Owner of record: Concourse Village INC
773 Concourse Village E is an elevator apartment building built in 1964 in Bronx, 10451. It has 936 residential units across 25 floors. The owner of record is Concourse Village INC. HPD has recorded 837 housing violations here, most recently on October 1, 2026. 46 of the 50 most recent violations are still open.
- HPD violations
- 837
- DOB violations
- 286
- ECB violations
- 106
- HPD complaints
- 1,660
What to know
Immediately hazardous issues among recent violations are still open.
Date of the most recent HPD inspection that found a problem.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 837
- ANon-hazardous
Trace and repair the source and abate the visible mold condition... observed less than 10 sq ft at ceiling in the bathroom located at apt 18d, 18th story, 1st apartment from east at south
Oct 1, 2026 · Apt 18D
Open — Notice of issuance sent to tenant - ANon-hazardous
Paint with light colored paint to the satisfaction of this department at ciling and all walls in the entire apartment located at apt 18d, 18th story, 1st apartment from east at south
Oct 1, 2026 · Apt 18D
Open — Nov sent out - BHazardous
Trace and repair the source and abate the visible mold condition... observed more than 10 sq ft but less than 30 sq. ft at north wall in the 1st room from east located at apt 18d, 18th story, 1st apartment from east at south
Oct 1, 2026 · Apt 18D
Open — Notice of issuance sent to tenant - ANon-hazardous
Paint with light colored paint to the satisfaction of this department the west wall at public hall, 19th story
Sep 5, 2026
Open — Nov sent out - ANon-hazardous
Properly repair with similar material the broken or defective fire retardant material on west wall at public hall, 19th story
Sep 5, 2026
Open — Nov sent out - BHazardous
Repair, replace or provide an approved and operational smoke detecting device, installed in accordance with department of buildings rules and regulations defective in the entire apartment located at apt 8n, 9th story, 3rd apartment from west at north
Sep 2, 2026 · Apt 8N
Open — Invalid certification - BHazardous
Repair, replace or provide an approved and operational carbon monoxide detecting device, installed in accordance with applicable law and rules defective in the entire apartment located at apt 8n, 9th story, 3rd apartment from west at north
Sep 2, 2026 · Apt 8N
Open — Invalid certification - BHazardous
Properly repair the source and abate the evidence of a water leak at east wall in the bathroom located at apt 8n, 9th story, 3rd apartment from west at north
Sep 2, 2026 · Apt 8N
Open — Civ14 mailed - ANon-hazardous
Repair the broken or defective plastered surfaces and paint in a uniform color at east wall in the bathroom located at apt 8n, 9th story, 3rd apartment from west at north
Sep 2, 2026 · Apt 8N
Open — Nov sent out - BHazardous
Properly repair with similar material the broken or defective fire retardant material at north wall at public hall, 2nd story
Aug 28, 2026
Open — Nov sent out
Show 40 more ↓
- ANon-hazardous
Paint with light colored paint to the satisfaction of this department at north wall at public hall, 2nd story
Aug 28, 2026
Open — Nov sent out - CImmediately hazardous
Trace and repair the source and abate the visible mold condition... more than 30 square feet at ceiling, east, north, south, and west walls in the bathroom located at apt 1a, 2nd story, 1st apartment from east at south , section ''a-g'', at west
Aug 28, 2026 · Apt 1A
Open — Notice of issuance sent to tenant - BHazardous
Repair the leaky and/or defective faucets at bathtub in the bathroom located at apt 1a, 2nd story, 1st apartment from east at south , section ''a-g'', at west
Aug 28, 2026 · Apt 1A
Open — Nov sent out - BHazardous
Properly repair the source and abate the evidence of a water leak at ceiling and east wall in the bathroom located at apt 1a, 2nd story, 1st apartment from east at south , section ''a-g'', at west
Aug 28, 2026 · Apt 1A
Open — Nov sent out - BHazardous
Repair the broken or defective plastered surfaces and paint in a uniform color at ceiling and east wall in the bathroom located at apt 1a, 2nd story, 1st apartment from east at south , section ''a-g'', at west
Aug 28, 2026 · Apt 1A
Open — Nov sent out - BHazardous
Properly repair the source and abate the evidence of a water leak at ceiling in the 3rd room from east located at apt 1a, 2nd story, 1st apartment from east at south , section ''a-g'', at west
Aug 28, 2026 · Apt 1A
Open — Nov sent out - BHazardous
Repair the broken or defective plastered surfaces and paint in a uniform color at ceiling, east, and west walls in the 3rd room from east located at apt 1a, 2nd story, 1st apartment from east at south , section ''a-g'', at west
Aug 28, 2026 · Apt 1A
Open — Nov sent out - ANon-hazardous
Properly repair with similar material the broken or defective vinyl floor tile in the private hallway located at apt 1a, 2nd story, 1st apartment from east at south , section ''a-g'', at west
Aug 28, 2026 · Apt 1A
Open — Nov sent out - ANon-hazardous
Paint with light colored paint to the satisfaction of this department at all ceilings and all walls in the entire apartment located at apt 1a, 2nd story, 1st apartment from east at south , section ''a-g'', at west
Aug 28, 2026 · Apt 1A
Open — Nov sent out - BHazardous
