2680 Morris Avenue is an elevator apartment building built in 2023 in Bronx, 10468. It has 36 residential units across 12 floors. The owner of record is 2680 Morris LLC. HPD has recorded 8 housing violations here, most recently on September 28, 2006. 8 of the 8 most recent violations are still open.
- HPD violations
- 8
- DOB violations
- 2
- ECB violations
- 58
- HPD complaints
- 24
What to know
Immediately hazardous issues among recent violations are still open.
Date of the most recent HPD inspection that found a problem.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 8
- IInformation / order
The premises or apts. have been vacated by the department and cannot be reoccupied until so ordered after proof of compliance for conversion to illegal 1 sty apartment at detached garage rear yard (vacate # 45784..09/28/2006)
Sep 28, 2006
Open — Info nov sent out - BHazardous
Discontinue use of rooms for living, disconnect plumbing fixtures where illegal and properly seal pipe connections , the detached garage converted into class ( a ) apartment at rear yard
Sep 7, 2006
Open — Nov sent out - BHazardous
Discontinue unlawful cooking space or file plans and application with this department to legalize same, if lawfully feasible ,the detached garage converted into class (a) apt. at rear yard
Sep 7, 2006
Open — Nov sent out - BHazardous
Section 9, 56, 193, 300, 302 m.d. law- above frame building has been converted from a private dwelling to a multiple dwelling and is now occupied and maintained as such contrary to law.restore premises to lawful occupancy
Sep 7, 2006
Open — Nov sent out - CImmediately hazardous
Abate the nuisance consisting of water leak at ceiling in the 2nd room from east at north located at apt 1, 1st story, 1st apartment from south at west
Jul 22, 2005 · Apt 1
Open — Nov sent out - CImmediately hazardous
Trace and repair the source and abate the nuisance consisting of mold ... mildew at ceiling in the 1st room from east at north located at apt 1, 1st story, 1st apartment from south at west
Jul 22, 2005 · Apt 1
Open — Nov sent out - BHazardous
Repair the broken or defective plastered surfaces and paint in uniform color the ceiling in the 2nd room from east at north located at apt 1, 1st story, 1st apartment from south at west
Jul 22, 2005 · Apt 1
Open — Nov sent out - CImmediately hazardous
Abate the nuisance consisting of rodents rats in the entire apartment located at apt 2, 1st story
Sep 27, 2003 · Apt 2
Open — Nov sent out
DOB building violations · 2
- Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Aug 7, 2024
Dob violation - dismissed - Construction other optional
The department of building orders that you stop all work under permit# 210179545 nb-fo-ea due to the applicant's withdrawal from the project.
Jun 14, 2023
Dob violation - dismissed
ECB violations · 58
- Class - 2
Failure to post permit at premises for work. permit#210179545-01-nb, post/properly post permit; post permits.
Oct 8, 2026 · Penalty $300
Active - Class - 2
Observed styrofoam fly around and entering adjacent property at 2676 morris ave (cinnamon beauty salon) effecting business. under permit#210179545-01-nb., repair and/or replace; comply with code.
Oct 8, 2026 · Penalty $1,250
Active - Class - 2
At time of inspection, ssc lic. #002491 was designated as ssc under permit 210179545 at 2680 morris ave and actively designated on pw2 as cs under permit x00911251-i1-gc at 1740 university ave. logs confirm sig
Aug 10, 2026 · Penalty $2,500
Active - Class - 2
During the inspection of the construction 12-story building, inadequate housekeeping was observed. debris and materials on top of sidewalk shed in disorganized manner. deck/platform of a sidewalk shed must be k
Mar 23, 2026
Resolve - Class - 1
At time of inspection on a active jobsite 12-story new building at roof, i observed air pressurized alarm system for the stand pipe onsite as per the department of buildings records electrical permit for stand
Nov 3, 2025 · Penalty $800
Resolve - Class - 2
At time of inspection observed active construction activities. at exp.1 notice two non commercial vehicles park on storage area. as per sitesafety plan it shows this are to be use for storage and debris contain
Sep 8, 2025
Resolve - Class - 2
At time of inspection observed active construction activities. on roof level observed unsafe working platform between stair, upon requesting design drawings they were not provided. upon requesting six months i
Sep 8, 2025 · Penalty $1,250
Resolve - Class - 1
At time of inspection observed active construction activities. sws installed at exp. 1 does not conform to approved drawings. several discrepancies observed, missing cross braces, horizontal post, vertical post
