1009 2 Avenue
Manhattan, NY 10022BBL 1-01327-0023Map
Owner of record: Lfl Partners, LLC
1009 2 Avenue is an elevator apartment building built in 2025 in Manhattan, 10022. It has 29 residential units across 19 floors. The owner of record is Lfl Partners, LLC. HPD has no housing violations on record for this property.
- HPD violations
- 0
- DOB violations
- 16
- ECB violations
- 64
- HPD complaints
- 0
What to know
No open immediately-hazardous violations among recent records.
HPD has not cited this building.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 0
No HPD violations on record
DOB building violations · 16
- Low pressure boiler boiler required
Violation issued-failure to file 2024 external low pressure inspection
Nov 14, 2025
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2023 external low pressure inspection
Sep 23, 2024
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2020 external low pressure inspection
Jun 30, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2021 external low pressure inspection
Jun 30, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2018 external low pressure inspection
Jun 20, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2019 external low pressure inspection
Jun 20, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2022 external low pressure inspection
Apr 25, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2017 inspection report
Nov 8, 2019
Dob violation - active - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Sep 19, 2019
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2016 inspection report
Apr 6, 2018
Dob violation - active
Show 6 more ↓
- Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2015 inspection report
Feb 24, 2017
Dob violation - active - Construction other optional
C-construction other optional
Jul 22, 2003
Dob violation - dismissed - Construction other optional
C-construction other optional
May 30, 2003
Dob violation - active - Construction other optional
C-construction other optional
May 30, 2003
Dob violation - dismissed - Construction other optional
C-construction other optional
Jan 17, 2003
Dob violation - active - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
May 4, 1998
Dob violation - dismissed
ECB violations · 64
- Class - 2
At time of inspection observed active suspended scaffolds. upon reviewing drawings notice it does conform. tie back shows to be at the rear of outrigger beam. option to be attached to the front of the outrigger
Aug 6, 2026
Resolve - Class - 2
At time of inspection observed active construction activities. notice inadequate fire extinguishers on multiple levels. extinguishers were store on ground and one on water. observed some without pressure and mi
Aug 6, 2026 · Penalty $2,500
Resolve - Class - 1
At time of inspection observed multiple location without adequate toe boards. on elevators shaft observed missing toe boards or not properly installed. toe boards should be 0 inches from slab, some toe boards o
Aug 6, 2026 · Penalty $5,000
Resolve - Class - 2
At time of inspection observed active suspended scaffolds. upon reviewing manufactures specs notices platform configuration does not conform for exp. a 6 meter platform config. is 2-2-2 but as per specs it shou
Aug 6, 2026 · Penalty $1,250
Resolve - Class - 1
At time of inspection observed at exp. 1 from 15 floor thru roof a ring lock system scaffold not shown on approved drawings. unable to verified compliance to design drawings. also observed sidewalk shed at expo
Aug 6, 2026 · Penalty $2,500
Resolve - Class - 2
At time of inspection observed supported scaffold not maintain in code complying manner. noticed materials and planks not secure to scaffold. on several location observed working platforms with no end rails mak
Aug 6, 2026 · Penalty $2,500
Resolve - Class - 2
At time of inspection observed active construction activities. upon requesting the load imposed letter for pipe scaffold on top of sidewalk shed it was not provided. temporary elevator certificate has expired a
Aug 6, 2026 · Penalty $1,250
Resolve - Class - 2
Observed bulkhead height is contrary to plans approved by dob. drawing #a201-00 indicates bulkhead height to be 9'-6" putting building height at 219'. i measured current bulkhead height to be approximately 17 1
Mar 13, 2026 · Penalty $1,250
Resolve - Class - 2
. during the inspection of the construction 19-story building, inadequate housekeeping was observed. debris at sidewalk shed, floors of the building debris and materials were left on the ground in a disorganize
Feb 11, 2026 · Penalty $1,250
Resolve - Class - 2
