1164 Wheeler Avenue
Bronx, NY 10472BBL 2-03739-0034Map
Owner of record: Wheeler Hotel LLC
1164 Wheeler Avenue is a hotel built in 2017 in Bronx, 10472. The owner of record is Wheeler Hotel LLC. HPD has no housing violations on record for this property.
- HPD violations
- 0
- DOB violations
- 7
- ECB violations
- 32
- HPD complaints
- 1
What to know
No open immediately-hazardous violations among recent records.
HPD has not cited this building.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 0
No HPD violations on record
DOB building violations · 7
- Construction other optional
Request for information:building is an 8 story steel structure that was reported to have improperly constructed the building in order to verify code compliance,plans and inspection reports are required for review.prov current plans of existing struct as-built.prov insp reprts incl clearly labeled photos+othr items req'd to verify existing const
Mar 18, 2021
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Sep 30, 2020
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Sep 30, 2020
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Sep 2, 2020
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Sep 2, 2020
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Sep 2, 2020
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
May 29, 2019
Dob violation - dismissed
ECB violations · 32
- Class - 1
Atoi observed electric hot water heater being in a storage room with no floor drain and a rubber tubing for the pressure relief draining into a garbage pale which must be corrected by licensed master plumber co
Aug 26, 2026 · Penalty $2,500
Active - Class - 2
At the time of inspection observed plastic pvc piping and fittings being used for drainage on the kitchen sink and the laundry slop sink contrary to . pc 1101.10 - pvc piping used for waste piping was observed
Aug 26, 2026
Resolve - Class - 1
At the time of inspection observed painted sprinkler heads and components of the sprinkler heads contrary to . bc 903.3.3 - automatic sprinklers shall be installed with due regard to obstructions that could del
Aug 26, 2026 · Penalty $2,500
Active - Class - 1
Failure to maintain building in code-compliant manner: no fire stopping per bc 712.3 (2014 code); 27-345; bc 711.2.4 (2022 code. at time of inspection notice holes in mechanical rm, lobby entrance and through o
Aug 21, 2025 · Penalty $2,530
Resolve - Class - 2
Observed at basement in sprinkler room gas valve installed on ball drip., repair and/or replace
Sep 4, 2024
Resolve - Class - 1
Work does not conform to approved(sws)construction document and/or approved amendment.at the time of inspection i observed active construction jobsite.upon review of sws approved dd sections shows/indicate shed
Jul 6, 2020 · Penalty $6,250
Resolve - Class - 1
Bc330161-design drawings(makeshift)at the time of inspection i observeactive construction jobsite.i observed 10 feet deep excavated pit ext#4 covered with wood plank and inadequate guardrail in place at toe req
Jul 6, 2020 · Penalty $2,500
Resolve - Class - 1
Bc3307.7=failure to provide protection construction fence at time of inspection on a jobsite inactive it was observed that construction fence was removed at exposure 3 and partial at exposure 4 leading to open
May 8, 2020 · Penalty $2,500
Resolve - Class - 1
Bc33012-no over head protection.note:at the time of inspection to the site on 1162 wheeler aven,observed people working on roof level and nooverhead protection on 1164 wheeler ave bldg.at exposure four adjacent
Feb 25, 2020 · Penalty $2,500
Resolve - Class - 1
Work does not conform to approved construction documents or and amendments pipe scaffold expo 1 & 3 at the time of inspection at a 8 story nb,i observed on the ground level pipe scaffold was not built to approv
Feb 5, 2020 · Penalty $1,250
Resolve
Show 22 more ↓
- Class - 2
Jobsite fence not constructed or maintained pursuant to subsection. attime of inspection i observed the rear plywood fence at exp#2&3 are leaning toward the job site,fence post footings are exposed & plywood
Sep 13, 2019
Resolve - Class - 2
Work does not conform to approved construction documents &/or approvedamendments. at time of inspection i observed the sidewalk shed on exp#1 is one continous 1 level platform,after reviewing plans i noticed it
Sep 13, 2019
Resolve - Class - 1
Failure to designate competent person.at time of inspection on an active jobsite based on construction superintendent daily log designated competent person jeffrey chao is signing as competent person on multip
Mar 4, 2019 · Penalty $10,000
Resolve - Class - 2
Bc3307.6.5.7/no installation inspection report for sidewalk shed.at time of inspection on an active jobsite i observed sidewalk shed installed at exp#1 upon request for installation inspection report non was pr
Mar 4, 2019 · Penalty $625
Resolve - Class - 1
Work w/o a permit. at time of inspection on an active job site i observed needle beams with supported pipe scaffold on top on exp4 used as overhead protection for adjacent property. when asked for permit and de
Mar 4, 2019
Resolve - Class - 2
