roofy

253 East 62nd Street

Manhattan, NY 10065BBL 1-01417-0021Map

Owner of record: 253 East 62nd Street,

253 East 62nd Street is an elevator apartment building built in 2016 in Manhattan, 10065. It has 6 residential units across 10 floors. The owner of record is 253 East 62nd Street,. HPD has recorded 38 housing violations here, most recently on April 29, 2026. 38 of the 38 most recent violations are still open.

HPD violations
38
DOB violations
32
ECB violations
52
HPD complaints
42

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
Last violation Apr 29, 2026

Date of the most recent HPD inspection that found a problem.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 38

  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Apr 29, 2026

    Open — Nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 17, 2025

    Open — Info nov sent out
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Jun 4, 2025

    Open — Nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 22, 2024

    Open — Info nov sent out
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Apr 1, 2024

    Open — Nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 15, 2023

    Open — Info nov sent out
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Mar 15, 2023

    Open — Nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 3, 2022

    Open — Info nov sent out
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Feb 15, 2022

    Open — Nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Feb 15, 2022

    Open — Info nov sent out
Show 28 more ↓
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Apr 1, 2021

    Open — Nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Apr 1, 2021

    Open — Info nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Oct 25, 2019

    Open — Info nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Oct 5, 2018

    Open — Info nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 6, 2017

    Open — Info nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Oct 24, 2016

    Open — Info nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Oct 1, 2015

    Open — Info nov sent out
  • B

    Arrange and make self-closing the doors , in the entrance located at apt 2a, 2nd story

    Feb 7, 2009 · Apt 2A

    Open — First no access to re- inspect violation
  • B

    Repair or replace the smoke detector missing in the entire apartment located at apt 2a, 2nd story

    Feb 7, 2009 · Apt 2A

    Open — First no access to re- inspect violation
  • B

    Provide an approved and operational carbon monoxide detecting device, installed in accordance with applicable law and rules. in the entire apartment located at apt 2a, 2nd story

    Feb 7, 2009 · Apt 2A

    Open — First no access to re- inspect violation
  • B

    Properly secure the loose door saddle in the bathroom located at apt 2a, 2nd story

    Feb 7, 2009 · Apt 2A

    Open — First no access to re- inspect violation
  • A

    Post a proper notice of carbon monoxide detecting device requirements, in a form approved by the commissioner, in a common area of a class a multiple dwelling near inspection certificate or provide notice to tenants in a private dwelling. at public hall, 1st story

    Jan 24, 2009

    Open — Not complied with
  • A

    Post sign on wall of entrance story bearing name, address including apartment number if any, and telephone number of superintendent, janitor or housekeeper.

    Jan 30, 1998

    Open — Not complied with
  • B

    Section 300, 301, 302, m/d law file plans and obtain a certificate of occupancy to legalize the following alteration or restore premises to prior legal condition formcrcy 3 class a apts converted into 1 class a apt 2 sty.

    Mar 5, 1996

    Open — First no access to re- inspect violation
  • B

    Repair the broken or defective plastered surfaces and paint in a uniform color water damaged ceiling & walls northwest room i sty apt 2b , section '' ''

    Jul 27, 1994 · Apt 2B

    Open — First no access to re- inspect violation
  • B

    Provide hot water at all hot water fixtures 3 sty apt 3b , section '' ''

    Feb 16, 1994 · Apt 3B

    Open — First no access to re- inspect violation
  • B

    Repair or replace the smoke detector missing 4 sty front east apt 4a zucker. , section '' ''

    Mar 23, 1993 · Apt 4A

    Open — First no access to re- inspect violation
  • B

    Properly repair the broken or defective balance lower sash north window northeast room 5 sty east apt 5a. located at apt 5a

    Jan 12, 1993 · Apt 5A

    Open — First no access to re- inspect violation
  • A

    Properly repair with similar material the broken or defective glazing puddy top and bottom window sashes thru out 5 sty east apt 5a. located at apt 5a

    Jan 12, 1993 · Apt 5A

    Open — First no access to re- inspect violation
  • B

    M/d law abate the nuisance consisting of lower sash south window at east painted shut southeast room 5 sty east apt 5a. located at apt 5a

    Jan 12, 1993 · Apt 5A

    Open — First no access to re- inspect violation
  • B

    M/d law abate the nuisance consisting of moisture penetrating ceiling northeast room 5 sty east apt 5a. located at apt 5a

    Jan 12, 1993 · Apt 5A

    Open — First no access to re- inspect violation
  • A

    Paint with light colored paint to the satisfaction of this department ceiling northeast room 5 sty east apt 5a. located at apt 5a

    Jan 12, 1993 · Apt 5A

    Open — First no access to re- inspect violation
  • A

    Post sign on wall of entrance story bearing name, address including apartment number if any, and telephone number of superintendent, janitor or housekeeper.

