530 President Street is an office building built in 1923 in Brooklyn, 11215. The owner of record is Pds Carroll Street LLC. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
31
ECB violations
29
HPD complaints
0

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 31

  • Construction other optional

    The dob hereby orders you to stop all work under job #322011470 due to contractor withdrawal

    May 18, 2020

    Dob violation - dismissed
  • Construction other optional

    The dob hereby orders you to stop all work under job #322011470 due to contractor withdrawal

    May 18, 2020

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jul 24, 2019

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jul 24, 2019

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jun 26, 2019

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jun 26, 2019

    Dob violation - dismissed
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    May 4, 2010

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    May 4, 2010

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jul 2, 2008

    Dob violation - resolved
  • Elevator elevatorrequired

    Cease use

    Jul 2, 2008

    Dob violation - resolved
Show 21 more ↓
  • Construction other optional

    C-construction other optional

    Jan 23, 2008

    Dob violation - dismissed
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    May 3, 2007

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    May 3, 2007

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Feb 3, 2006

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Feb 3, 2006

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    May 4, 2005

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    May 4, 2005

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Mar 10, 2004

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Mar 10, 2004

    Dob violation - resolved
  • Elevator elevatorrequired

    3p7901

    Aug 15, 2001

    Dob violation - resolved
  • Elevator elevatorrequired

    3p7902

    Aug 15, 2001

    Dob violation - resolved
  • Elevator elevatorrequired

    3p7902

    Jul 17, 2000

    Dob violation - resolved
  • Elevator elevatorrequired

    3p7901

    Jul 17, 2000

    Dob violation - resolved
  • Elevator elevatoroptional

    Ll1081-local law 10/81 - elevator elevatoroptional

    Jan 13, 1997

    Dob violation - active
  • Elevator elevatoroptional

    Ll1081-local law 10/81 - elevator elevatoroptional

    Jan 13, 1997

    Dob violation - dismissed
  • Elevator elevatoroptional

    Ll1081-local law 10/81 - elevator elevatoroptional

    Apr 17, 1995

    Dob violation - dismissed
  • Elevator elevatoroptional

    Ll1081-local law 10/81 - elevator elevatoroptional

    May 31, 1994

    Dob violation - dismissed
  • Elevator elevatoroptional

    2

    Jun 28, 1993

    Dob violation - dismissed
  • Boiler boiler optional

    B-boiler boiler optional

    May 18, 1993

    Vp-violation unserved ecb-active
  • Boiler boiler optional

    B-boiler boiler optional

    May 18, 1993

    Vp-violation unserved ecb-active
  • Boiler boiler optional

    B-boiler boiler optional

    May 18, 1993

    Vp*-violation unserved ecb- dismissed

ECB violations · 29

  • Class - 2

    28-116.2.3;failure to provide an adequate inspection program tr-3 (concrete design misc)as noted :at time of inspection on an active job site observed ramp to the cellar about to be cast with concrete without a

    Jun 21, 2019

    Resolve
  • Class - 1

    Failure to safeguard all persons & property affected by construction operations. at time of inspection on an active jobsite,observed uncapped rebars at various locations throughout site,creating impacement haza

    Apr 4, 2019 · Penalty $5,000

    Resolve
  • Class - 2

    Failure to maintain/display on-site documents required by bc chapter 33(no design drawing for ramp/egress). at time of inspection on an active jobsite,observed makeshift ramp build of lumber & plywoods installe

    Apr 4, 2019

    Resolve
  • Class - 1

    Failure to instutite/maintain safety equipment measures or temporary construction-no guardrails at time of inspection on an active jobsite,observed guardrails missing at 1st fl level,along the leading edge of

    Apr 4, 2019 · Penalty $2,500

    Resolve
  • Class - 2

    Work does not conform to approved construction documents &/or approvedamendments. at time of inspection observed ramp installed at excavation/foundation area contrary to ssp-003.00 foundation plan of site safet

    Apr 4, 2019 · Penalty $250

    Resolve
  • Class - 1

    Sec. 3304.7 required means of egress. at time of inspection on an active jobsite,observed worker present actively working in an excavated area between timber lagging(soe)& foundation wall at exp#1,approx 15ft

    Apr 4, 2019 · Penalty $2,500

    Resolve
  • Class - 1

    Sec: bc 3313.1, 3301.1.2. failure to comply w/ nyc fire code- general:no permit for oxygen,acetylene- use & storage @ job site. @ time of insp of a new 8 story bldg under construction @ file during stage, activ

    Jun 13, 2018 · Penalty $625

    Resolve
  • Class - 2

    Construction superintendent fails to maintain job site logs. @ time of insp of a 8 story new bldg under construction @ piles installation stage, active job site, upon request for the construction superintendent

    Jun 13, 2018 · Penalty $2,500

    Resolve
  • Class - 1

    Failure to provide unobstructed exit passageway. @ time of insp of a new 8 story bldg under construction @ pile drying stage, active job site, observed that there was an obstructed passageway from means of egre

    Jun 13, 2018 · Penalty $1,250

    Resolve
  • Class - 1

    Failure to provide guard rail system 3'-6' high @ open & accessible sides of excavation. @ time of insp of a new 8 story bldg @ pile drying stage, active job site, observed that there were no protection provide