Repair, replace or provide an approved and operational carbon monoxide detecting device, installed in accordance with applicable law and rules missing in the entire apartment located at apt 1a, 2nd story, 1st apartment from east at south , section ''a-g'', at west
Aug 28, 2026 · Apt 1A
Open — Nov sent out - BHazardous
Repair, replace or provide an approved and operational smoke detecting device, installed in accordance with department of buildings rules and regulations missing in the entire apartment located at apt 1a, 2nd story, 1st apartment from east at south , section ''a-g'', at west
Aug 28, 2026 · Apt 1A
Open — Nov sent out - BHazardous
Repair the broken or defective plastered surfaces and paint in a uniform color at ceiling and north amd east walls in the bathroom located at apt 18f, 18th story, 2nd apartment from south at west
Aug 22, 2026 · Apt 18F
Open — Nov sent out - BHazardous
Repair the leaky and/or defective faucets at bathtub in the bathroom located at apt 20j, 20th story, 5th apartment from south at west
Aug 5, 2026 · Apt 20J
Open — Nov sent out - CImmediately hazardous
Repair the broken or defective plastered surfaces and paint in a uniform color at ceiling in the bathroom located at apt 20j, 20th story, 5th apartment from south at west
Aug 5, 2026 · Apt 20J
Closed — Violation closed - BHazardous
Repair the broken or defective plastered surfaces and paint in a uniform color at south wall in the private hallway located at apt 7m, 7th story, 2nd apartment from east at south
Jul 27, 2026 · Apt 7M
Open — Invalid certification - BHazardous
Trace and repair the source and abate the visible mold condition... more than 10 sq. ft at west wall in the bathroom located at apt 7m, 7th story, 2nd apartment from east at south
Jul 27, 2026 · Apt 7M
Open — Notice of issuance sent to tenant - BHazardous
Repair the broken or defective plastered surfaces and paint in a uniform color at ceiling and south wall in the bathroom located at apt 7m, 7th story, 2nd apartment from east at south
Jul 27, 2026 · Apt 7M
Open — Invalid certification - CImmediately hazardous
Abate the infestation consisting of roaches in the entire apartment located at apt 1a, 2nd story, 1st apartment from east at south , section ''west''
Jul 24, 2026 · Apt 1A
Open — Notice of issuance sent to tenant - BHazardous
Repair, replace or provide an approved and operational carbon monoxide detecting device, installed in accordance with applicable law and rules missing in the entire apartment located at apt 1a, 2nd story, 1st apartment from east at south , section ''west''
Jul 24, 2026 · Apt 1A
Open — Civ14 mailed - BHazardous
Repair, replace or provide an approved and operational smoke detecting device, installed in accordance with department of buildings rules and regulations missing in the entire apartment located at apt 1a, 2nd story, 1st apartment from east at south , section ''west''
Jul 24, 2026 · Apt 1A
Open — Civ14 mailed - CImmediately hazardous
Trace and repair the source and abate the visible mold condition... more than 30 sq feet at all walls and ceiling in the bathroom located at apt 1a, 2nd story, 1st apartment from east at south , section ''west''
Jul 24, 2026 · Apt 1A
Open — Notice of issuance sent to tenant - BHazardous
Repair the leaky and/or defective water supply pipe cold water line under sink in the kitchen located at apt 1a, 2nd story, 1st apartment from east at south , section ''west''
Jul 24, 2026 · Apt 1A
Open — Civ14 mailed - BHazardous
Repair the leaky and/or defective faucets at bathtub in the bathroom located at apt 1a, 2nd story, 1st apartment from east at south , section ''west''
Jul 24, 2026 · Apt 1A
Open — Civ14 mailed - BHazardous
Repair, replace or provide an approved and operational smoke detecting device, installed in accordance with department of buildings rules and regulations defective in the entire apartment located at apt 8k, 8th story, 1st apartment from south at west
Jul 20, 2026 · Apt 8K
Open — Nov sent out - ANon-hazardous
Repair the broken or defective plastered surfaces and paint in a uniform color at ceiling and north wall in the 2nd room from north located at apt 8k, 8th story, 1st apartment from south at west
Jul 20, 2026 · Apt 8K
Open — Nov sent out - ANon-hazardous
Repair the broken or defective plastered surfaces and paint in a uniform color at ceiling in the 3rd bathroom from east located at apt 8k, 8th story, 1st apartment from south at west
Jul 20, 2026 · Apt 8K
Open — Nov sent out - BHazardous
Repair the flushing apparatus and maintain same so as to flush effectively the water closet .. in the 3rd bathroom from east located at apt 8k, 8th story, 1st apartment from south at west
Jul 20, 2026 · Apt 8K
Open — Nov sent out - BHazardous
Repair, replace or provide an approved and operational carbon monoxide detecting device, installed in accordance with applicable law and rules defective in the entire apartment located at apt 8k, 8th story, 1st apartment from south at west
Jul 20, 2026 · Apt 8K
Open — Nov sent out - BHazardous
Repair the broken or defective plastered surfaces and paint in a uniform color at south wall in the bathroom located at apt 8k, 8th story, 1st apartment from south at west
Jul 20, 2026 · Apt 8K
Open — Nov sent out - BHazardous
Properly repair the source and abate the evidence of a water leak over ceiling at public hall, 1st story