    Jan 12, 1993

    Open — Not complied with
  • B

    Properly repair the broken or defective light fixture at wall 4 sty apt 5b bathroom. located at apt 5b

    Sep 21, 1992 · Apt 5B

    Open — First no access to re- inspect violation
  • B

    Section 300, 301, 302, m/d law file plans and obtain a certificate of occupancy to legalize the following alteration or restore premises to prior legal condition four apts 2 sty converted to commercial space.

    Sep 30, 1991

    Open — First no access to re- inspect violation
  • B

    Repair or replace the smoke detector missing 4 sty northwest apt 4a zucker. located at apt 4a

    May 1, 1991 · Apt 4A

    Open — First no access to re- inspect violation
  • B

    Properly repair the broken or defective improperly counterbalance lower window sash 4 sty northwest apt 4a thru out. located at apt 4a

    May 1, 1991 · Apt 4A

    Open — First no access to re- inspect violation
  • A

    Section 300 m/d law file plans and application and legalize the following alteration or restore to the legal condition existing prior to the making of said alteration commercial sink and walking in freezer cellar at east.

    Sep 14, 1989

    Open — First no access to re- inspect violation

DOB building violations · 32

  • Construction other optional

    Borough commissioner has issue a stop work order under application # 121332138. due to applicant or contractor withdrawal. stop all work

    Jun 25, 2019

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Oct 31, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Aug 22, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Aug 22, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Aug 22, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Aug 22, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Apr 18, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Apr 18, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Apr 18, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Apr 18, 2018

    Dob violation - dismissed
Show 22 more ↓
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Mar 7, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Mar 7, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Mar 7, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Mar 7, 2018

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Mar 7, 2018

    Dob violation - dismissed
  • Construction other optional

    C-construction other optional

    Jan 27, 2018

    Vp*-violation unserved ecb- dismissed
  • Construction other optional

    C-construction other optional

    Sep 27, 2017

    Vp*-violation unserved ecb- dismissed
  • Construction other optional

    C-construction other optional

    Sep 27, 2017

    Vp*-violation unserved ecb- dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Dec 28, 2016

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Nov 4, 2015

    Dob violation - dismissed
  • Construction other optional

    C-construction other optional

    Aug 18, 2009

    Dob violation - dismissed
  • Construction other optional

    C-construction other optional

    Jul 2, 2009

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Jan 1, 2009

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Jan 3, 2008

    Dob violation - dismissed
  • Construction other optional

    C-construction other optional

    Dec 5, 2001

    Dob violation - dismissed
  • Construction other optional

    C-construction other optional

    Dec 5, 2001

    Dob violation - dismissed
  • Construction other optional

    C-construction other optional

    May 17, 1994

    Vp*-violation unserved ecb- dismissed
  • Construction other optional

    C-construction other optional

    May 17, 1994

    Dob violation - dismissed
  • Construction other optional

    C-construction other optional

    Jun 1, 1992

    Dob violation - dismissed
  • Construction other optional

    C-construction other optional

    Jun 1, 1992

    Vp-violation unserved ecb-active
  • Construction other optional

    C-construction other optional

    Oct 9, 1991

    Dob violation - dismissed
  • Construction other optional

    C-construction other optional

    Dec 9, 1988

    Dob violation - dismissed

ECB violations · 52

  • Class - 2

    70z9 pit water leak remove

    Mar 11, 2019

    Resolve
  • Class - 2

    Egress. at time of inspection i observed a temporary scaffold completely blocking off the staircase at the duplex level. workers were observed on the floors where the egress was blocked while the scaffold was n

    Aug 7, 2018 · Penalty $10,000

    Resolve
  • Class - 1

    Bc 3314.4 scaffold. at time of inspection of a 10 story nb i observed the supported scaffold w/ loose platforms, excess concrete debris and missing toe boards throughout the entire scaffolds. scaffold was in us