Sep 8, 2025 · Penalty $2,500
Resolve - Class - 1
12 story nb active site.observed no/missing or inadequate guardrail systems in multiple location onsite/missing loose netting. floor opening without guardrail systems.1/2 in plywood throughout all floors. not a
Feb 13, 2025 · Penalty $5,000
Resolve - Class - 2
12 story new building active site. observed supported scaffolding on top of needle beams cantilevered at exp#2,4 on 2nd & 9 fl. upon request to contractor for loads imposed letter by engineer of record. none we
Feb 13, 2025 · Penalty $1,250
Resolve
Show 40 more ↓
- Class - 2
12 story nb active site. observed sidewalk shed in place at exp#1 permit#x00746676. observed 2 missing section of vertical members posts 8x10ft with makeshift connections of 1 1/2 inch pipes for vertical post e
Feb 13, 2025
Resolve - Class - 2
12 story nb active site.observed 2 levels of angle brackets approximately 3 ft on installed and in place on bulkhead of roof. with guardrail systems attached for concrete pour. upon request to contractor for de
Feb 13, 2025 · Penalty $1,250
Resolve - Class - 2
12 story nb active site. observed no/missing or inadequate signage on all floors onsite. no exit signage, no smoking, fire extinguisher signage onsite. unsafe not posting signage for adequate ingress/egress for
Feb 13, 2025 · Penalty $2,500
Resolve - Class - 2
12 story nb active site. observed inadequate housekeeping onsite large pile of combustible materials wood piled 4ft in height x 12 ft on 1st floor at exp#1 ground level behind construction fence . covering shed
Feb 13, 2025 · Penalty $3,125
Resolve - Class - 2
3301.6 manufacturer specifications, design, and capacity- observed makeshift concrete washout in use at street level of jobsite. upon request for design drawings for the washout none were provided at the time o
Dec 4, 2024 · Penalty $2,500
Resolve - Class - 2
Observed inadequate housekeeping throughout entire jobsite. the housekeeping consist of large amounts of construction debris & materials.maintain adequate housekeeping as per code
Dec 4, 2024
Resolve - Class - 2
Observed needle beams installed 2nd fl expo 4 of jobsite. upon review of approved drawings 3 post are required for securement however double the required is installed. underneath needle beam 1 osha plank is req
Dec 4, 2024
Resolve - Class - 2
Observed standpipe installed in jobsite reaching 9th floor. upon request for hydrostatic test from onsite personnel, none were provided at the time of inspection.provide/maintain documents to be kept onsite
Dec 4, 2024 · Penalty $1,250
Active - Class - 2
3308.6.1.4 alternative systems-observed supported pipe scaffold used for protection as alternate means of horizontal netting. pipe scaffold reaches 9th fl below line of work @ roof lvl not providing full enclos
Dec 4, 2024 · Penalty $2,500
Resolve - Class - 2
Observed hoist installed at exposure 1 of jobsite. hoist is connected to diesel fueled generators for power. upon review of dob approved drawings it shows the hoist to be powered through electrical means & show
Oct 15, 2024
Resolve - Class - 2
3301.5 unsafe conditions-observed 2 diesel generators on the ground inside of building to operate hoist, generators w/out caz, fire safety measures and discharge of carbon monoxide in place. no certificate of f
Oct 15, 2024 · Penalty $2,500
Resolve - Class - 2
3310.8.4 site safety log- jobsite continued work since 07-15-2024 protection for adjacent properties not corrected, sup scaff not corrected, building not enclosed w/alternate system, hoist in use not on ssp in
Oct 15, 2024 · Penalty $1,250
Active - Class - 2
28-110.2 phased site safety plans- observed hoist installed @ expos1 of jobsite upon review of provided site safety plan it does not reflect the current field conditions of hoist @ exposure 1 of jobsite. stop a
Oct 15, 2024 · Penalty $625
Resolve - Class - 2
3301.1.2 fire code- observed 2 diesel fueled generators in interior of jobsite on 1st floor. upon request for required fdny permit for the generators, none were provided at the time of inspection. stop all use
Oct 15, 2024 · Penalty $2,500
Resolve - Class - 2
Observed work on major building above 75 feet continued since 07-15-2024 while protection for adjacent properties ( needle beams ) not corrected, pipe scaffold not corrected, building not enclosed w/ alternativ
Oct 15, 2024 · Penalty $5,000
Resolve - Class - 2
During my inspection, i observed exposure 2 adjacent property at the 6 floor level window protection, not in place. ecb violation served bc 3309.1/ 3309.14 provide the required protection.