Jul 18, 2026
Open — Nov sent out - CImmediately hazardous
Provide hot water at all hot water fixtures in the entire apartment located at apt 19e, 19th story, 1st apartment from south at west
Jul 18, 2026 · Apt 19E
Open — Nov sent out - BHazardous
Properly repair with similar material the broken or defective fire retardant material at ceiling at public hall, 1st story
Jul 18, 2026
Open — Nov sent out - CImmediately hazardous
Provide ready access to buildings heating system door lock at boiler room
Jul 18, 2026
Open — Nov sent out - BHazardous
Repair the broken or defective plastered surfaces and paint in a uniform color at ceiling and all walls in the bathroom located at apt apt18f, 18th story, 2nd apartment from south at west
Jul 18, 2026 · Apt APT18F
Open — Nov sent out - BHazardous
Properly repair the source and abate the evidence of a water leak at ceiling and all walls in the bathroom located at apt apt18f, 18th story, 2nd apartment from south at west
Jul 18, 2026 · Apt APT18F
Open — Nov sent out - BHazardous
Repair the broken or defective plastered surfaces and paint in a uniform color at north wall in the 1st room from north located at apt 5k, 5th story, 1st apartment from south at west
Jun 20, 2026 · Apt 5K
Open — Nov sent out - BHazardous
Repair the broken or defective plastered surfaces and paint in a uniform color at ceiling in the 1st room from north located at apt 5k, 5th story, 1st apartment from south at west
Jun 20, 2026 · Apt 5K
Open — Nov sent out - CImmediately hazardous
Provide hot water at all hot water fixtures in the entire apartment located at apt 19e, 19th story, 1st apartment from south at west
Jun 18, 2026 · Apt 19E
Closed — Violation closed - CImmediately hazardous
Provide hot water at all hot water fixtures in the entire apartment located at apt 11l, 11th story, 1st apartment from north at east
Jun 18, 2026 · Apt 11L
Closed — Violation closed - CImmediately hazardous
Provide hot water at all hot water fixtures in the entire apartment located at apt 24h, 23rd story, 4th apartment from south at west
Jun 16, 2026 · Apt 24H
Closed — Violation closed
DOB building violations · 286
- Construction other optional
Owner responsibility:the podium structure and supporting columns are in a state of disrepair.remedy:the owner shall complete the required permanent repairs under permit by 12/21/28
Aug 14, 2026
Dob violation - active - Construction other optional
Owner responsibility:the podium structure and supportin columns are in a state of disrepair.remedy:the owner shall complete the required permanent repairs under permit by 12/31/28
Aug 14, 2026
Dob violation - active - Construction other optional
Owner responsibility:the podium structure and supporting columns are in a state of disrepair.remedy:the owner shall complete the required permanent repairs under permit by 12/31/28
Aug 14, 2026
Dob violation - active - Construction other optional
Owner responsibility:the podium structure and supporting columns are in a state of disrepair.remedy:the owner shall complete the required permanent repairs under permit by 12/31/28
Aug 14, 2026
Dob violation - active - Construction other optional
A precast plank underside fell at lot 170; others may fail; structural integrity is compromised remedy: bldg owner to retain a nys pe to perform hands on inspection of precast planks and submit s/s engr's report by 8/28/25
Jul 29, 2025
Dob violation - dismissed - Construction other optional
Vacate 125'x120' area btw 777 & 779 cve except egress pathways 290'x90 'btw 775 & 777 cve.due to substantial spalling of pre cast concrete el emnts posiible stability issues.vacate approx 125'x120'area between 77 7 & 779 cve with exception of 10'.0"wide egress pathway along the sout h elev of 779 cve.also 290'x90' area of the plaza bw 775 & 777 cve
Jul 16, 2025
Dob violation - active - Construction other optional
Partial vacate order.entire parking garage at cellar level.the parking garage exhibits substantial deteriorating materials,multiple large sec tions of removed planks and concrete slabs with significant section of spalled concrete rusted reinforcements,cracked and spalling concrete c olumns.concere in danger of falling.remedy:vacate entire parking garag
Jul 15, 2025
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2023 external low pressure inspection
Sep 23, 2024
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2023 external low pressure inspection
Sep 23, 2024
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2023 external low pressure inspection
Sep 23, 2024
Dob violation - active
Show 40 more ↓
- Low pressure boiler boiler required
Violation issued-failure to file 2023 external low pressure inspection
Sep 23, 2024
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2023 external low pressure inspection
Sep 23, 2024
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2023 external low pressure inspection
Sep 23, 2024
Dob violation - active - Construction other optional
Emergency work order:an active parking structure consisting 2 levels rooftop&basement with vehicles occupied. unsafe notication #unps-x0038 09-1c-001 dated 7/29/24. safety not installed in place demolishing of concrete slab.remedy: owner to retain nys registered design prof to evaluate, superv direct all work to [email protected]
Aug 20, 2024
