roofy

159 3 Avenue

Brooklyn, NY 11217BBL 3-00407-0001Map

Owner of record: Aast Holding Corp

159 3 Avenue is an elevator apartment building built in 2025 in Brooklyn, 11217. It has 92 residential units across 11 floors. The owner of record is Aast Holding Corp. HPD has recorded 2 housing violations here, most recently on October 15, 2026. 1 of the 2 most recent violations are still open.

HPD violations
2
DOB violations
2
ECB violations
25
HPD complaints
1

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Watch
Last violation Oct 15, 2026

Date of the most recent HPD inspection that found a problem.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 2

  • B

    Properly repair or replace the broken or defective venterlation system at ceiling in the bathroom located at apt 7e, 7th story, 2nd apartment from north at east

    Oct 15, 2026 · Apt 7E

    Open — Nov sent out
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    May 11, 2026

    Closed — Violation dismissed

DOB building violations · 2

  • Construction other optional

    C-construction other optional

    Mar 29, 1996

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Mar 18, 1993

    Dob violation - dismissed

ECB violations · 25

  • Class - 1

    At the time of my inspection of a 11 story new building, i observed jersey barriers at exposure #1 and 4 they were not interlocking and were empty, causing the wind to blow them over. failure to provide and mai

    Oct 31, 2025 · Penalty $2,500

    Resolve
  • Class - 1

    Bc 3307.2.1 at the time of my inspection of a 11 story new building, i observed office trailer on street at exposure #4. upon request for dot permit to place office trailer on street none was presented or at j

    Oct 31, 2025 · Penalty $5,000

    Resolve
  • Class - 2

    Bc 3303.3. atoi of 11 story new building at roof, building approximately 11398 square feet. site closed and there were no construction activity. upon shouting at perimeter and banging on fence and door to alert

    Oct 18, 2025 · Penalty $2,500

    Resolve
  • Class - 2

    At time of inspection of an inactive 11-story new building job site, observed jersey barriers (yodok) placed on the street not in accordance with manufacturer's specifications. barriers not securely connected o

    Oct 18, 2025 · Penalty $1,250

    Resolve
  • Class - 2

    Proposed 11 story nb with a building footprint (sq. ft.)11398. observed no construction activity takin place at the time of inspection. i walked around the outside of the building to take my pictures banged on

    Sep 20, 2025 · Penalty $5,000

    Resolve
  • Class - 2

    Observed yodoks installed contrary to manufacturing specifications. mix match components in use preventing all yodoks from interlocking together, also not filled with water as per specs which prevents shifting

    Sep 20, 2025 · Penalty $3,125

    Resolve
  • Class - 1

    Cns builders llc was notified on 08-06-25 that all hoisting & riggings was not permitted on site which was detailed in swo# 080625ct01 served to site. at time of audit rigging operation was observed, comply wit

    Aug 7, 2025 · Penalty $10,000

    Resolve
  • Class - 2

    Bc 28-105.12.8 a time of inspection observed: mini crane in place at main roof level upon reviewed site safety plan provided by site safety manager not equipment for hoisting materials activities found it. crea

    Aug 7, 2025 · Penalty $625

    Resolve
  • Class - 1

    Site safety manager# 3071 was notified on 08-06-25 that all hoisting & riggings was not permitted on site which was detailed in swo# 080625ct01 served to site. at time of audit rigging operation was observed.,

    Aug 7, 2025 · Penalty $10,000

    Resolve
  • Class - 1

    At time of inspection, a knuckle boom crane was on site hoisting machinery ' the crew involved with attaching and detaching the load was without all perons in the rigging crew with valid rigging certs.; bc 3316

    Aug 6, 2025 · Penalty $2,500

    Resolve
Show 15 more ↓
  • Class - 1

    At time of inspection, a knuckle boom crane was on site hoisting machinery, while under employment of gc. the crew involved with attaching and detaching the load was without all persons in the rigging crew with

    Aug 6, 2025 · Penalty $2,530

    Resolve
  • Class - 2

    Bc3303.3 watchperson 11 story new building, building approximately 11398 square feet. site closed and there were no construction activity. upon shouting at perimeter and banging on fence and door to alert wat

