on nonactive jobsite,i observed construction fence @exp1,2,4
Jan 5, 2021 · Penalty $1,250
Resolve - Hazardous
Work w/o a permit work noted new interior partitions walls construction in progress throughout 1 story blg new 2x3 metal stud land sheet rock with new electrical work observed at time of inspection stop all
Nov 3, 2003 · Penalty $800
Resolve - Non-hazardous
Failure to maintain bldg defect concrete slag spalling and section missing from ceiling m cellar crack observed with rotten steal amd messing section of cement slob of ceiling concreted collumn cracked and sep
Nov 3, 2003
Resolve
Complaints
No HPD complaints in our records
Sales history
No recorded sales in our data
Building details
- Building type
- Hotel (H3)
- Year built
- 2022
- Floors
- 5
- Residential units
- —
- Building area
- 24,541 ft²
- Lot area
- 12,000 ft²
- Zoning
- C8-2
- Community board
- 309
- Council district
- 35
- Block / lot
- 1307 / 80
- Assessed value
- $2,985,750
- Landmark / historic district
- No
Questions about 169 Empire Boulevard
Who owns 169 Empire Boulevard?
The owner of record in NYC Department of City Planning PLUTO data is Empire Prospect LLC.
Does 169 Empire Boulevard have violations?
NYC HPD has no housing violations on record for this property.
Is 169 Empire Boulevard rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 169 Empire Boulevard built?
City records list 2022 as the year it was built.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.