    Aug 7, 2018 · Penalty $12,500

    Resolve
  • Class - 1

    Unsafe storage of materials.at time of inspection observed materials stored against construction fence creating undue stress on fence and creating a condition where fence could fail and break/fall onto public p

    May 21, 2018 · Penalty $2,500

    Resolve
  • Class - 1

    Guardrail-inadequate.at 6,7,8,9,10 flr observed guardrails that were inadequate cables were no taunt and moved more than 2 inches,mat windowcables no attached at staires 2 x 4 guardrails werent at correct heigh

    May 21, 2018 · Penalty $2,500

    Resolve
  • Class - 1

    Missing handrails at time of inspection observed stair to hoie level had no handrail to prevent public from fall.at roof level,ladder to bulkhead,handrail did no extend 2'-0' onto bulkhead handrail did not exte

    May 21, 2018 · Penalty $2,500

    Resolve
  • Class - 1

    Scaffold;at time of insepction observed scaffold erected erected to roof at exp1.planking on scaffold was not tied with wire or nailed creating a condition where planking could shift & dislodge at other areas o

    May 21, 2018 · Penalty $2,500

    Resolve
  • Class - 1

    Fdny-general-fire extinguishers.at time of inspection observed multiple areas where fire extinguisher were not maintain in minimum of 4 inches off the floor or not hung.observed on floor where there was no fire

    May 21, 2018 · Penalty $6,250

    Resolve
  • Class - 1

    3307.2.1 failure to comply w/dot regulations. at time of inspection on an active jobsite of a 10 story building, observed material storage on the street enclosed by a yodock system. material consisting of brick

    Jan 27, 2018 · Penalty $1,600

    Resolve
  • Class - 1

    3304.4 sidewalk shed debris and material. at time of inspection on an active jobsite, observed debris, material storage on the sws. sws is to be maintained free of debris and materials at all times. under const

    Jan 27, 2018 · Penalty $1,600

    Resolve
Show 40 more ↓
  • Class - 1

    3304.7 required means of egress. at time of inspection of an active jobsite of a 10 story building observed that the means of egress were compromised. means of egress/ingress from hoist to work site and from wo

    Jan 27, 2018 · Penalty $1,600

    Resolve
  • Class - 1

    Housekeeping. at time of inspection on an active jobsite of a 10 story building observed debris. building materials scattered throughout jobsite. also, by hoist areas this situation creates a trip and fall haza

    Jan 27, 2018 · Penalty $2,400

    Resolve
  • Class - 1

    Failure to maintain/display on site documents required by chapter 33. note: observed 10 sty bldg erected to 10 fl,observed workers at 5th fl/3rd fl tied off to existing concrete enbedded straps. there is no tra

    Dec 7, 2017

    Resolve
  • Class - 2

    Sec. 3303.4.7 storage rear sidewalks/walkways. note: 10 sty bldg erected to 10 fl observed on 62 st bricks pallets stacked approx 5-6 feet high in street only be 3 feet high. remedy: comply w/code.

    Dec 7, 2017

    Resolve
  • Class - 2

    Failure to maintain: housekeeping note: 10 sty bldg erected to 10 fl at exp#2 of site. workers performing stucco operation. there is white debris blowing off scaffold into air & street. the debris should be con

    Dec 7, 2017 · Penalty $800

    Resolve
  • Class - 2

    Work does not conform to approved construction documents &/or approvedamendments. note: at time of inspection observed supported scaffold about 150 foot in height on top of sidewalk shed upon further review of

    Dec 4, 2017 · Penalty $250

    Resolve
  • Class - 2

    Failure to have sidewalk shed built according to plan.note at time of inspection i observed sidewalk shed in place missing cross braces & verticle pipe.rem:comply with code provide crossbraces & verticle pipe.

