roofy

1982 3 Avenue

Manhattan, NY 10029BBL 1-01636-0040Map

Owner of record: 1978-82 Third Ave LLC

1982 3 Avenue is a store building built in 1920 in Manhattan, 10029. The owner of record is 1978-82 Third Ave LLC. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
9
ECB violations
22
HPD complaints
0

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 9

  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Dec 12, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Oct 3, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jul 25, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jul 25, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jul 25, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jul 25, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jun 27, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    May 16, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    May 16, 2018

    Dob violation - dismissed

ECB violations · 22

  • Class - 2

    Atoi observed: 3 workers on construction activity consisting of demolition all partitions and working plumbing and also removed all electrical wire and bx cables and removed also the electrical panel box, at fl

    Apr 16, 2025 · Penalty $6,250

    Active
  • Class - 1

    Failure to comply with commissioner's order contained in summons/violation#35250162m issued on 02/22/18 and to file a certificate of correction pursuant to 28-201.1&1rcny 102-01.for work without a permit.remedy

    Oct 2, 2019 · Penalty $2,500

    Active
  • Class - 1

    Failure to comply w/the comm's order contained in summons/vio#35250162m issued on 02/22/18 & to file a c of c pursuant to 28-201.1 & 1rcny 102-01. for work w/o a permit. remedy: comply w/comm's order &/or file

    Jul 26, 2019 · Penalty $6,250

    Resolve
  • Class - 1

    Failure to comply w/the comm's order contained in summons/vio#35250162m issued on 02/22/18 & to file a c of c pursuant to 28-201.1 & 1rcny 102-01. work w/o permit. remedy: comply w/comm's order &/or file a c of

    May 11, 2019 · Penalty $6,250

    Active
  • Class - 1

    Failure to comply w/ the commissioner's order contained in summons/violation#35250162m issued on 2/22/18 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01. work w/o permit. remedy:co

    Mar 9, 2019 · Penalty $6,250

    Active
  • Class - 1

    Failure to comply w/the comm's order contained in summons/vio#35250162m issued on 02/22/18 & to file a c of c pursuant to 28-201.1 & 1rcny 102-01. remedy: comply w/comm's order &/or file a c of c.

    Nov 23, 2018 · Penalty $2,500

    Active
  • Class - 1

    Failure to comply w/the comm's order contained in summons/vio#35250162m issued on 02/22/18 & to file a c of c pursuant to 28-201.1 & 1rcny 102-01. for work w/o a permit. remedy: comply w/comm's order &/or file

    Sep 27, 2018 · Penalty $2,500

    Active
  • Class - 2

    Failure to maintain bldg in a code compliant manner. noted: side entrance on e 109 street side of bldg is bent & out of shape & in a disrepair condition. remedy: comply w/summons. repair/replace door.

    Sep 27, 2018 · Penalty $625

    Resolve
  • Class - 1

    Failure to comply with the commissioner's order contained in summons/violation#35250162m issued on 2/22/18 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01.comply with commissioner;

    Aug 23, 2018 · Penalty $2,500

    Active
  • Class - 2

    Failure to maintain bldg in code compliant manner. at exp#4,observed steel door w/large indentation,major dispair. remedy: comply w/code.

    Aug 23, 2018 · Penalty $625

    Resolve
Show 12 more ↓
  • Class - 1

    Failure to comply w/the comm's order contained in summons/vio#35250162m issued on 02/22/18 & to file a c of c pursuant to 28-201.1 & 1rcny 102-01. work w/o a permit.(cellar) remedy: comply w/comm's order &/or

    Jul 2, 2018 · Penalty $3,125

    Active
  • Class - 1

    Failure to maintain bldg in code compliant manner. noted: at exp#4,(190 e 109th street),steel door bent & in disrepair. remedy: repair &/or replace.

    Jul 2, 2018 · Penalty $3,125

    Resolve
  • Class - 2

    Failure to comply w/ the commissioner's order contained in summons/violation# 35326300j issued on 4/4/18 & to file a c of c pursuant to 28-201.1 & 1rcny 102-01. note: no document file for failure to maintain bl

    May 14, 2018 · Penalty $1,250

    Resolve
  • Class - 1

    Failure to comply with the commissioner's order contained in summons/violation #35250162m issued 02/22/18 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01. note: no document file fo

    May 14, 2018 · Penalty $2,500

    Active
  • Class - 1

    Work w/o a permit. at time of my inspection i observed on the main floor in the back of the store the installation of new gas piping to a heating unit w/o a permit. utility company locked head of service gas

    May 1, 2018 · Penalty $1,600

    Active
  • Class - 1

    Gas being supplied to bldg w/o inspection & certification by dob. at time of my inspection i observed gas being supplied to the bldg w/o dob authorization after new gas piping was installed in the back of the

    May 1, 2018 · Penalty $5,000

    Active
  • Class - 1

    Failure to maintain bldg in code compliant manner. at time of my inspection,i observed in the cellar a gas flex installed in a prohibited location. utility company locked head of service gas valve & removed fle

    May 1, 2018 · Penalty $1,250

    Active
  • Class - 1

    Failure to have new or altered plumbing system tested. at time of my inspection,i observed new gas piping installed that have not been tested in the back of the store by the heating unit. utility company locked

    May 1, 2018 · Penalty $2,500

    Active
  • Class - 1

    Failure to maintain building in code-compliant manner. at the time of inspection, i observed at exp #2 steel door had been bend onto the buiding leading infested mice/rats through the opening. at exp #2 sidewal

    Apr 4, 2018 · Penalty $1,563

    Active
  • Class - 1

    Failure to maintain bldg in code compliant manner. noted: 1)sidewalk vault in fromt exp#1 extends approx 5ffet fromt bldg front towards street. approx 3feet front corner(ax 1,4)the sidewalk vault at street leve

    Feb 22, 2018 · Penalty $500

    Active
  • Class - 1

    Work w/o a permit. noted: in cellar wooden 8inch by 8inch wooden timbers throughout supporting beam for ground floor store. some along exp#4middle of bldg from expose 1 to 3 & along exp#2,also at exp#1 the side

    Feb 22, 2018 · Penalty $1,600

    Active
  • Class - 1

    Failure to maintain exterior bldg walls or appurtenances. defects noted: at time of inspection there is spalling/spalled brownstone from lintels above & below windows at exposure #4 side of bldg. fire escape is

    Oct 18, 2012 · Penalty $1,000

    Resolve

Complaints

No HPD complaints in our records

Complaint data is still being backfilled from NYC Open Data.

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Store building (K4)
Year built
1920
Floors
4
Residential units
—
Building area
1,000 ft²
Lot area
1,330 ft²
Zoning
R9
Community board
111
Council district
8
Block / lot
1636 / 40
Assessed value
$286,200
Landmark / historic district
No

Questions about 1982 3 Avenue

Who owns 1982 3 Avenue?

The owner of record in NYC Department of City Planning PLUTO data is 1978-82 Third Ave LLC.

Does 1982 3 Avenue have violations?

NYC HPD has no housing violations on record for this property.

Is 1982 3 Avenue rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 1982 3 Avenue built?

City records list 1920 as the year it was built.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.