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2021 external low pressure inspection
Jun 30, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2021 external low pressure inspection
Jun 30, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2021 external low pressure inspection
Jun 30, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2021 external low pressure inspection
Jun 30, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2021 external low pressure inspection
Jun 30, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2021 external low pressure inspection
Jun 30, 2023
Dob violation - active - Construction other optional
Currently, existing podium lvl structure@773 concourse villgeast, bx, has temp shoring installd for structural stability remedy: ownr2submt strctrl stablty rpt,prepard,signd&seald by nys pe for podium struct every3months'til repaird,submt rpt 1 by6/30/23
Jun 12, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2022 external low pressure inspection
Apr 25, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2022 external low pressure inspection
Apr 25, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2022 external low pressure inspection
Apr 25, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2022 external low pressure inspection
Apr 25, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2022 external low pressure inspection
Apr 25, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2022 external low pressure inspection
Apr 25, 2023
Dob violation - active - Failure to post energy grade/score none
Failure to display energy efficiency score and energy efficiency grade as per adcode sec. 28-309.12.3
Dec 1, 2022
Dob violation - active - Construction other optional
Emergency work order-during dob site inspection observed numerous reinforced concrete slabs, beams and columns supporting the east plaza podium level located at tax lot 170 were structually compromised reinforcement of the structure are extensively corroded and exposed remedy:submut s/s eng'r report of shoring work w/associated photos
Aug 11, 2022
Dob violation - dismissed - Construction other optional
Owner responsibilities-observed during a limited visual inspection of the podium structure on june 21 2022 there a numerous reinforced concrete beams/columns with missing/spalled concrete. the deficiencies affect the load carrying and safety of the public. remedy: immed hire a nys lic struct en'r to eval the entire structure
Jun 22, 2022
Dob violation - active - Failure to benchmark none
Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4
Jun 2, 2022
Dob violation - dismissed - Hazardous condition (facade) facade required
Cycle 9c unsafe report filed
Feb 21, 2022
Dob violation - active - Hazardous condition (facade) facade required
Cycle 9c unsafe report filed
Feb 21, 2022
Dob violation - active - Hazardous condition (facade) facade required
Cycle 9c unsafe report filed
Feb 21, 2022
Dob violation - active - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Oct 27, 2021
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Sep 15, 2021
Dob violation - active - Failure to benchmark none
Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4
Aug 2, 2021
Dob violation - dismissed - Construction other optional
Failure to comply. on 01/08/2021 commissioner's order 265855 (010821cllfa02jj)was issued to wner to retain a nys lic prof to eval & inspect all balcony slabs, provide eng'r report & repair plans/ proposals to dob by 2/25/21. as of 6/29/21 owner has not complied with immed cure order. remedy: immed comply w/code and commissioner's order
Jun 29, 2021
Dob violation - active - Construction other optional
Failure to comply. on 01/13/2021 commissioner's order 349630 (011321cllfa04rf)was issued to owner to retain a nys lic prof to eval and inspect 100% of all balcony slabs. provide eng'r report, repair plans and proposals to dob by 02/25/2021. as of 6/29/21 owner has not complied. remedy: immed comply with code and commissioner's order
Jun 29, 2021
Dob violation - active - Construction other optional
Failure to comply. on 01/08/2021 commissioner's order 265857 (010821cllfa04jj)was issued to owner to have all balcony slabs 100% inspected by a nys lic prof. as of 06/06/2021 owner has not complied with immed cure order to have all balcony slabs inspected & provide eng'r report & repair dwgs. immed comply w/code & commissioner's order
Jun 8, 2021
Dob violation - active - Failure to benchmark none
Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4
Jun 2, 2021
Dob violation - dismissed - Construction other optional
Ftm exterior building facade and appurtenances. exposures 1,2,3, north and south elevations display approx 25% of blacony concrete corners with water penetration, spalling and exp 3 south east bldg, 4th and 6th fl broken concrete corners. remedy: maintain exterior facade. take safety measures. partial vacate ordered for all balconies
Jan 13, 2021
Dob violation - active - Construction other optional
Balcony concrete corners on exposures 1 and 3, north and south elevations display water penetration, spalling and some broken/ cracked concrete. remedy: owner to retain a nys lic professional to evaluate and inspect 100% of all balcony slabs. provide engineer's report,repair plans and proposals to dept facade unit by 2/25/2021
