roofy

771 56 Street

Brooklyn, NY 11220BBL 3-00834-0049Map

Owner of record: Shun Yi LLC

771 56 Street is an office building built in 1945 in Brooklyn, 11220. The owner of record is Shun Yi LLC. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
11
ECB violations
22
HPD complaints
0

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 11

  • Construction other optional

    Stop all work except to make site safe contact the borough commissioner's office at 716 802-3677

    Jul 17, 2020

    Dob violation - dismissed
  • Construction other optional

    Stop all work immediately except to make site safe contact the borough commissioner office at 718 802-3677

    Jul 17, 2020

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Nov 13, 2019

    Dob violation - dismissed
  • Construction other optional

    Stop all work immediately and make site safe contact the borough commi ssioner's office at 718 802-3677

    Sep 28, 2019

    Dob violation - dismissed
  • Construction other optional

    Stop all work immediately and make site safe contact the borough commi ssioner's office at 718 802-3677

    Sep 28, 2019

    Dob violation - dismissed
  • Construction other optional

    C-construction other optional

    Jul 2, 2019

    Dob violation - active
  • Construction other optional

    Stop all work immediately7, make job site safe, and contact boro. comm . office at 718 802-3677

    Mar 15, 2019

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jan 10, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jan 10, 2018

    Dob violation - dismissed
  • Construction other optional

    Stop all work immediately and make site safe, contact boro. comm. offi ce at 718 802-3677

    Aug 3, 2017

    Dob violation - dismissed
Show 1 more ↓
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jul 12, 2017

    Dob violation - dismissed

ECB violations · 22

  • Class - 2

    Failure to safeguard all persons & property affected by construction operations.note:time of inspection it was observed the elevator operating mechanic/worker was working on elevator on the 1st fl.at the same

    Jul 27, 2021 · Penalty $625

    Resolve
  • Class - 1

    Right of entry - denied access at active site.noted:job site w/job #321154371 expires 01/27/2021.workers present & refusing to give access for inspection.stop all work.remedy:provide access/entry

    Sep 26, 2020 · Penalty $2,500

    Resolve
  • Class - 2

    Failure to provide access to active site. at time of inspection observed worker @ street level observed worker @ street setting up barricades in street. observed workers taping drywall on 3rd fl balcony areas.

    Sep 20, 2019 · Penalty $5,000

    Resolve
  • Class - 1

    Failure to maintain adequate housekeeping per section requirements. note: at time of inspection of a 4 sty bldg at 75% completion i observed debris-construction-on all 4 floors 7 stairwells,throughout the site.

    Aug 21, 2019 · Penalty $2,500

    Resolve
  • Class - 1

    Guardrails: note: at time of my inspection,i observed that the elevator shaft opening was covered w/pile wood boards as well as a window at exp#1 & there was no guardrails in place at exp#3 on all floors. failu

    Aug 21, 2019 · Penalty $5,000

    Resolve
  • Class - 2

    Permit holder fail to provide access & /or expose work on active site.note @the time of inso of a 4 story alteration const work in progress unpon calling worker to gate to open site worker simply came to gate @

    May 8, 2018 · Penalty $2,500

    Resolve
  • Class - 1

    Sec: bc 3303.4.2. containers. note: @ time of insp of a 4 story alteration, construction work in progress. observed a 20 cubic yard dumpster full beyond the rim w/ construction debris, also observed that there

    May 8, 2018 · Penalty $625

    Resolve
  • Class - 1

    Work does not conform to approved documents or approved amendments.at the time of inspection i observed excavation were being done at exp 2,3,4.approved drawings soe-102-00 shows stages of work where stage one

    Dec 13, 2017 · Penalty $2,500

    Resolve
  • Class - 2

    Construction superintendent failed to perform duties as per rule.at the time of inspection i observed excavation and shoring done at exposure #2,3 and #4.1/superintendent failed to work according to plans doing

    Dec 13, 2017 · Penalty $2,500

    Resolve
  • Class - 1

    Failure to protect side of excavation.at the time of inspection i observed excavation work done at exposure #2,3,and 4.the depth at exposure#2 was over 5 feet(approx 6 ft)nd lagging or protection was provided.

