1763 Amsterdam Avenue is a hotel built in 2025 in Manhattan, 10031. The owner of record is Empire Development Fund, LLC. HPD has no housing violations on record for this property.
- HPD violations
- 0
- DOB violations
- 24
- ECB violations
- 63
- HPD complaints
- 1
What to know
No open immediately-hazardous violations among recent records.
HPD has not cited this building.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 0
No HPD violations on record
DOB building violations · 24
- Low pressure boiler boiler required
Violation issued-failure to file 2024 external low pressure inspection
Nov 14, 2025
Dob violation - active - Construction other optional
Vio25-50503
Jun 23, 2025
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2023 external low pressure inspection
Sep 23, 2024
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2020 external low pressure inspection
Jun 30, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2021 external low pressure inspection
Jun 30, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2018 external low pressure inspection
Jun 20, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2019 external low pressure inspection
Jun 20, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2022 external low pressure inspection
Apr 25, 2023
Dob violation - active - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Feb 17, 2021
Dob violation - dismissed - Immediate emergency anythingoptional
Repair approximately 125 linear feet of construction fence along exposure 1 to safeguard the public and property
Nov 17, 2020
Dob violation - dismissed
Show 14 more ↓
- Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Sep 2, 2020
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2017 inspection report
Nov 8, 2019
Dob violation - active - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jun 27, 2018
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jun 27, 2018
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jun 27, 2018
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jun 27, 2018
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jun 27, 2018
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2016 inspection report
Apr 6, 2018
Dob violation - active - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2015 inspection report
Feb 24, 2017
Dob violation - active - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2014 inspection report
Oct 1, 2015
Dob violation - active - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jun 19, 2013
Dob violation - dismissed - Emergency none
Egncy-emergency none
Apr 2, 2013
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Mar 26, 2002
Dob violation - dismissed - Construction other optional
C-construction other optional
Feb 5, 1993
Dob violation - dismissed
ECB violations · 63
- Class - 2
3314.4.4.9: obs active 8 story nb with exterior temporary equip. @ expo 1. outrigger suspended scaff. assembly installed @ expo 3. upon review of the suspended scaffold motors, one motor was missing its identif
Aug 10, 2026 · Penalty $2,500
Active - Class - 1
Obs suspended scaffold installation not conforming to approved cd plans. suspension lines installed with fiber rope in lieu of required 3/8" wire rope with fist grip clamps.tieback/outrigger assembly&rigging co
May 20, 2026 · Penalty $2,530
Active - Class - 1
3314.10.11 at time of inspection, suspended scaffold at exposure #1 observed not in use and not lowered to ground or deck as required. scaffold left parked at expo:#2 5th fl roof deck. no details provided to de
May 20, 2026 · Penalty $5,030
Active - Class - 1
3314.15.2 observed suspended scaffold outriggers, ropes and rigging in place and readily available for use at 5th floor roof, exposure 2. stirrups installed approximately 3 feet and 2.5 feet from platform ends,
May 20, 2026 · Penalty $5,030
Active - Class - 1
3314.10 observed outrigger beam installed not perpendicular to wall and not centered on pipe frame support. beam shall be installed with all bearing supports perpendicular to beam centerline and maintained in v
May 20, 2026 · Penalty $5,030
Active - Class - 1
3314.6.2 failure to protect life lines from sharp edges and abrasion causing ahazardous condition for personnel/workers and public ,life lines in use were not protected of contact that includes roof top and bu
May 20, 2026 · Penalty $5,030
Active - Class - 2
No records or dob notifications on file for installation of suspended scaffold.upon further review of dob now/bis,no permits,filings,or documentation were found verifying authorized installation.without require
May 20, 2026
Resolve - Class - 1
Failure to maintain adequate housekeeping per section requirement.obs inadequate housekeeping throughout roof at exposures 2 & 4 at work areas.loose ropes,debris,panks,rubble,bucket and miscellaneous materials
May 20, 2026
Resolve - Class - 1
Super failed to adequately supervise site operations to maintain a safe construction site. hazardous conditions obs including scaf planks not secured, loose netting @scaffold, missing guardrails,elect panels un
Mar 13, 2026 · Penalty $10,000
Resolve - Class - 1
Upon review of approved plans & filed amendment, sequence drawings eq-008 & eq-005 limit work to 1 working level @a time with a max of 10 levels. however, at expos #1/3 supported scaffold observed fully planked
Mar 13, 2026
Resolve
Show 40 more ↓
- Class - 1
At time of inspection, severe inadequate housekeeping was obs @ active construction site. construction debris, wood, metal studs, styrofoam, broken materials & garbage bags were accumulated throughout the work
Mar 13, 2026
Resolve - Class - 1