Jan 13, 2021
Dob violation - active - Construction other optional
Balcony concrete corners of exposures 1 and 3, north and south elevations display water penetration, spalling, and some broken/ cracked concrete. remedy: owner to retain a nys lic professional to evaluate and inspect 100% of all balcony slabs. provide engineer's report, repair plans and proposals to dept facade unit by 2/25/2021
Jan 12, 2021
Dob violation - dismissed - Construction other optional
Ftm exterior bldg facade and appurtenances. exp 1 and 3, east and west exposures display aprox 40% of balconies with various defects, water penetration, cracks in slabs. broken glass and dislodged, appurtenance and masonry defects found on roof and chimney. remedy: maintain exterior facade, take safety measures
Jan 8, 2021
Dob violation - active - Construction other optional
Balcony concrete corners on exposures 2 and 3, east and west elevations display water penetration, spalling, cracks and broken concrete. remedy: owner to retain a nys lic professional to evaluate and inspect 100% of all balcony slabs. provide eng'r report and repair plans/proposals to dept facade unit by 2/25/2021. file and permit work
Jan 8, 2021
Dob violation - active - Construction other optional
Ftm exterior building facade and appurtenances. exp 1 and 3, north and south exposures display aprrox 45% of blaconies with water penetration cracks, spalls and other defects throughout the structure. broken conrete corners exp 1 at 9th, 18, 19, 22, 24, 21 and others. remedy: maintain exterior facade. take safety measures
Jan 8, 2021
Dob violation - active - Construction other optional
Concrete balconies at exposures 1 and 3, north and south exposures display water penetration, spalling and broken concrete. remedy: owner to retain a nys lic professional to evaluate and inspect 100% of all blacony slabs. provide eng'r report and repair plans as well as proposals to dept facade unit by 2/25/2021. file and permit all work
Jan 8, 2021
Dob violation - active - Hazardous condition (facade) facade required
Fisphaz-hazardous condition (facade) facade required
Sep 8, 2020
Dob violation - active - Hazardous condition (facade) facade required
Fisphaz-hazardous condition (facade) facade required
Sep 2, 2020
Dob violation - active
ECB violations · 106
- Class - 2
Observed a federal boiler model plw 529, serial #8496 with a defective butterfly gas valve, boiler inoperative. correct all violating conditions and submit a certificate of correction.
Feb 10, 2026 · Penalty $1,280
Active - Class - 2
Found federal brickset boiler inoperative. correct violating condition and submit a certificate of correction.
Feb 10, 2026 · Penalty $1,280
Active - Class - 1
Failure to safeguard parking structure(ftsg-ps).as noted at time of inspection observed warranted crack concrete present planks.also some spalling of column and present planks.also observed fallen and dislodged
Jul 15, 2025 · Penalty $25,000
Active - Class - 1
Failure to maintain parking structure in safe condition.as noted at time of inspection on an occupied parking structure consisting of 1 level below the building and courtyard observed crack concrete at the col
Jul 15, 2025 · Penalty $12,500
Active - Class - 2
Found federal boiler s/n-15218 active with defects. boiler room sump pump defective with standing water in boiler room. steam isolation valve leaking with evidence of corrision. correct all violating conditions
Mar 31, 2025 · Penalty $6,250
Active - Class - 2
Failure to comply with commissioner's order contained in summons #35682291h issued on 04/16/2024, and failure to file a certificate of correction pursuant to 28.201.1 and 1 rcny 102-01(d)(2). an acceptable cert
Feb 11, 2025 · Penalty $3,125
Resolve - Class - 1
Unlawful acts.failure to comply with commissioner's order.noted:violation#011321cllfa04rf dated january 13,2021 states balconies on exposure1 & 3(north & south elevation)display spalling,and cracked concrete an
Apr 23, 2024
Resolve - Class - 1
Unlawful acts.failure to comply with commissioner's order.noted:violation#010821cllfa02jj dated january 8,2021 states balconies on exposure 1 & 3(east and west elevations)display spalling cracked concrete and w
Apr 23, 2024
Resolve - Class - 2
Failure to mainatin exterior wall facade and appurtenances. note observed at exposure 1 south elevation spall at west balcony slab upper floors crack at 15 floor. open joint 1st floor. deflect at east balcony.
Apr 16, 2024 · Penalty $1,250
Active - Class - 1
Unlawful act. failure to comply with an order of the commissioner's: owner/respondent failed to comply with previous violation #010821cllfa04jj issued on 01/08/2021. to evaluate and inspect 100% of all balcony
Apr 16, 2024
Resolve
Show 40 more ↓
- Class - 2
Observed in basement water leaking from boiler, repair and/or replace
Sep 12, 2023 · Penalty $3,125
Active - Class - 2
Blr 05 tubes leaking-guards missing from oil pump pulleys blr. 02, 03, 04 and pump station. oil stored blr. 03. press switch covers missing-cond. ret. pump, vac pump make-up tank pumps leak-no elect cover for b
Mar 4, 2022 · Penalty $3,125
Active - Class - 2
Failure to file acceptable amended cycle 7c & 8c report indicating correction of unsafe conditions described in initial facades report required by 28-302.5 for control#807539. remedy: file acceptable report.