    Jun 13, 2018 · Penalty $2,500

    Resolve
Show 19 more ↓
  • Class - 1

    Work does not conform to approved construction documents and or approved amendments as noted at time of inspection on an active constructionsite observed at exposure # 4 excavation below foundation of adjacent

    Feb 13, 2018 · Penalty $400

    Resolve
  • Class - 2

    Work doe snot conform to approved construction documents and or apprved amendments.premises under alt 2 job#320127947 permit exp.03-28-14.attime of inspection found:1 layout of partition and or configuration of

    Sep 15, 2017 · Penalty $500

    Resolve
  • Class - 2

    40m07,16m07. 40m/16m-provide keys for proper dob inspection.

    Apr 7, 2015

    Resolve
  • Class - 2

    40m07,16m07 provide keys for proper dob inspection.

    Apr 7, 2015

    Resolve
  • Class - 2

    17d06/ 12x10/ 37v02/ 32h11/ 08v01/ 71j01/ 70q03/ 70m07/ 10j01/ 40p16/ 17d secure where needed 32m worn car shoes 08v adjust where needed 71j mount switch at entrance to hatch 70q sump pump 70m ladder 10j adjust

    Oct 21, 2011

    Resolve
  • Class - 2

    70m07/ 52b14/ 70q03/ 08v01/ 17h11/ 17d06/ 39y02/ 40p16/ 70m ladder 52bshorten 70q sump pump 08v where needed 17h,s where needed 40p provide immediate 24/7 access to all equipment

    Oct 21, 2011

    Resolve
  • Class - 3

    Occupancy contrary to that allowed by the cert of occupancy or dob records.note:cert of occupancy#168724 dated 12/22/59 indicate bldg to be occupied as factory @ bsmnt factory & office @ 1st,2nd,3rd flr.@ time

    Mar 8, 2011 · Penalty $200

    Resolve
  • Non-hazardous

    1b10/2b10/5j1/8j1/10m7/10h11/17h11/28m7/38m7/40m7/84l10/55y13/55e10/41g7/41n7/85m5/86m5/64x10/66o2/71x10/74b14/84x10/.1b-alarm bell inaudible.2b-stop switch inaudible.5j-adjust car door to reduce gap.8j-adjust

    May 31, 2007 · Penalty $2,500

    Resolve
  • Non-hazardous

    Failure to maintain defect is: bottom of water tank on the roof is leaking (water is dripping heavily). remedy- repair defect.

    May 15, 2007 · Penalty $2,500

    Resolve
  • Non-hazardous

    50a 50b 32a cyclotherm 1984 n.b. 16309 50a reverse the valves on the bottom blowdown line so that the quick closing valve is closest to the boiler followed by the slow opening valve. 50b add a quick opening

    Mar 23, 2005

    Resolve
  • Non-hazardous

    50a 50b 1984 cyclotherm natl bd 16270 50a pipe safety valve to a safe point. 50b add a quick closing valve to the glass drain and pipe into the drain line.

    Mar 23, 2005

    Resolve
  • Non-hazardous

    50a 50b 50c 1984 cyclotherm natl bd 16311 50a install a quick opening valve to the glass drain and pipe into water column drain line 50b draft stat is loose. 50c seal flue pipe to chimney.

    Mar 22, 2005

    Resolve
  • Non-hazardous

    75u,74t. provide city id in mr equiptment.

    Nov 20, 1998

    Resolve
  • Non-hazardous

    18a,18b,

    May 1, 1996 · Penalty $175

    Resolve
  • Non-hazardous

    6b, 6b boiler has steam generating capacity of 2070 ibs/hr where as existing safety valve has a relieving capacity of 1223 lbs/ hr the later be replaced by new one with at least the capacity of the boiler or mo

    May 1, 1996 · Penalty $175

    Resolve
  • Hazardous

    Failure to maintain exterior building wall defect is brick parapet at front facade (located at east) is leaning and pulling away for approx 25'-0" feet in length, with defective cement stucco. remedy- provide a

    May 5, 1994 · Penalty $800

    Resolve
  • Non-hazardous

    32 no blow down valves on boiler remove plug replace with pet cock valve sight glass.

    May 18, 1993

    Resolve
  • Non-hazardous

    32.

    May 18, 1993

    Resolve
  • Non-hazardous

    35o,53x

    Mar 18, 1992

    Resolve

Complaints

No HPD complaints in our records

Complaint data is still being backfilled from NYC Open Data.

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Office building (O2)
Year built
1923
Floors
3
Residential units
—
Building area
101,395 ft²
Lot area
34,231 ft²
Zoning
M1-4
Community board
306
Council district
39
Block / lot
448 / 13
Assessed value
$5,265,000
Landmark / historic district
No

Questions about 530 President Street

Who owns 530 President Street?

The owner of record in NYC Department of City Planning PLUTO data is Pds Carroll Street LLC.

Does 530 President Street have violations?

NYC HPD has no housing violations on record for this property.

Is 530 President Street rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 530 President Street built?

City records list 1923 as the year it was built.