Bc3314.4.3.3/no installation inspection report for supported pipe scaffold.at time of inspection on an active jobsite i obsered supported pipe scaffold at exp #1,2,3,4 approx.80ft in height.upon request for ins
Mar 4, 2019 · Penalty $625
Resolve - Class - 2
Housekeeping.at time of inspection of 8 story nb at bulkhead sheetrocking phase i observed an extensive about of garbage and debris in room/halls/stairs/front entrance blocking egress of employees and first res
Jan 29, 2019
Resolve - Class - 2
Failure to provide approved/accepted plans at job site at time of inspection. at time of inspection the violating conditions are as follows 2 male workers on 2nd fl exposure#4 installing framing and drywall und
Aug 15, 2018
Resolve - Class - 1
Bc3305.3.6.1.2/reshores in proximity to unenclosed perimeters;a time of inspection of an ew 8 story building at 8th flr,construction work inprogress.i observed reshores on expo 1 & 3 at 7th and 8th flr were not
Jan 24, 2018 · Penalty $1,600
Resolve - Class - 1
Bc3314.4.4.5/dislodgement.at time of inspection of a new 8 story building at 8th flr construction work in progress.i observed planking on the supported scaffold at expo 1 and 3 was not clean and debris netting
Jan 24, 2018 · Penalty $1,600
Resolve - Class - 1
Bc3308.5/vertical safety netting.at the time of inspection of a new 8 story building currently at the 8th flr,construction work in progress.i observed tha there were inadequate vertical netting provided from 2n
Jan 24, 2018 · Penalty $400
Resolve - Class - 2
Housekeeping/at the time of inspection of a new 8 story building at 8th flr construction work in progress.i observed debris of combustible material on different locations of the buildings.i observed also floodi
Jan 24, 2018
Resolve - Class - 2
Failure to institute and maintain safety equipment measures and temporary construction.at the time of my inspection of a new 8 story building at 8th flr,construction work in progress.i observed 2 workers at 8th
Jan 24, 2018 · Penalty $5,000
Resolve - Class - 1
Work does not conform to approved construction documents and or approved amendments.at the time of my inspection of a new 8 story building at 8th flr,construction work in progress.i observed at the elevator sha
Jan 24, 2018 · Penalty $250
Resolve - Class - 2
Failure to institute and maintain safety equiptment measures and temporary construction.at the time of my inspection of a new 8 story building currently at 8th flr,construction work in progress,i observed 2 wor
Jan 24, 2018 · Penalty $5,000
Resolve - Class - 2
Construction superintendent fail to perform duties as per rule.the following hazardous conditions was observed and stop work order was issued to this construction sit on this date.inadequate vertical safety net
Jan 24, 2018 · Penalty $400
Resolve - Class - 2
Insulation placement and/or r-values do not meet min required. nb job #220517527. at time of an energy compliance inspection. i observed that the exterior walls on exp#4 on 2d and 3rd flr were installed w/o
Jan 18, 2018 · Penalty $2,000
Resolve - Class - 1
3309.1 failure to provide roof protection at adjoining property. as noted: at time of inspection on an active construction site, reinforced concrete building is approx. 40 feet in height and 4 stories. failure
Oct 18, 2017 · Penalty $400
Resolve - Class - 2
Bc3307.7.7/condition of fences;at the time of inspection it was observed that the construction was not maintained per code.viewing panels were not maintained making it difficult to see through.rem:maintain fenc
May 16, 2017
Resolve - Class - 2
Work does not conform to approved construction documents.@ time of inspection observed an active construction site w/ excavation work in progress.during inspection noted that the contractor excavated @ exp3 & 4
Apr 13, 2017
Resolve - Class - 2
Inadequate construction superintendent logs.@ time of inspection observed an active construction site w/ excavation work in progress.during inspection noted that the construction superintendent was not on site
Apr 13, 2017
Resolve - Class - 1
No guard rails.@ time of inspection observed an active construction site w/ excavation work in progress.during inspection noted that there is no guard rails around excavation as required by code creating a haza
Apr 13, 2017 · Penalty $1,200
Resolve
Complaints
- Heat/hot water
Entire building
Jul 7, 2026 · Apt BLDG
Close
Sales history
No recorded sales in our data
Building details
- Building type
- Hotel (H3)
- Year built
- 2017
- Floors
- 8
- Residential units
- —
- Building area
- 27,975 ft²
- Lot area
- 6,691 ft²
- Zoning
- C4-2
- Community board
- 209
- Council district
- 17
- Block / lot
- 3739 / 34
- Assessed value
- $3,714,750
- Landmark / historic district
- No
HPD registration #229357, last renewed Dec 8, 2025.
Questions about 1164 Wheeler Avenue
Who owns 1164 Wheeler Avenue?
The owner of record in NYC Department of City Planning PLUTO data is Wheeler Hotel LLC.
Does 1164 Wheeler Avenue have violations?
NYC HPD has no housing violations on record for this property.
Is 1164 Wheeler Avenue rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 1164 Wheeler Avenue built?
City records list 2017 as the year it was built.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.