Oct 8, 2021 · Penalty $6,250
Active - Class - 2
Failure to file acceptable amended cycle 8c report indicating correction of unsafe conditions described in initial facades report required by 28-302.5 for control#807541. remedy: file acceptable report.
Oct 8, 2021 · Penalty $6,250
Active - Class - 2
Failure to file acceptable amended cycle 7c,8c&9c report indicating correction of unsafe conditions described in initial facades report required by 28-302.5 for control#907540. remedy: file acceptable report.
Oct 8, 2021 · Penalty $6,250
Active - Class - 2
Failure to comply w/commissioner's order contained in summons/v35507702p issued6/26/21 &to file c/c pursuant to28-201.1&1rcny102-01.comply w/commissioner's order &/or file c/c.
Sep 23, 2021 · Penalty $5,000
Resolve - Class - 2
Failure to comply with the commissioners order contained in summons.violation #35507702p issued on 06-26-21 an dto file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01.comply with commissioner
Aug 6, 2021 · Penalty $1,280
Resolve - Class - 1
No door lock monitoring installed in this controller as per 3.10.12 of appendix k3 of the 2014 nycbc. remedy; install dlm and perform and file test with nycdob.
Jul 22, 2021 · Penalty $1,250
Resolve - Class - 1
Failure to maintain concrete parking garage spalled in various places.exposed rusted rebar.netting in place.maintain in codecompliant manner.
Jun 26, 2021 · Penalty $6,250
Active - Class - 2
Failure to maintain building exterior walls and appurtenances. at timeof inspection,i observed step-cracks at the top of masonry chimney,mortar falling out of parapet wall and broken windows on bulkhead,detache
Jan 8, 2021 · Penalty $6,250
Active - Class - 1
Class 1. no door lock monitoring installed in this controller as mandated by 3.10.12 of appendix k3 of the 2014 nycbc. remedy; file application, install dlm and perform and file test with nycdob,
Apr 2, 2020 · Penalty $1,250
Resolve - Class - 2
Failure to submit an acceptable required cycle 8c report of critical examination documenting condition of exterior wall and appurtenances required by 28-302.4 for control#807540.rem:submit acceptable required t
Feb 13, 2020 · Penalty $1,250
Active - Class - 2
Failure to submit an acceptable required cycle 8c report of critical examination documenting condition of exterior wall and appurtenances required by 28-302.4 for control#807541.rem:submit acceptable required t
Feb 13, 2020 · Penalty $1,250
Active - Class - 2
Failure to submit an acceptable required cycle 8c report of critical examination documenting condition of exterior wall and appurtenances required by 28-302.4 for control#807539.rem:submit acceptable required t
Feb 13, 2020 · Penalty $1,250
Resolve - Class - 2
Failure to comply w/the comm's order contained in summons/vio#38267208z issued on 01-03-19 & to file a c of c pursuant to 28-201.1 & 1rcny 102-01(d)(2). an acceptable certificate has not been filed despite the
Nov 13, 2019 · Penalty $1,250
Resolve - Class - 2
39p07;100m078;80b07;68b07;68m07. 39-provide access to car top; 100- provide door access ((....key hole) at all landing; 80-runby signage insuff; 68-update mainta log; 68-provide mcp
Jul 16, 2019
Resolve - Class - 2
25m07,26b11,26d06,40o02,59d06,52u07,7d06,68b07,02b10,80m07. 25-providefire signaged; 26-repalce sw with a manual reset type; 26-provide chain on hinges; 40-clean machine room; 59-secure brake missing cover; 52-
May 29, 2019 · Penalty $625
Active - Class - 1
97x10 restore to service so full inspection can be done by this dept
Feb 22, 2019 · Penalty $1,250
Resolve - Class - 1
Failure to maintain building in code compliant manner- noted:building support structure @basement lvl in disrepair (exposed and rusted rebars) on beams and colums)rem:repair or place forthwith.
