roofy

1916 Longfellow Avenue

Bronx, NY 10460BBL 2-03016-0033Map

Owner of record: 1916 Longfellow LLC

1916 Longfellow Avenue is an elevator apartment building built in 2025 in Bronx, 10460. It has 69 residential units across 9 floors. The owner of record is 1916 Longfellow LLC. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
5
ECB violations
32
HPD complaints
0

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 5

  • Construction other optional

    At time of inspection building has been observed having superintendent withdrawn from under application # 220682688. until a new permit holder is in place to ensure inspection occurs all work must stop immediately.

    Feb 10, 2026

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Nov 25, 2020

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Nov 25, 2020

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Nov 25, 2020

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Sep 30, 2020

    Dob violation - dismissed

ECB violations · 32

  • Class - 2

    3303.7.7.2 standpipes- observed standpipe installed in active 9 story jobsite from 1st floor to roof. the stand pipe is not in a state of readiness. no red paint ahs been applied to standpipe and upon request f

    May 9, 2026 · Penalty $2,500

    Resolve
  • Class - 1

    Observed active stucco operations on shed of jobsite at exposures 1&4 with material storage on shed. review of dob records show that there is a pswo in place stating stop all work on shed deck issued 4-11-2026.

    May 9, 2026 · Penalty $10,000

    Resolve
  • Class - 2

    3301.5 unsafe conditions- at multiple locations i active jobsite staircase, observed live electrical components wrapped/connected to standpipe system. this creates a hazardous electrical condition due to standp

    May 9, 2026 · Penalty $2,500

    Resolve
  • Class - 2

    Observed sws @ exp 1 & 4 missing components. specifically required cross bracing ( cross bar) at both ends of the sidewalk shed were missing, contrary to approved plans. stop all use of sidewalk shed deck. comp

    Apr 11, 2026

    Resolve
  • Class - 1

    9 story new building active site.interior elevator not maintained in a state of readiness for safe operation, constituting a hazardous condition to worker's/visitor's & first responders. equipment not operation

    Mar 25, 2026 · Penalty $2,500

    Resolve
  • Class - 2

    9 story new building active site. observed makeshift staircases installed from cellar to 1st floor. stairs were attached to cmu walls. in use by worker's onsite. upon request to contractor for engineered design

    Mar 25, 2026

    Resolve
  • Class - 2

    Work contrary to c hook plans.9 story new building active site at facade phase under nb permit. observed c hook installed with wire ropes attached to platforms in prep for use. on roof level parapet clamps had

    Mar 25, 2026

    Resolve
  • Class - 2

    9 story new building active site at facade phase under nb permit. observed c hook installed with wire ropes attached to platforms in prep for use.on roof level wire ropes not maintained for safe use.multiple ki

    Mar 25, 2026

    Resolve
  • Class - 1

    At time of inspection of a 9 story building approximately 84 ft. no hoist was in place in state of readiness. failure to provide safe access and egress to elevated work areas creates an unsafe condition at time

    Dec 22, 2025 · Penalty $5,000

    Active
  • Class - 1

    At the time of my inspection of a 9 story new building approximately 7098 square feet, site was closed and there was no construction activity. upon shouting at perimeter and banging on fence to alert watchperso

    Dec 21, 2025

    Resolve
Show 22 more ↓
  • Class - 1

    At time of inspection, observed active jobsite. observed heavy machinery on site above cellar. no construction fence installed at exposure 3 as per site safety plan provided. there is accumulation of debris at

    Oct 10, 2024 · Penalty $5,000

    Resolve
  • Class - 1

    At time of inspection, observed active demolition site. upon inspecting site observed heavy machinery on site right above cellar. no permit as per dob records for mechanical demolition.

    Oct 10, 2024 · Penalty $1,250

    Resolve
  • Class - 1

    At time of inspection, observed active demolition site. upon inspection observed heavy machinery in use. as per dob records site was file as hand held equipment and mechanical means only for foundation removal.

    Oct 10, 2024 · Penalty $1,250

    Resolve
  • Class - 2

    At time of inspection, observed active demolition site. site being demo is approx. semi attached to adjacent property. adjacent property has crack on wall upon requesting pre construction survey to cp and prope

    Oct 10, 2024 · Penalty $1,250

    Resolve
  • Class - 2

    At time of inspection observed active demolition site. upon inspection observed excessive accumulation of debris at exposure 1, 3 and 4. tripping hazards observed on site and sidewalk. on sidewalk observed a ho

    Oct 10, 2024

    Resolve
  • Class - 1

    At time of inspection observed active demolition site. upon inspecting observed several unsafe conditions. active heavy machinery located on top of cellar slab. missing construction fence at exposure 3 between

    Oct 10, 2024

    Resolve
  • Class - 2

    Construction fence erected not erected per subsection. noted: jobsite fence erected under permit #x00557167-i1-fn has fallen to public sidewalk along longfellow avenue frontage., comply with code; comply with c

    Jan 13, 2024 · Penalty $2,500

    Resolve
  • Class - 2

    At the time of inspection, observed cracked and damaged sidewalk on exposure 4 creating tripping hazard to public. owner failed to maintain clear housekeeping for the area used by public as required by 3303.4.1

    Mar 22, 2023

    Resolve
  • Class - 2

    Due to portion of construction fence at exposure #4 wood panels are missing there is no protection to the public at this job site. this condition is a hazard to the public due to the site it is not enclosed.