    Dec 4, 2017

    Resolve
  • Class - 1

    Bc 3308.6.1.4 supported scaffold(alternative) horizontal nets.note:observed active site,erected to the 10 fl level @exp#1/4 there is a supported (scaffold) in place in (lines) of horizontal (nets).there air res

    Sep 27, 2017 · Penalty $1,600

    Resolve
  • Class - 1

    Work does not conform to approved const docs as amendments.note:10 story bldg erected to the 10 fl level, observed shear will platform installed @exp#2/3 (@)6th fl the platform are not erected as per designs on

    Sep 27, 2017 · Penalty $1,000

    Resolve
  • Class - 2

    Failure to maintain housekeeping.note:10 story bldg erected to (10 fl) level not enclosed observed various housekeeping issues.(hz) (nets) exp#3 not clean,lead edge exp#1 not clean, stairs not clean,supported s

    Sep 27, 2017 · Penalty $800

    Resolve
  • Class - 1

    Bc 3305.3.6.1.2 (reshores) in (proxmity) of uneclosed perimeter note:10 story bldg erected to the 10 fl level the bldg is not enclosed @perimeter.there are approx 15-20 (reshores) on 9 fl, 10 fl that are @the l

    Sep 27, 2017 · Penalty $1,600

    Resolve
  • Class - 1

    Failure to institute/(recreation).safety equipmtment measure or temp const:toe boards note:@time of insp 10 story bldg masonry work being done on the interior of bldg i observed guardrail w/inadequate toeboards

    Sep 27, 2017 · Penalty $1,000

    Resolve
  • Class - 1

    Bc3301.2/safety measures:note at time of inspection of a 10 story new building at bulkhead level.i observe safety embeded straps installed at several floors at perimeter and interior.i ask for a daily log for

    Aug 30, 2017 · Penalty $1,630

    Resolve
  • Class - 1

    Safety measures.note at time of inspection of a 10 story new building at bulkhead phase.i observed on all floor at elevator shaft-a temporary platform i erected and being use as a means egress.with wooden ladde

    Aug 30, 2017 · Penalty $1,630

    Resolve
  • Class - 2

    Failure to maintain adequate house keeping.note at time of inspection of a 10 story new building at bulkhead level.i observe excessive debris and construction equipment and cardboard scattered over several loca

    Aug 30, 2017

    Resolve
  • Class - 2

    Work does not conform to approved construction documents.note:at time of inspection of a 10 story new building at bulkhead level.i observed a supported scaffold erected to 8fl.checking the site safety plain sho

    Aug 30, 2017

    Resolve
  • Class - 1

    Bc3307.7.5 design of fences. note: at time of my inspection of a 10 story bldg at excavation phase, construction work in progress.i observe apprx 140 feet of construction fence ereced at exp1 and 4 made of

    Oct 4, 2016 · Penalty $1,600

    Resolve
  • Class - 1

    Guardrail system. note: at the time of my inspection of a 10 story building in excavation phase construction work in progress. i observed that there were no guardrail system provided at side of excavation at ex

    Oct 4, 2016 · Penalty $2,400

    Resolve
  • Class - 2

    Pedestrian protection does not meet code specs.noted:observed sidewalkshed erected @exp#1(e 62 st)& exp#4(2nd ave) under permit #122415797-01-eq-sh.sidewalk shed lights not operating @time of insp 1:45 am that

    Sep 12, 2015 · Penalty $400

    Resolve
  • Class - 1

    Sec. 3307.6.5 failure to maintain sidewalk shed no artificial lightingas per code. at time of complaint inspection noted that lighting undersidewalk shed are not connected to any electrical output. therefore

    Sep 9, 2015 · Penalty $1,600

    Resolve
  • Class - 1

    Failure to carry out demolition operations as required by section of code.at time of insp.noted that @ the 3rd level of job all the joist where removed leaving 3 walls fuse standing also the floor joist on the

    Aug 13, 2015 · Penalty $2,400

    Resolve
  • Class - 1

    Sec. 3314.8 guardrails & toe boards. at time of inspection observed,active job site. supported pipe scaffold erected at exp#1,2,3 & 4. guardrails are inadequate at exp#1 & 2 & are placed lower than the required

    Aug 3, 2015 · Penalty $1,600

    Resolve
  • Class - 2

    Failure to maintain adequate housekeeping. at time of inspection observed,active job site. debris found on all floors not cleaned from site.the job site foreman stated that the debris have not been cleaned dail

    Aug 3, 2015 · Penalty $400

    Resolve
  • Class - 1

    Sec. 3301.7 design drawing required. at time of inspection observed,active job site. supported pipe scaffold erected at the exterior of the bldg at all exposures. approved plans only show the scaffold erected @

    Aug 3, 2015 · Penalty $1,000

    Resolve
  • Class - 2

    Pedestrian protection does not meet code specs.noted @ time of inspection underside lights for sidewalk shed are not lit.time of inspection 10pm.rem comply w/ code