Feb 19, 2019 · Penalty $625
Active - Class - 2
29-r-05=work without permit.part number(29)(1)door operator and part was installed without permit being obtained and application being filed remedy.file application and obtain permit for work and schedule test
Jan 3, 2019 · Penalty $1,250
Resolve - Class - 2
67.x.10,39.o.02,70.o.02,68.b.07=(67,x,10)phone in car is inoperative,repair(39,o,02)car top dirty clean(70,o,02)pit dirty clean (68,b,07)maintenances insufficient provide.(40,o,02)motor room dirty clean
Jan 3, 2019 · Penalty $625
Resolve - Class - 1
False statements shall be unlawful for any person to knowingly (negligently)make or allow to be made a material fake statements in any certificate of professional, form, signed statements, application reports
Dec 13, 2018
Resolve - Class - 1
97x17 failure to maintain building equipment elevator as per bc 2001.2and 27-987 elevator in building upon inspection the device is found out of service creating a hazardous condition per 1rcny11-02 the elevato
Dec 4, 2018 · Penalty $625
Resolve - Class - 1
97x17-rmdy: upon inspection the device is found to be out of service. creating a hazardous condition as per 1rcny 11-02-rmdy: restore to service immediately and notify ncdob the device has been returned to ser
Dec 4, 2018 · Penalty $625
Resolve - Class - 1
97x10 elevator out of service.upon inspection elevator device #2-3898is found out of service creting a hazardous condition as per 1rcny 11 -02. rmdy: repair back to service immediately. and notify nycdob the d
Mar 20, 2017 · Penalty $250
Resolve - Class - 2
97r## elevator use for transportation of construction personnel,toolsand materials this is a work w/o permit,file and appicaiton as pe rapendix k section 5.10 elevator use for construction rmdy: file applica
Mar 20, 2017
Resolve - Class - 1
Partial swo issued for supported scaffold pursuant 28-201.2 & posted on premises. supported scaffold over 40 feet installed w/o permit. noted: at time of inspection supported scaffold approx 45'feet in height
Mar 17, 2017 · Penalty $1,200
Resolve - Class - 2
Partial swo issued for supported scaffold pursuant 28-207.2 & posted on premises. work does not conform to approved plans. noted: at time of inspection supported scaffold that installed on the roof level at the
Mar 17, 2017 · Penalty $250
Resolve - Class - 2
2x10,59b6,57bb7,70o2,40o2/(2x10)phone inoperative repair(59b6)machine brake no lock nuts,properly secure(57bb7)provide fire extinguisher;(70o2)pit dirty clean;(40o2)motor room dirty clean.
Jan 11, 2017 · Penalty $500
Resolve - Class - 2
5j1,78b14,5x10/(5j1)car door misaligned,adjust(78b14)car and counter weight tension weight,insufficient,shorten;(2x10)phone inoperative repair.
Jan 11, 2017 · Penalty $500
Resolve - Class - 2
2x10,40o2,60b7/(2x10)phone inoperative,repair;(40o2)machine room dirty,clean;(60b7)lighting machine space,provide.
Jan 11, 2017 · Penalty $500
Resolve - Class - 2
5x10,2x10,70o2/(5x10)door restrictor,inoperative,repair;(2x10)phone inoperative,repair;(70o2)
Jan 11, 2017 · Penalty $500
Resolve - Class - 2
2x10,63j1,70o2/2-x-10-phone-inoperative-repair;63-j-1-motor brushes-misaligned-adjust;70-o-2-pit dirty;clean.
Jan 11, 2017 · Penalty $500
Resolve - Class - 2
2x10,63j1,57m7/(2x10)phone inoperative repair;(63j1)motor brushes misaligned-adjust;57m7
Jan 11, 2017 · Penalty $500
Resolve - Class - 2
Failure to file acceptable amended report indicating correction of unsafe conditions described in initial local law 11/98 report. agg2 history of noncompliance on 36024123k, 36027701r. rem: file acceptable amen
Nov 7, 2016 · Penalty $4,000
Active - Class - 2
Failure to file acceptable amended report indicating correction of unsafe conditions described in initial local law 11/98 report. agg2 history of noncompliance on 36024125y, 36027702z. rem: file acceptable amen
Nov 7, 2016 · Penalty $4,000
Resolve - Class - 2
Failure to file acceptable amended report indicating correction of unsafe conditions described in initial local law 11/98 report. agg2 history of noncompliance on 36024128j, 36027736r. rem: file acceptable amen
Nov 7, 2016 · Penalty $4,000
Active - Class - 1
97x10. upon insp the device is found to be out of service. rem: restore to service immediately.