    Feb 21, 2023 · Penalty $500

    Resolve
  • Class - 2

    Construction fence permit expired on 4/07/2022.re-new construction fence permit.

    Feb 21, 2023

    Resolve
  • Class - 2

    Portion of construction fence at exposure # 4 wood panels is missing approx. 10 feet.enclose construction fence with new wood panels at exposure #4.

    Feb 21, 2023

    Resolve
  • Class - 1

    A 4 story nb at excavation phase closed site. i observed sidewalk not maintained as per code at exp#4 the sidewalk seems to be partially collapsed approximately 10 by 10 section of sidewalk has a sink hole appr

    Dec 7, 2022 · Penalty $2,500

    Resolve
  • Class - 2

    An 8 story nb closed site. i observed fence not maintained at exp#1,4. fence was leaning on to pedestrian walkway gaps aprox 1 to 2 feet partially open to public. also holes nails protruding unlawful graffiti.

    Dec 7, 2022

    Resolve
  • Class - 2

    A proposed 8 story building at excavation phase closed site. i observed large amount of accumulated/pockets of pooling water along adjoining property wall at foundation level at exp#2 not properly drained.poten

    Dec 7, 2022

    Resolve
  • Class - 2

    Bc3301.2 ac27-1009(a) failure to safeguard all persons & property affected by construction operations-jobsite open to pubic at exp #4.noted:at time of inspection of proposed 8 story jobsite observed constructio

    May 6, 2022

    Resolve
  • Class - 2

    Temporary construction equipment on site expired permit for constructin fence.noted:at time of inspection of proposed 8 story nb at support of excavation phase observed construction fence in place at exp #1 #2

    May 6, 2022

    Resolve
  • Class - 2

    Jobsite fence not const or maintained pursuant to subsec.atoi on 8stynb jobsite in excavation phase i observed const fence installed@exp1&4-const fence isnt being maintained to code due to following-(1)viewing

    Jan 14, 2022

    Resolve
  • Class - 1

    Failure to provide pre-shift meeting at time of my inspection of an active demolition jobsite with 5 workers onsite.upon requesting preshiftmeeting for worker none was provided at time of my inspection.preshift

    Aug 25, 2020 · Penalty $5,000

    Resolve
  • Class - 1

    Housekeeping inadequate.at time of my inspection of an active jobsite with 5 workers onsite.i observed a large amount of construction debri accumulated piled up of.this creates a unsafe situation for neighborin

    Aug 25, 2020 · Penalty $625

    Resolve
  • Class - 1

    Failure to maintain a record of orientations at worksite at time of myinspection of an active-demolition jobsite with 5 workers.i requested to see site safety orientations for workers and none was provided to m

    Aug 25, 2020 · Penalty $12,500

    Resolve
  • Class - 2

    Pedestrian protetcion does not meet code at time of my inspection of a 2 story building observed a construction fence at a demo site constructionf ence is inadequate and should be full enclosed i observed a 3

    Jul 10, 2020 · Penalty $2,400

    Resolve
  • Class - 1

    Failure to safeguard all persosn & property at time of my inspection fo a demo 2 story buildingi observed no overhead protetcion at neighboring building exp #2 and at exp #1,4 sidewalks as per section (3307,6)

    Jul 10, 2020 · Penalty $10,000

    Resolve

Complaints

No HPD complaints in our records

Complaint data is still being backfilled from NYC Open Data.

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Elevator apartment building (D1)
Year built
2025
Floors
9
Residential units
69
Building area
60,247 ft²
Lot area
8,731 ft²
Zoning
R8X
Community board
206
Council district
15
Block / lot
3016 / 33
Assessed value
$160,830
Landmark / historic district
No

Questions about 1916 Longfellow Avenue

Who owns 1916 Longfellow Avenue?

The owner of record in NYC Department of City Planning PLUTO data is 1916 Longfellow LLC.

Does 1916 Longfellow Avenue have violations?

NYC HPD has no housing violations on record for this property.

Is 1916 Longfellow Avenue rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 1916 Longfellow Avenue built?

City records list 2025 as the year it was built.

How many apartments are in 1916 Longfellow Avenue?

It has 69 residential units.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.