Sep 26, 2024 · Penalty $5,000
Resolve - Class - 2
At the time of my inspection of a 12-story nb. i observed throughout the site inadequate temporary lighting, which constitutes a danger to workers & dob/ emergency workers. ecb violation served bc 3303.2.3.1
Sep 26, 2024 · Penalty $2,500
Resolve - Class - 1
At time of inspection of 11 story new building in progress observed forming work at 10 fl level with hoist not in operating conditions creating hazards. stop all work above 75'have hoist in operational conditio
Sep 19, 2024 · Penalty $5,000
Resolve - Class - 1
Bc 3308.1 unenclosed perimeter protection. obvd propsd 12 str nb at 8fl with vert sfty cabls/netng and/or guard rails missing, partially removed & severely loosened in multiple areas & flrs. also obsvd 1 area a
Jul 15, 2024 · Penalty $5,000
Resolve - Class - 2
Bc 3303.7.2 fire extinguishers. obsvd proposed 12 str nb at 8fl with the majority of fire extinguishers on site not having the appropriate fdny-approved service/inspection tags as required by fc 901.6.. provide
Jul 15, 2024 · Penalty $2,500
Resolve - Class - 2
Obsvd proposed 12 str nb at 8fl with adj building at exp#4 having inadequate roof protection- parapet walls not protected- and with the top floor windows of the exp#2 adj building not protected despite being di
Jul 15, 2024 · Penalty $5,000
Resolve - Class - 2
Obsvd sup scaf at exps# 1,2,3,4- scaf in use- w/ the exp#1 scaf having been erected on top of the sws at exp#1. upn request for the: sup scaf installation report, sup scaf daily inspn log; sws loads imposed rep
Jul 15, 2024 · Penalty $1,250
Resolve - Class - 2
Bc 3308.6 horizontal safety netting systems. obsvd propsd 12 sr nb with 8th flr/str (poured) with an aprx 20ft wide gap at exp#1 btwn the sup scaf sections (serving as alt system). per bc 3308.6, the nb having
Jul 15, 2024 · Penalty $2,500
Resolve - Class - 2
Observed needle beam pltfm at 2nd fl, exp#4 w/ sup scaf on top w/ needle beams instld contr to plans- anchors/tie down diff size than on plan, no masonry expansion bolts at top conctn of shoring post to slab. o
Jul 15, 2024
Resolve - Class - 1
While conducting a safety compliance inspection on a closed jobsite, i observed construction equipment stored on the street. above the yodok without adequate pedestrian protection provided that will provide s
May 27, 2024 · Penalty $1,250
Resolve - Class - 2
Fail to provide adequate fire extinguishers on entire site. at time of inspection observed active jobsite currently working on all floors. notice missing fire extinguishers on third and fourth floor and inadequ
Apr 15, 2024 · Penalty $2,500
Resolve - Class - 2
At time of inspection of a12 story new building observed sidewalk shed in place with vertical members not 18" from curb line causing a hazard to public.place vertical members 18" from curbline
Jan 25, 2024 · Penalty $2,400
Resolve - Class - 2
At time of inspection of 12 story new building observed construction fence in place not maintained broken plywood at driveway causing hazardous conditions to public.remove unsafe conditions.