    Jul 10, 2015 · Penalty $2,400

    Resolve
  • Class - 2

    Sidewalk shed does not meet code specifications noted:signage missing junior beams cantileviered on both ends approx 4 lf.remedy:conform shed to code specifications

    Mar 4, 2010 · Penalty $2,400

    Resolve
  • Class - 2

    Sidewalk shed does not meet bldg code specs noted shed at exp #1 missing horizontal bracing and columns are out of plumb and not level shed is beaming draticaly previous vio's written agg 2 condition for hitor

    Dec 24, 2009 · Penalty $2,400

    Resolve
  • Class - 2

    Failure to maintain lighting under sidewalk shed noted at approx 6pm in dark the lighting under shed is inoperable previous vio's written for this condition.remedy maintain lighting.

    Dec 24, 2009 · Penalty $2,400

    Resolve
  • Class - 2

    Sdwlk shed doesnt meet bldg code spec's.noted:shed @ exp#1 under permit#120148562.the support columns are out of plums & not level & it is missing horizontal & cross bracing.vio written 12-2-09 for some conditi

    Dec 18, 2009 · Penalty $2,400

    Resolve
  • Class - 2

    Failure to maintain lighting under shed. noted: shed erected at exp #1. lights are inoperable at approx 6 am. remedy: maintain shed lighting.

    Dec 2, 2009 · Penalty $2,400

    Resolve
  • Class - 2

    Sidewalk shed does not meet bldg code specifications. noted: shed at exp #1 under pmt #120148562. the columns are out of plumb and not level approx 6" to 8" cross bracing is disconnected and electric for

    Dec 2, 2009 · Penalty $2,400

    Resolve
  • Class - 1

    Sec. bc 1001.4, 27-365. inadequate exits from existing structure: illegal condition. noted: at 4th fl apt 4b (rear) & 5th fl apt 5b (rear) having no 2nd means of egress as required by law. remedy: provide

    Jul 22, 2008 · Penalty $1,600

    Resolve
  • Non-hazardous

    Work without permits demolition of interior partition walls & ceilings at secend floor apartment 2b remedy: stop all work obtain approals permits before doing any futher construction.

    Aug 21, 2002

    Resolve
  • Non-hazardous

    Occupancy contrary to certificate of occupancy noted: occuapncy at rear of 1st flr residential lobby is contrary to building department records (altereation plan alt 1038/45 c. of o. 32/72 rear of residentail l

    Dec 22, 1995 · Penalty $1,000

    Resolve
  • Non-hazardous

    Occupancy contrary to that allowed by the certificate of occupancy #32172.from 3apt at 2nd fl to office for computer services remedy discontinue illegal use or obtain a valid c of o for current use.

    Nov 29, 1995 · Penalty $800

    Resolve
  • Non-hazardous

    Work without a permit work noted partition walls removed kitchen fixture /cabinets removed bathroom fixture removed changing 3apts at 2nd flr to open office space remedy obtian a permit if feasible or restore p

    Nov 29, 1995

    Resolve
  • Non-hazardous

    Failure to maintain bldg wall:defect is: at east 62st side of premises3 floor brownstone lintels are spalling,cracked + defective.section ofuntel has broken off +struck pedestrian at sidewalk.remedy:provide pro

    Aug 10, 1995 · Penalty $800

    Resolve
  • Non-hazardous

    Contrary to the c of o isssued oct.3 1946 the 2nd story use has been changed from 3 aprtments to offices.remedy:discontinue the use or 2 if feasible file with this dept.and obtain a new c of o.

    Feb 16, 1993 · Penalty $350

    Resolve
  • Non-hazardous

    Occupancy at rear of 1st floor residential lobby is contrary to building department records (alteration plan alt 1038 - 45, c/0 #32172. rear of residential lobby has been cobnverted to office use (realestate of

    Oct 2, 1991 · Penalty $285

    Resolve
  • Non-hazardous

    Contrary to certificate of occupancy issued october 3 1946 the wnd story use has been changed from 3apts to offices remedy discontinue ue or if feasible obtain new coertificate of occupancy

