226 East 54 Street
Manhattan, NY 10022BBL 1-01327-0035Map
Owner of record: Gemini Partners Realty LLC
226 East 54 Street is an office building built in 1920 in Manhattan, 10022. The owner of record is Gemini Partners Realty LLC. HPD has no housing violations on record for this property.
- HPD violations
- 0
- DOB violations
- 30
- ECB violations
- 31
- HPD complaints
- 0
What to know
No open immediately-hazardous violations among recent records.
HPD has not cited this building.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 0
No HPD violations on record
DOB building violations · 30
- Failure to post energy grade/score none
Failure to display energy efficiency score and energy efficiency grade as per adcode sec. 28-309.12.3
Dec 1, 2024
Dob violation - active - Failure to post energy grade/score none
Failure to display energy efficiency score and energy efficiency grade as per adcode sec. 28-309.12.3
Dec 1, 2023
Dob violation - active - No report and / or late filing (facade) facade required
Failed to file fisp cycle 9b technical report by 2/21/2023
Feb 22, 2023
Dob violation - active - Failure to post energy grade/score none
Failure to display energy efficiency score and energy efficiency grade as per adcode sec. 28-309.12.3
Dec 1, 2022
Dob violation - active - Failure to post energy grade/score none
Failure to display energy efficiency score and energy efficiency grade as per adcode sec. 28-309.12.3
Dec 1, 2021
Dob violation - active - Failure to post energy grade/score none
Failure to display energy efficiency score and energy efficiency grade as per adcode sec. 28-309.12.3
Apr 29, 2021
Dob violation - active - Sprinkler none
Failed to file final sprinkler report by july 1, 2019
Sep 3, 2019
Dob violation - active - Elevator elevatorrequired
E-elevator elevatorrequired
Apr 9, 2019
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Mar 25, 2015
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Mar 25, 2014
Dob violation - resolved
Show 20 more ↓
- Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jan 15, 2014
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Feb 14, 2013
Dob violation - resolved - Facade facade optional
File unsafe report cycle 7
Aug 21, 2012
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
May 2, 2012
Dob violation - resolved - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Apr 4, 2012
Dob violation - dismissed - Emergency none
Egncy-emergency none
Jan 24, 2012
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Jul 21, 2011
Dob violation - resolved - Plumbing none
P-plumbing none
Mar 1, 2010
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Sep 22, 2009
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
May 28, 2008
Dob violation - resolved - Emergency power none
Ll2604e-emergency power none
Mar 31, 2008
Dob violation - active - Facade facade optional
Ll1198-local law 11/98 - facade facade optional
Nov 30, 2007
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Jul 11, 2007
Dob violation - resolved - Photoluminescent none
Ll2604-photoluminescent none
Nov 1, 2006
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Jul 5, 2006
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jan 13, 2004
Dob violation - resolved - Facade facade required
L1198-local law 11/98 - facade facade required
Aug 8, 2002
Dob violation - dismissed - Construction other optional
C-construction other optional
Oct 6, 2000
Dob violation - dismissed - Elevator elevatorrequired
1p29738
May 11, 2000
Dob violation - resolved - Public assembly none
Pa-public assembly none
Nov 2, 1991
Dob violation - dismissed
ECB violations · 31
- Class - 2
A. c. 27-929.1, failure to complete the installation of a full system of automatic sprinklers and file a final sprinkler report prepared by a registered design professional in an office building 100 feet or mor
Jun 17, 2024 · Penalty $6,250
Active - Class - 2
Failure to submit an acceptable required cycle 9b report of critical examination documenting condition of exterior wall and appurtenances required by 28-302.4 for control #904611. remedy: submit acceptable requ