Jan 25, 2024 · Penalty $1,000
Resolve - Class - 1
12 story nb jobsite under construction, i observed in places at exposure 2&4 with formwork and use of existing structures to support vertical or lateral loads imposed prior concrete operation. upon request for
Jan 3, 2024 · Penalty $5,000
Resolve - Class - 2
Active 12 nb jobsite under construction, i observed no safety adequate protection in places at exposure-2 adjoining walkway, no protection to adjoining roof exp-4 and adjoining wall exposure-4 potentially compr
Jan 3, 2024 · Penalty $1,250
Resolve - Class - 2
Active 12 story nb. i observed at exposure 1 storage zone roadway office trailer and concrete washout box with no pedestrian protection and after reviewing the system no up dated dot permit were found. ecb viol
Jan 2, 2024 · Penalty $2,500
Resolve - Class - 1
At time of inspection, observed active jobsite currently on superstructure phase. at exposure 1 and 3 observed deep excavations greater than 5 feet. no guardrail system installed at any of this excavations nor
Dec 14, 2023 · Penalty $5,000
Resolve - Class - 1
Failure to comply with code 28-103.21.1 reporting. permitholder didn't report incident within allowed time after such incident occurred on 08/31/2023 subject to permitting by the commissioner under permit # 21
Sep 28, 2023
Resolve - Class - 2
Permitholder failed to maintain adequate housekeeping at working area. the accumulated standing water, rocks and mud on site an on the egress areas creating a hazardous of slipping and falling which resulted of
Aug 31, 2023 · Penalty $625
Resolve - Class - 2
Gc failed to comply with dot stipulation, at the time of my inspection of an inactive 12 story nb with office trailer and storage zone in-place at exposure 1 rdway morris ave & after reviewing dot records i fou
Aug 5, 2023 · Penalty $1,250
Resolve - Class - 1
At time of complaint inspection at new 12 story building currently at excavation phase i observed 3 workers working on jobsite fence at expo#2 upon request to see site safety coordinator worker( competent perso
Jun 12, 2023 · Penalty $10,000
Resolve - Class - 1
Access during excavation. at time of inspection i observed inadequate means of egress/ingress 1 ladder inadequately maintained during excavation phase which should have 2 means of egress ( 2 ladders ) and kep
Jun 7, 2023 · Penalty $2,500
Resolve - Class - 2
In response to incident i observed car that was hit by barriers in street area that had tipped over by leaning scaffold sections on barriers which were overloaded. failure to properly secure and maintain barrie
Jun 7, 2023 · Penalty $5,000
Resolve - Class - 1
At time of inspection i observed inadequate guardrails used at excavation phase which are unable to withstand the 200 pounds of pressure without tipping over resulting in injury . failure to provide proper guar
Jun 7, 2023 · Penalty $5,000
Resolve - Class - 2
Water conditions. at time of inspection i observed standing water approx. 8 inches inside pit area at excavation phase creating a health hazard and is a breeding ground for mosquitoes and other rodents.properly
Jun 7, 2023
Resolve
Complaints
- Heating
Heat related
Sep 5, 2006 · Apt 1A
Close - General
Doors
Jul 18, 2006 · Apt 1A
Close - Nonconst
Vermin
Jul 18, 2006 · Apt 1A
Close - General
Floor
Jul 18, 2006 · Apt 1A
Close - General
Mold
Jul 18, 2006 · Apt 1A
Close - Electric
Lighting
Jun 16, 2005 · Apt 1
Close - Plumbing
Water-leaks
Jun 16, 2005 · Apt 1
Close - Construction
Pavement
Apr 28, 2005 · Apt 2
Close - General
Cooking gas
Apr 28, 2005 · Apt 2
Close - Plumbing
Water supply
Jan 27, 2005 · Apt 2FL
Close
Show 14 more ↓
- Plumbing
Water supply
Jan 26, 2005 · Apt 2FL
Close - Paint/plaster
Ceiling
Aug 5, 2004 · Apt BSMT3
Close - General
Doors
Aug 5, 2004 · Apt BSMT3
Close - Paint/plaster
Door/frame
Aug 5, 2004 · Apt BSMT3
Close - General
Mold
Aug 5, 2004 · Apt BSMT3
Close - Plumbing
Water-leaks
Aug 5, 2004 · Apt BSMT3
Close - Nonconst
Rubbish
Jan 28, 2004 · Apt BLDG
Close - Nonconst
Rubbish
Jan 28, 2004 · Apt BLDG
Close - Heating
Heat related
Jan 13, 2004 · Apt 2
Close - Heating
Heat related
Jan 11, 2004 · Apt 3PH
Close - Electric
Electric-supply
Jan 11, 2004 · Apt 3PH
Close - Electric
Electric-supply
Jan 11, 2004 · Apt 2
Close - Heating
Heat related
Jan 11, 2004 · Apt 2
Close - Nonconst
Odor
Sep 22, 2003 · Apt 2
Close
Sales history
No recorded sales in our data
Building details
- Building type
- Elevator apartment building (D7)
- Year built
- 2023
- Floors
- 12
- Residential units
- 36
- Building area
- 44,762 ft²
- Lot area
- 6,029 ft²
- Zoning
- R8
- Community board
- 207
- Council district
- 14
- Block / lot
- 3316 / 11
- Assessed value
- $2,700,000
- Landmark / historic district
- No
Questions about 2680 Morris Avenue
Who owns 2680 Morris Avenue?
The owner of record in NYC Department of City Planning PLUTO data is 2680 Morris LLC.
Does 2680 Morris Avenue have violations?
Yes. NYC HPD has recorded 8 housing violations at this property.
Is 2680 Morris Avenue rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 2680 Morris Avenue built?
City records list 2023 as the year it was built.
How many apartments are in 2680 Morris Avenue?
It has 36 residential units and 38 units in total.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.