Unapproved/unsafe/unsuitable electrical equipment, apparatus, materials, devices, appliances or wiring in use. note:at time of inspection observed unsuitable, electrical conditions creating a potential electric
Mar 13, 2026
Resolve - Class - 2
At time of inspection of an 8-story building under construction, uncapped vertical reinforcing steel bars were observed at the 1st and 2nd floor working decks. exposed rebars lacked required protective caps or
Mar 13, 2026
Resolve - Class - 2
At time of inspection of an 8-story building under construction, 1 worker was observed performing work on a supported scaffold without a required scaffold user certificate. the foreman/& worker were unable to p
Mar 13, 2026
Resolve - Class - 1
At time of inspection, supported scaffold observed erected and in use at exposures #1 and #3 without required guardrail system. no top rails, mid-rails, toe boards, or end gates provided. scaffold planks were n
Mar 13, 2026
Resolve - Class - 2
At time of inspection, electrical cables were observed loosely draped across structural beams without proper strain relief or conduit protection, creating electrical hazards. debris and construction materials o
Mar 13, 2026
Resolve - Class - 1
At time of inspection, multiple propane/fuel gas cylinders were observed improperly stored in the cellar in a confined area. cylinders were stored in bulk quantities, some corroded and partially submerged in st
Mar 13, 2026
Resolve - Class - 2
"at the time of inspection of a proposed 8-story new building, i observed supported scaffolding with improperly installed and loose vertical netting. this condition creates an immediate hazard of flying debris,
Feb 5, 2026
Resolve - Class - 1
"at the time of inspection, i observed the standpipe in readiness only up to the 7th floor. stop all work on the 7th floor and above until the main standpipe is extended and maintained in readiness at 75 feet a
Feb 5, 2026
Resolve - Class - 1
"at the time of inspection of an 8-story new building, i observed inadequate housekeeping throughout the entire site. this condition creates an immediate hazard, leading to slip, trip, and fall risks. maintain
Feb 5, 2026
Resolve - Class - 2
At time of inspection, inadequate roof protection was observed for the adjacent building. no roof protection was installed along the parapet wall on exp 1 of adjacent property( 1773 amsterdam ave). stop all ext
Dec 26, 2025
Resolve - Class - 2
At time of inspection, a c-hook suspended scaffold was observed installed on exp 2 without prior notification to the department of buildings. failure to notify d.o.b before the installation of c hook system is
Dec 26, 2025 · Penalty $2,500
Resolve - Class - 2
At time of inspection, a suspended scaffold was observed on site without the required documentation. no design drawings were available on site, and no pre- inspection report was provided for installed suspended
Dec 26, 2025 · Penalty $1,250
Resolve - Class - 2
Respondent use crane to hoist materials on jobsite knowing that none of his riggers possessed any rigging certifications; bc 3316.9.2, comply with code; obtain rigging certification from an approved provider
Sep 26, 2025
Resolve - Class - 2
Respondent permitted crane to be used to hoist materials knowing that none of the riggers possessed any rigging certification; bc 3316.9.2, comply with code; obtain rigging cert from an approved providr
Sep 26, 2025
Resolve - Class - 1
Respondent permitted yanchatipan pilco edison, fernando to operate a knuckle boom crane lic plate #15736sr to hoist materials to the top of a 5 story building. knowing he does not possess proper licensing., obt
Sep 3, 2025 · Penalty $5,000
Resolve - Class - 1
Respondent used yanchatipan pilco edison, fernando to operate a knuckle boom crane lic plate #15736sr to hoist materials to the top of a 5 story building. knowing he does not possess proper licensing., obtain l
Sep 3, 2025 · Penalty $5,000
Resolve - Class - 1
An existing stop work order on exposure 4, order # op-71-25-02675 dated on 2025-6-23 when the building was on ground floor level. at the visit time noted that the building at 3rd floor level at the same exposur
Jul 28, 2025 · Penalty $10,000
Resolve - Class - 1
Respondent was allowed construction operation were led to damage windows on the adjacent buildings at exposure one and four, the masons and iron rebar workers were performing work while some cement fall on wind
Jul 28, 2025 · Penalty $5,000
Resolve - Class - 1
Upon reviewing site safety plan, we found that the site condition wasn't reflecting the plan as it was missing trailer and storage area in street, fence gates in different location and missing fence at exposure
Jun 23, 2025 · Penalty $2,500
Resolve - Class - 1
Failure to build and maintain pipe scaffold as per code 3314.1, creating immediate hazards. scaffold missing guard rails, mud sills, toe board and included cracked planks, while been used to erect concrete maso
Jun 23, 2025 · Penalty $5,000
Resolve - Class - 1
Respondent failed to maintain safe operation. observed no overhead protection at exposure 2and 4. no protection for adjacent yard spaces materials fell, creating immediate hazardous people access the areas in
Jun 23, 2025 · Penalty $10,000
Resolve - Class - 2
Failure to comply with code requirement for 3307.4.7 work or storage zones. observed street storage area related to the construction adjacent to a sidewalk shed at expo 1, and such area wasn't protected with a
Jun 23, 2025 · Penalty $2,400
Resolve - Class - 2
Observed ongoing soe operations. raker position at corner of expo 1 extending to expo 4 and missing second raker. upon review of provided dob approved drawings, current field conditions does not match drawing.