    Dec 13, 2017 · Penalty $6,000

    Resolve
Show 12 more ↓
  • Class - 1

    Failure to safeguard all persons and property affected by constructionoperations.at time of inspection i observed contractor has excavated trench of approx x 6ft deep for underpining work with no approach box p

    Oct 16, 2017 · Penalty $10,000

    Resolve
  • Class - 2

    Work does not conform to apporved construction document and or approved amendments.at time of inspection i observed an active construction site with contractor wa doing underpining work in rear yard,underpining

    Oct 16, 2017 · Penalty $500

    Resolve
  • Class - 1

    Unlawfully continued work on notice of a stop work order.at time of inspection i observe-a active construction site contractor was doing wood frame work at basement 1st and 2nd story also there was doing underp

    Oct 16, 2017

    Resolve
  • Class - 1

    Failure to notify dob within 24-48 of the start of excavation.at time of inspection i observed an active construction site within the rear yard contractor was doing underpining work,check on biz system and note

    Oct 16, 2017 · Penalty $1,200

    Resolve
  • Class - 1

    Bc1704.1.1:failure to identify construction operations for the work indicated on the construction docs that are suspect of special inspection on the construciton docs and forms supplied by the dept prior to the

    Jun 15, 2017 · Penalty $1,600

    Resolve
  • Class - 1

    Failure to filed a special inspection statement of responsibility prior to permit issuance &priior to the start of work under special inspection requirement.the respondent who is the holder of permit#321154371

    Jun 15, 2017 · Penalty $1,600

    Resolve
  • Class - 2

    Work does not conform to the approved construction and submittal docs.the respondent who at the time of inspection was the holder of permit#321154371 failed to ensure that the underpinning was done as per the a

    Jun 15, 2017

    Resolve
  • Class - 2

    Xxx8-104.7.1:construction docs submittals are incomplete and are not of sufficient clarity to indicate the entire nature and full extent of the proposed works.the respondent failed to provide approved demolitio

    Jun 15, 2017

    Resolve
  • Class - 2

    Bc1704.1:failure to retain a special inspection agency to perform reinspections during construction for works requiring special inspection.the responsdednt was at the time of inspection was the owner of the pro

    Jun 15, 2017

    Resolve
  • Class - 1

    Failure to notify dob within 24-48 hours of the start of excavation.atthe time of the inspection i did observed 2 stry house with interior and exterior work by excavation and removed dirt for new extension.duri

    Apr 12, 2017 · Penalty $1,200

    Resolve
  • Class - 2

    Bc3301.7/failure to provide construction super daily logs.at the time of inspection observed active construction site with excavation of removed dirt "soil"for new extension of rear area.during inspection const

    Apr 12, 2017 · Penalty $400

    Resolve
  • Class - 1

    Bc3307.3.2/failure to provide required lot line construction fence.noted:at the time of inspection i did observed that there was no construction rear fence site at expo 2,expo 3.wide open and unprotected.when w

    Apr 12, 2017 · Penalty $1,600

    Resolve

Complaints

No HPD complaints in our records

Complaint data is still being backfilled from NYC Open Data.

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Office building (O2)
Year built
1945
Floors
4
Residential units
—
Building area
5,783 ft²
Lot area
2,003 ft²
Zoning
R6B
Community board
307
Council district
43
Block / lot
834 / 49
Assessed value
$470,700
Landmark / historic district
No

Questions about 771 56 Street

Who owns 771 56 Street?

The owner of record in NYC Department of City Planning PLUTO data is Shun Yi LLC.

Does 771 56 Street have violations?

NYC HPD has no housing violations on record for this property.

Is 771 56 Street rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 771 56 Street built?

City records list 1945 as the year it was built.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.