Sep 26, 2016 · Penalty $5,000
Active - Class - 2
Failure to file an amended seventh round report acceptable to this dept indicating correction of unsafe condition described in intial local law 11/98 report.rem:file an amended report following remedial repairs
Jul 7, 2016 · Penalty $4,000
Active - Class - 2
Failure to file an amended seventh round report acceptable to this dept indicating correction of unsafe condition described in intial local law 11/98 report.rem:file an amended report following remedial repairs
Jul 7, 2016 · Penalty $2,000
Resolve
Complaints
- Water leak
Damp spot
Oct 12, 2026 · Apt 2M
Open - Water leak
Slow leak
Oct 12, 2026 · Apt 2M
Open - Heat/hot water
Entire building
Oct 6, 2026 · Apt 15M
Close - Heat/hot water
Entire building
Oct 3, 2026 · Apt 19E
Close - General
Bell/buzzer/intercom
Oct 1, 2026 · Apt 7E
Close - Elevator
Maintenance
Oct 1, 2026 · Apt 7E
Close - Unsanitary condition
Mold
Sep 25, 2026 · Apt 18D
Close - Plumbing
Water supply
Sep 25, 2026 · Apt 18D
Close - Paint/plaster
Wall
Sep 1, 2026 · Apt 19F
Close - Water leak
Damp spot
Sep 1, 2026 · Apt 19F
Close
Show 40 more ↓
- Unsanitary condition
Mold
Sep 1, 2026 · Apt 19F
Close - Paint/plaster
Wall
Aug 31, 2026 · Apt 8N
Close - Water leak
Heavy flow
Aug 31, 2026 · Apt 8N
Close - Water leak
Damp spot
Aug 17, 2026 · Apt 18F
Close - Plumbing
Basin/sink
Aug 10, 2026 · Apt 1A
Close - Unsanitary condition
Mold
Aug 10, 2026 · Apt 1A
Close - Plumbing
Bathtub/shower
Aug 10, 2026 · Apt 1A
Close - Water leak
Damp spot
Aug 1, 2026 · Apt 18F
Close - Unsanitary condition
Mold
Aug 1, 2026 · Apt 18F
Close - General
Bell/buzzer/intercom
Jul 27, 2026 · Apt BLDG
Close - Electric
Power outage
Jul 24, 2026 · Apt 1A
Close - Unsanitary condition
Mold
Jul 21, 2026 · Apt 7M
Close - Unsanitary condition
Mold
Jul 20, 2026 · Apt 1A
Close - Plumbing
Basin/sink
Jul 20, 2026 · Apt 1A
Close - Water leak
Slow leak
Jul 20, 2026 · Apt 1A
Close - Water leak
Heavy flow
Jul 18, 2026 · Apt 20J
Close - Heat/hot water
Entire building
Jul 18, 2026 · Apt 19E
Close - Electric
Lighting
Jul 18, 2026 · Apt 20J
Close - Water leak
Damp spot
Jul 17, 2026 · Apt APT18F
Close - Water leak
Slow leak
Jul 16, 2026 · Apt 18F
Close - Water leak
Damp spot
Jul 11, 2026 · Apt APT18F
Close - Water leak
Slow leak
Jul 11, 2026 · Apt APT18F
Close - Water leak
Damp spot
Jul 9, 2026 · Apt APT18F
Close - Paint/plaster
Ceiling
Jul 8, 2026 · Apt 8K
Close - Water leak
Slow leak
Jul 8, 2026 · Apt 8K
Close - Unsanitary condition
Mold
Jul 4, 2026 · Apt 7M
Close - Heat/hot water
Entire building
Jun 21, 2026 · Apt 9D
Close - Heat/hot water
Entire building
Jun 19, 2026 · Apt 19E
Close - Heat/hot water
Entire building
Jun 19, 2026 · Apt BLDG
Close - Heat/hot water
Entire building
Jun 19, 2026 · Apt 1E
Close - Heat/hot water
Entire building
Jun 19, 2026 · Apt 11G
Close - Heat/hot water
Entire building
Jun 18, 2026 · Apt 8E
Close - Heat/hot water
Entire building
Jun 18, 2026 · Apt BLDG
Close - Heat/hot water
Entire building
Jun 18, 2026 · Apt BLDG
Close - Heat/hot water
Entire building
Jun 18, 2026 · Apt 19E
Close - Heat/hot water
Entire building
Jun 18, 2026 · Apt BLDG
Close - Heat/hot water
Entire building
Jun 18, 2026 · Apt PAST2D
Close - Heat/hot water
Entire building
Jun 18, 2026 · Apt 18F
Close - Heat/hot water
Entire building
Jun 17, 2026 · Apt 19E
Close - Heat/hot water
Entire building
Jun 17, 2026 · Apt 24H
Close
Sales history
No recorded sales in our data
Building details
- Building type
- Elevator apartment building (D4)
- Year built
- 1964
- Floors
- 25
- Residential units
- 936
- Building area
- 876,500 ft²
- Lot area
- 163,680 ft²
- Zoning
- R8
- Community board
- 204
- Council district
- 16
- Block / lot
- 2443 / 170
- Assessed value
- $22,198,050
- Landmark / historic district
- No
HPD registration #221589, last renewed Jul 25, 2025.
Questions about 773 Concourse Village E
Who owns 773 Concourse Village E?
The owner of record in NYC Department of City Planning PLUTO data is Concourse Village INC.
Does 773 Concourse Village E have violations?
Yes. NYC HPD has recorded 837 housing violations at this property.
Is 773 Concourse Village E rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 773 Concourse Village E built?
City records list 1964 as the year it was built.
How many apartments are in 773 Concourse Village E?
It has 936 residential units and 937 units in total.