During the inspection of the construction 19-story new building, it was observed that the sws at exposure 1 was being used as storage for construction equipment. the excessive load on this structure may comprom
Feb 11, 2026 · Penalty $2,500
Resolve
Show 40 more ↓
- Class - 2
During the inspection of the construction 19-story new building, observed uncovered floor openings greater than 2" were observed. these openings present a significant risk of tripping and fall hazard and mater
Feb 11, 2026 · Penalty $1,250
Resolve - Class - 1
During inspection of the 19-story construction building, a worker on the 6th floor was observed using a grinder for hot work with no fire guard present. hot work requires a designated fire guard at all times to
Feb 11, 2026 · Penalty $2,500
Resolve - Class - 1
During inspection of the 19-story construction building, inadequate stair guardrails were observed at multiple locations, including incorrect heights, missing toe boards, and unsecured or improper netting. thes
Feb 11, 2026 · Penalty $2,500
Resolve - Class - 1
During inspection of the construction 19-story building, observed 160' high supported scaffolds at exposure# 1 upon request of daily inspection non was provided. maintain daily inspections/documents on site as
Feb 11, 2026 · Penalty $2,500
Resolve - Class - 1
During inspection of the construction 19-story building, observed vertical netting installed on building openings at exp 1,2 and 3 upon checking on their ssp, vertical nettings does not conform with approved si
Feb 11, 2026 · Penalty $2,500
Resolve - Class - 1
During the inspection of the construction 19-story new building, observed fire extinguishers expired. expired fire extinguishers creates hazards for workers on jobsite in case of fire emergency.provide and main
Feb 11, 2026 · Penalty $2,500
Resolve - Class - 2
Note: at time of inspection of an active construction site with ongoing concrete operations multiple portable fuel-fired heaters were observed in use beneath the concrete pouring deck. there was no escape hatch
Jan 27, 2026 · Penalty $2,500
Resolve - Class - 1
Note: at time of inspection, i observed ongoing concrete operations with missing the required alternate horizontal netting system as per 3308.6.1.4 from the 13 to the 15-floor working deck at expo# 1. increasin
Jan 27, 2026 · Penalty $5,000
Resolve - Class - 2
Note: at time of inspection on a active construction site, i observed ongoing concrete operations with fire hydrant in use without the required reduced pressure zone backflow prevention assembly as per 15 rcny
Jan 27, 2026
Resolve - Class - 1
Observed street areas in use, dot expired permits on 1-7-2026. permitholder failed comply 20-01 permits. all permits for work requiring opening or obstructing a street and/or sidewalk shall be contingent upon
Jan 8, 2026 · Penalty $2,500
Resolve - Class - 2
New 19 story building , noted upon inspection active site cs present , also noted supported scaffold has been erected on exposure 1 upon inspection noted missing toe board on different location creating hazards
Dec 26, 2025
Resolve - Class - 1
Failed to maintain backer scaffold as per code and manufacturer specifications. observed unsafe baker scaffold on 2nd floor stairs wheels not on stable surface no guardrails also been modified using loose unsui
Dec 18, 2025 · Penalty $2,500
Resolve - Class - 1
Failure to follow drawings for window protections of adjacent property at exposure 3. the drawing showing wire mesh to protect adjacent windows but the respondent didn't comply on 7 and 8 floors at exposure3.st
Dec 18, 2025 · Penalty $5,000
Resolve - Class - 2
Failure to comply with code requirement for 3307.4.7 work or storage zones. observed street storage area related to the construction adjacent to a sidewalk shed, and such area wasn't protected with a fence in c
Dec 18, 2025 · Penalty $2,400
Resolve - Class - 1
Failure to renew fire hydrant permit. observed the hydrant in use while permit was expired. in contrary with 20-01 permitsrenew permit
Dec 18, 2025 · Penalty $2,500
Resolve - Class - 1
At time of inspection of a proposed 19 stories building at 6 floor level i observed construction activities above adjacent building at exposure # 4 without roof protection to protect equipment on the roof and t
Dec 3, 2025 · Penalty $5,030
Resolve - Class - 2
Atoi observed expired permit m01241565-i1-el exp 10/01/2025 posted on construction fence. valid permit not posted, post/properly post permit
Dec 2, 2025
Resolve - Class - 2
At time of inspection, observed yodock barriers not interlocked and not filled with sand or water as required. this condition compromises barrier stability and poses a hazard to the public.