Apr 11, 2024 · Penalty $1,250
Active - Class - 2
27-929.1 failure to complete the installation of a full system of automatic sprinklers and file a final sprinkler report prepared by a registered design professional in an office building 100 feet or more in he
Feb 28, 2023 · Penalty $6,250
Active - Class - 2
27-929.1 ac27-929.1,failure to complete installation of full system ofautomatic sprinklers&file final sprinkler report prepared by registered design professional in office bldg 100' or more in hy in existence o
Mar 30, 2021 · Penalty $3,125
Active - Class - 2
Sec. 27-929.1 ac 27-929.1 failure to complete the installation of a full system of automatic sprinklers & file a final sprinkler report prepared by a registered design professional by 7/1/19,in an office bldg
Mar 30, 2020 · Penalty $3,125
Active - Class - 2
Failure to maintain ext bldg facade & appurtenances.as noted exposure1several locations w/spalled bricks,vertical crack in bricks above 1st fl.exp:4-spalled masonry in several locations,exposed rebar spalling c
Jan 28, 2020 · Penalty $1,250
Active - Class - 2
Ac279291-failure to complete the installation of a full system of automatic sprinklers and file a final sprinkler report prepared by a registered design professional by july 1,2019,in an office building 100 fee
Nov 15, 2019 · Penalty $6,250
Active - Class - 2
Failure to maintain bldg walls & appurtenances. noted: at time of inspection at exp#1 a/ spalled concrete at parapet b/spalling concrete at various spots at east facing facade of stair sahft from f8-9 c/spallin
Apr 26, 2017
Resolve - Class - 1
Failure to provide & maintain safety measures such as sidewalk shed,fence etc to protect public from document unsafe facades-cycle 7b facade filing was designated as"unsafe". at time of inspection no such safet
Apr 26, 2017 · Penalty $2,400
Resolve - Class - 2
Failure to file acceptable amended report indicating correction of unsafe conditions described in initial local law 11/98 report. remedy: file acceptable amended report.
Nov 7, 2016 · Penalty $800
Resolve
Show 21 more ↓
- Class - 2
Failure to file an acceptable amended cycle 7 report to this dept indicating correction of unsafe conditions described in initial local law fisp report. remedy: file an amended report following remedial repairs
Dec 11, 2015 · Penalty $800
Resolve - Class - 2
Removal of shed w/o dept approval. note: facade repairing job #121345 099 has been completed and signed off at 1.23.2014 facade inspection report never been filed to facade unit.sidewalk shed has been removed
Jul 28, 2015 · Penalty $800
Resolve - Class - 1
Failure to maintain exterior bldg wall(s) or appurtenances. defects noted: at time of inspection pcs of stucco have spalled off of the exp #4 side of bldg (west side exp) down to set back roof of 220 east 54th
Aug 8, 2012 · Penalty $2,400
Resolve - Class - 2
Failure to comply w/the commissioner's order to file a c/c w/the dob. defects noted at time of inspection no c/c filed for ecb nov #34937738k. dated 1.13.12. remedy: file c/c.
Mar 26, 2012 · Penalty $800
Resolve - Class - 1
Failure to maintain exterior building wall(s) or appurtenances. defects noted:at time of inspection there is concrete spalling & craking at all floors. some concrete has fallen & other concrete is hanging in an
Jan 13, 2012 · Penalty $1,000
Resolve - Class - 2
Exit passage/corridor required width decreased by obstruction. noted: the west exit corridor for required means of egress has been obstructed w/wood materials, boxes, garbage, mops and buckets. remedy:clear all
Apr 24, 2011 · Penalty $250
Resolve - Class - 2
Work w/o a permit. noted: at 3rd fl front (north) office space,ceilinggrid,flooring & partitions have been completely demolished & remove. all work done w/o a permit. remedy: stop all work at 3rd fl north offic
Jul 2, 2010 · Penalty $800
Resolve - Class - 3
Failure to maintain bldg in a code-complaint manner: noted defects at 3rd flr suite #308 rear exposure casement type windows are sealed shutcaulked w/silicone caulk not operational (unable to vent).