    Jul 19, 2025

    Resolve
  • Class - 2

    Observer jersey barriers installed at exp# 1 3 4 not as per manufacture specification. jersey barriers several not interlocked and not filled with sand/water which posing a potential hazard by allowing uninte

    Jul 19, 2025

    Resolve
  • Class - 2

    Windows were installed with u-factor 0.27 contrary to en and architectural drawing which is u-factor 0.25, conform work to approved construction documents/amendments; please go to https://www1.nyc.gov/site/buil

    Jun 6, 2025 · Penalty $1,250

    Resolve
  • Class - 2

    Work does not conform to approved construction documents and/or approved amendments. at time of inspection, observed construction fence between adjacent property 560 baltic st. rear yard do not conform to dob a

    May 28, 2025 · Penalty $625

    Resolve
  • Class - 2

    Note: atoi of a 11-story new building 11,398 sq ft. site was closed with no construction activity. i shouted around the perimeter and banged on the fence/door to alert a watchperson and verify code compliance,

    May 24, 2025 · Penalty $2,500

    Resolve
  • Class - 2

    At time of inspection observed: rasping styrofoam in progress using unsafe supported scaffold contrary to bc 3314.8 there is a gap 13 inches approx. open throughout between supported scaffold and facade of the

    May 14, 2025 · Penalty $2,530

    Resolve
  • Class - 2

    3308.6 horizontal safety netting. on expo#1 a horizontal netting system installed at the 9th floor with concrete stripping operations taking place on the 11th&10th floor. at the corner of expo#1 and expo#2 miss

    May 8, 2025 · Penalty $2,500

    Resolve
  • Class - 1

    Observe delivery been taken and blocking pedestrian walkway at the corner of baltic and 3 ave across the street from job site.contrary to ssp and dot stipulations. stop all delivery operation provide means an

    May 6, 2025 · Penalty $2,500

    Resolve
  • Class - 1

    At time of inspection, a knuckle boom crane was on site hoisting material. the operator of the knuckle boom crane did not hold a valid new york city hmo license at time of inspection. the hmo license is require

    Apr 30, 2025 · Penalty $5,000

    Resolve
  • Class - 2

    Observed the adjoining buildings window on the 1st floor covered with a mesh and enclosed by a construction fence, preventing the tenant of apartment 1r from escaping incase of an emergency. a pipe scaffold is

    Apr 24, 2025 · Penalty $1,000

    Resolve
  • Class - 1

    At time of inspection of an active jobsite of proposed 11 story new building at 2nd floor level during concrete operations. upon inspection on dob records no active new building permit was observed b00678425. o

    Feb 3, 2025

    Resolve
  • Class - 1

    At the time of my inspection of a 11 story new building at foundation/excavation phase, i observed at exposure #4 a ramp made from excavation dirt approximately 12 feet and there were no guardrail on either sid

    Nov 15, 2024

    Resolve
  • Class - 1

    At the time of inspection active site at excavation phase. i observed excavator in, use for pile driving operation at exposures#2 elevated on an angle and not on a flat surface as per manufacture specs creating

    Jun 27, 2024 · Penalty $2,500

    Resolve
  • Class - 2

    Work w/o a permit: work noted: front facade 1st fl erected business accessory awning "deli & grill" approx 4'h x 15'w x 4' projection. remedy: obtain all required permits.

    Aug 31, 2017 · Penalty $800

    Resolve

Complaints

  • General

    Ventilation system

    Sep 9, 2026 · Apt 7E

    Close

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Elevator apartment building (D7)
Year built
2025
Floors
11
Residential units
92
Building area
96,771 ft²
Lot area
11,800 ft²
Zoning
M1-4/R7X
Community board
306
Council district
39
Block / lot
407 / 1
Assessed value
$602,550
Landmark / historic district
No

Questions about 159 3 Avenue

Who owns 159 3 Avenue?

The owner of record in NYC Department of City Planning PLUTO data is Aast Holding Corp.

Does 159 3 Avenue have violations?

Yes. NYC HPD has recorded 2 housing violations at this property.

Is 159 3 Avenue rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 159 3 Avenue built?

City records list 2025 as the year it was built.

How many apartments are in 159 3 Avenue?

It has 92 residential units and 94 units in total.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.