Mar 27, 2025
Resolve - Class - 2
At time of inspection, i observed the project information panel not posted to construction fence at exposure #1 as per bc 3301.9.1.
Aug 7, 2024 · Penalty $1,250
Resolve - Class - 2
At time of inspection, 20 cubic yards of combustible debris located at premises, a vacant lot, posing a fire and vermin infestation hazard to adjacent occupied premises, repair and/or replace; remove all debris
Dec 29, 2023 · Penalty $625
Active - Class - 2
Temporary construction equipment onsite with expired permit. approx 100lf of construction fence present at exp #1. permit #m00488034-i1-fn for 8'-0" high construction fence expired 06/08/2023., renew permit
Oct 2, 2023 · Penalty $1,250
Resolve - Class - 2
Failure to comply w/the commissioner's order contained in summons/violation #35502461k issued on 02/17/21 & to file a certificate of correction pursuant to 28-201.1 & 1rcny 102-01.remedy:comply w/commissioner's
Apr 12, 2021
Resolve - Class - 1
Failure to maintain bldg-code-compliant manner.noted:@time of my insp i observed on amsterdam ave temp const fence deteriorating.entry plywood doors semidetached part of plywood fence approx35' partially collap
Feb 17, 2021
Resolve - Class - 2
Temporary construction equipment on site-expired permit: noted: observed at location a temporary construction fence at exposure #1 approximately 125 linear feet. permit #122995492 issued for the use of a tempor
Nov 17, 2020 · Penalty $1,250
Resolve - Class - 2
Job site fence not constructed or maintained pursuant to subsection: noted: observed at location at exposure #1 a temporary construction fence under permit #122995492 approximately 125 linear feet. temporary co
Nov 17, 2020 · Penalty $1,000
Resolve - Class - 1
Failure to maintain in code-compliant manner: observed at location a temporary construction fence that is deteriorating. the entry plywood doors are semi detached from the temporary construction fence and is be
Nov 17, 2020 · Penalty $1,250
Resolve - Class - 1
Bc330777-failure to maintain jobsite fence.at time of comp inspection i observed vacant lot with its jobsite fence inadequately maintained with fence leaning outward towards pedestrian traffic(sidewalk)putting
Mar 18, 2020 · Penalty $1,000
Resolve - Class - 1
Failure to maintain guardrails - note: at time of inspection of a complaint. i observed that there were no guardrails installed around opening of more than 5ft in depth this creates a potential fall hazard to p
Mar 29, 2018 · Penalty $5,000
Resolve - Class - 1
3309.12 failure to protect adjoining yard. at time of inspection of a complaint at an active demolition site. i observed that there was no overhead protection for occupants of adjoining protection at exposure 2
Mar 29, 2018 · Penalty $2,500
Resolve - Class - 1
Construction superintendent failed to perform duties as per code. note: at time of inspection of a compliant of an active demolitian site. i issued several vio that included a fir. stop work under - for no supe
Mar 29, 2018
Resolve - Class - 1
3301.2 failure to maintain institute-at time of inspection of an active demolition site with workers working in cellar with no adequate means of egress. i observed a stain with no handrails on platform (inadequ
Mar 29, 2018 · Penalty $2,500
Resolve - Class - 1
3309.14 failure to protect adjoining property during demolition. note: at time of inspection of a complaint at a demo site. active site. i observed demo in progress and no window protection at exposure 2 and 4.
Mar 29, 2018 · Penalty $1,250
Resolve - Class - 2
1rcny 3301-02(d) construction superintendent fails to maintain and/or make job site logs available. note at time of inspection of a complaint. i asked for a superintendent daily log, none provided. no indicatio
Mar 29, 2018
Resolve - Class - 2
Certificate card. at time of my inspection anwering above complaint i observed worker juan urgilez at exp3 erecting scaffolding at the second either were aprx 9'above ground. w/o a 32 hour installers card or a
Feb 26, 2018 · Penalty $400
Resolve
Complaints
- Heating
Heat related
Oct 30, 2007 · Apt BLDG
Close
Sales history
No recorded sales in our data
Building details
- Building type
- Hotel (HR)
- Year built
- 2025
- Floors
- —
- Residential units
- —
- Building area
- 67,488 ft²
- Lot area
- 12,467 ft²
- Zoning
- R7A
- Community board
- 109
- Council district
- 7
- Block / lot
- 2062 / 2
- Assessed value
- $1,291,500
- Landmark / historic district
- No
Questions about 1763 Amsterdam Avenue
Who owns 1763 Amsterdam Avenue?
The owner of record in NYC Department of City Planning PLUTO data is Empire Development Fund, LLC.
Does 1763 Amsterdam Avenue have violations?
NYC HPD has no housing violations on record for this property.
Is 1763 Amsterdam Avenue rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 1763 Amsterdam Avenue built?
City records list 2025 as the year it was built.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.