Apr 19, 2010
Resolve - Class - 1
Fail to maintain bldg in a code compliant manner. at front facade exp 1 at above 5th fl windows near parapet center of facade shards of stucco have broken loose & fell to public sidewalk below. obtain a sidewal
Mar 30, 2010 · Penalty $1,000
Resolve - Class - 2
44h9.44h11.52h11.42b10.100h11.42 replace worn contacts on p relay and relay and replace shut wire on sfs relay 100 replace worn saddle on lobby hall door
Feb 9, 2010 · Penalty $500
Active - Class - 1
Failure to provide unobstructed exit passageway: noted: at 9th flr 6th flr & 7th flr & lobby level fire egress stairway refuse stored at landings. remedy: remove obstruction forthwith.
Feb 2, 2010 · Penalty $1,200
Resolve - Class - 2
Failure to file an architect / engineer report certifying exit / directional signal signs are connected to emergency power source / storage battery equipment. remedy: file architect / engineer report.
Jan 27, 2010 · Penalty $800
Active - Non-hazardous
Altered bldg occupied w/o a valid c of o. noted: alt #760/82 to increase bldg height from 6 stry to 9 story. remedy: obtain valid c of o.
Dec 30, 1998
Resolve - Non-hazardous
Operation of assembly w/o current permit. noted: expired pa permit #32/84 exp 08/03/97. bldg w/o c of o required under alt application #760/82. "dba" pulse at 1st fl. remedy: discontinue illegal use! obtain
Dec 30, 1998
Resolve - Non-hazardous
Operation of place of assembly without current permit a pa is in operation on the ground floor no cureent permit permit 32/84 with 8000 issued jannury 15 1997 and expired august 3 1997 remedy obtain pa permit
Oct 30, 1998
Resolve - Hazardous
Failure to install an acceptable two way voice communication system with central station connection. remedy: provide either tr-1 form or 23c & 23d forms or building department sign off as per local laws of 197
Jun 2, 1997 · Penalty $500
Resolve - Non-hazardous
Altered building occupied without a valid c. of o. alt#760-82 remedy: obain a valid c. of o.
Jan 19, 1996
Resolve - Non-hazardous
Work without a permit. noted: three large air conditioning units have been installed in rear yard of building without first obtaining permitremedy:obtain permits and approvals from this department or restore to
Oct 30, 1991 · Penalty $285
Resolve - Non-hazardous
Failure to maitain exterior wall. defect noted: spalling concrete noted throughout south (rear)wall and west wall (at rear). pieces of concrete fell to rear yard of adjacent building (220 e 54 st)remedy:provide
Mar 20, 1991
Resolve - Hazardous
Failure to have approved pa plan available for inspection remedy provide apprve plan for inspection
Jun 1, 1990 · Penalty $115
Resolve - Non-hazardous
Altered bldg occupied without a valid c of o under alt.#760/82 for 7,8,9. failure to provide approved plans at premises at time of inspection for alt. #760/82. remedy: discontinue the illegal occupancy until
Apr 26, 1990 · Penalty $340
Resolve
Complaints
No HPD complaints in our records
Sales history
No recorded sales in our data
Building details
- Building type
- Office building (O6)
- Year built
- 1920
- Floors
- 9
- Residential units
- —
- Building area
- 31,105 ft²
- Lot area
- 5,021 ft²
- Zoning
- C1-9
- Community board
- 106
- Council district
- 4
- Block / lot
- 1327 / 35
- Assessed value
- $3,517,200
- Landmark / historic district
- No
Questions about 226 East 54 Street
Who owns 226 East 54 Street?
The owner of record in NYC Department of City Planning PLUTO data is Gemini Partners Realty LLC.
Does 226 East 54 Street have violations?
NYC HPD has no housing violations on record for this property.
Is 226 East 54 Street rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 226 East 54 Street built?
City records list 1920 as the year it was built.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.