    Oct 17, 1990

    Resolve

Complaints

  • Unsanitary condition

    Pests

    May 13, 2026 · Apt 1

    Close
  • Heat/hot water

    Entire building

    May 13, 2026 · Apt 1

    Close
  • Unsanitary condition

    Pests

    May 13, 2026 · Apt 1

    Close
  • Unsanitary condition

    Pests

    May 13, 2026 · Apt 1

    Close
  • Door/window

    Door

    May 13, 2026 · Apt 1

    Close
  • Electric

    Power outage

    May 13, 2026 · Apt 1

    Close
  • Plumbing

    Water supply

    May 13, 2026 · Apt 1

    Close
  • Plumbing

    Water supply

    May 13, 2026 · Apt 1

    Close
  • Door/window

    Door

    May 13, 2026 · Apt 1

    Close
  • Electric

    No lighting

    May 13, 2026 · Apt 1

    Close
Show 32 more ↓
  • Door/window

    Door

    May 13, 2026 · Apt 1

    Close
  • Plumbing

    Toilet

    May 13, 2026 · Apt 1

    Close
  • Heat/hot water

    Apartment only

    May 13, 2026 · Apt 1

    Close
  • Plumbing

    Water supply

    May 13, 2026 · Apt 1

    Close
  • Electric

    Power outage

    May 13, 2026 · Apt 1

    Close
  • Door/window

    Door

    May 13, 2026 · Apt 1

    Close
  • Paint/plaster

    Wall

    Aug 4, 2008 · Apt 4

    Close
  • Nonconst

    Vermin

    Dec 5, 2007 · Apt 4B

    Close
  • Nonconst

    Vermin

    Dec 5, 2007 · Apt 4B

    Close
  • General

    Floor

    Dec 5, 2007 · Apt 4B

    Close
  • Electric

    Lighting

    Dec 5, 2007 · Apt 4B

    Close
  • Plumbing

    Basin/sink

    Dec 5, 2007 · Apt 4B

    Close
  • Plumbing

    Toilet

    Dec 5, 2007 · Apt 4B

    Close
  • General

    Doors

    Dec 5, 2007 · Apt 4B

    Close
  • General

    Windows

    Dec 5, 2007 · Apt 4B

    Close
  • General

    Windows

    Dec 5, 2007 · Apt 4B

    Close
  • Paint/plaster

    Wall

    Dec 5, 2007 · Apt 4B

    Close
  • Heating

    Heat related

    Dec 5, 2007 · Apt 4B

    Close
  • Paint/plaster

    Wall

    Jun 27, 2007 · Apt BLDG

    Close
  • Appliance

    Electric/gas range

    Dec 14, 2006 · Apt 4B

    Close
  • General

    Floor

    Dec 14, 2006 · Apt 4B

    Close
  • Paint/plaster

    Wall

    Dec 14, 2006 · Apt 4B

    Close
  • Paint/plaster

    Wall

    Dec 14, 2006 · Apt 4B

    Close
  • General

    Doors

    Dec 14, 2006 · Apt 4B

    Close
  • General

    Windows

    Dec 14, 2006 · Apt 4B

    Close
  • General

    Windows

    Dec 14, 2006 · Apt 4B

    Close
  • Nonconst

    Vermin

    Dec 14, 2006 · Apt 4B

    Close
  • Nonconst

    Vermin

    Dec 14, 2006 · Apt 4B

    Close
  • Nonconst

    Vermin

    Dec 14, 2006 · Apt 4B

    Close
  • Nonconst

    Vermin

    Dec 14, 2006 · Apt 4B

    Close
  • Nonconst

    Vermin

    Mar 23, 2004 · Apt 4B

    Close
  • Nonconst

    Vermin

    Mar 23, 2004 · Apt 4B

    Close

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Elevator apartment building (D7)
Year built
2016
Floors
10
Residential units
6
Building area
17,164 ft²
Lot area
1,779 ft²
Zoning
C2-8
Community board
108
Council district
5
Block / lot
1417 / 21
Assessed value
$3,573,000
Landmark / historic district
No

HPD registration #132664, last renewed Dec 23, 2014.

Questions about 253 East 62nd Street

Who owns 253 East 62nd Street?

The owner of record in NYC Department of City Planning PLUTO data is 253 East 62nd Street,.

Does 253 East 62nd Street have violations?

Yes. NYC HPD has recorded 38 housing violations at this property.

Is 253 East 62nd Street rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 253 East 62nd Street built?

City records list 2016 as the year it was built.

How many apartments are in 253 East 62nd Street?

It has 6 residential units and 7 units in total.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.