Dec 2, 2025 · Penalty $1,250
Resolve - Class - 2
Atoi observed expired permit m00267386-i1-pl exp 11/13/2025 posted on construction fence. no valid permit posted., post/properly post permit
Dec 2, 2025 · Penalty $150
Active - Class - 2
Atoi observed expired permit m01250601-i1-sh exp 10-18-2025 posted on constructon fence. valid permit not posted on site., post/properly post permit
Dec 2, 2025 · Penalty $300
Resolve - Class - 1
At time of inspection, materials were stored on top of the sidewalk shed, creating an overhead hazard and unsafe condition. this is contrary to bc 3307.6.4.2.2. approved plans do not indicate or permit any mate
Dec 2, 2025 · Penalty $5,000
Resolve - Class - 2
Failure to perform proper concrete washout procedures and collection and containment:as noted at time of inspection on a active constructionsite observed concrete pump truck onsite and worker washing street off
Aug 25, 2025 · Penalty $2,500
Resolve - Class - 1
During the excavation phase, i inspected a 19-story nb and observed exposed adjacent property walls that were not weatherproof bc 3309.9. this constitutes a danger to the structural integrity of the exposed adj
Jun 16, 2025 · Penalty $5,000
Resolve - Class - 2
At the time of my inspection of a 19-story nb, at the excavation phase, no downpour of rain. i observed standing accumulated water. 3303.14.2 drainage of excavations not provided. stop all foundation operations
Jun 16, 2025 · Penalty $5,000
Resolve - Class - 2
During my inspection of a major building. i observed the field office on roadway exposure 1. i ask to review the on-site approved ssp, no field office was located on the roadway as per the ssp provided. amend a
Jun 16, 2025
Resolve - Class - 2
Respondent failed to correct violating condition and file for a certificate of correction pursuant to ac 28-204.4 for violation no. 39535278z issued 12/20/2024. at time of inspection, i observed closed inactive
Feb 14, 2025 · Penalty $625
Resolve - Class - 2
Respondent failed to correct violating condition and file for a certificate of correction pursuant to ac 28-204.4 for violation no. 39535277r issued 12/20/2024. at time of inspection, i observed closed inactive
Feb 14, 2025
Resolve - Class - 1
Failure to remove all glass located in the area authorized to be demolished. observed windows and doors glasses remained in place after one story been demolished and the permit for full demolition in contrary w
Jan 29, 2025
Resolve - Class - 1
Observed pervious demolished work was performed without any protection for public. second floor at exposure one, partially demolished without sidewalk shed protection for the pedestrian. create an immediate haz
Jan 29, 2025
Resolve - Class - 1
3303.4 housekeeping.at time of inspection of a 2story building active jobsite demo work in progress i noticed inadequate housekeeping 1floor and basement large amount of debris this create unsafe situation for
Dec 20, 2024
Resolve - Class - 1
28-105.12.2 at time of inspection of a 2 story building active jobsite demo working in progress upon requestion demo plan for jobsite i noticed dob seal missing from plan code state all work shall conform to th
Dec 20, 2024 · Penalty $312
Resolve - Class - 1
At time of inspection 2story building active jobsite demo work in progress i noticed workers are using open holes on floor and staircase to remove debris and materials material shall be removed the by means of
Dec 20, 2024 · Penalty $5,000
Resolve - Class - 1
At time of inspection of a 2story active jobsite observed inadequate guards rail on 1 floor and 2floor inside building construction or demolition operation shall institute and maintain all safety measure requir
Dec 20, 2024 · Penalty $5,000
Resolve - Class - 2
Failure to comply w/commissioner's order contained in summons/v39004732r issued6/27/19 &to file c/c pursuant to28-201.1&1rcny102-01.comply w/commissioner's order &/or file c/c.
Jun 23, 2021
Resolve - Class - 2
Failure to comply with the commissioner's order contained in summons/violation#39004732r issued on 6/27/2019 and to file certificate of correction pursuant to 28-201.1 and 1rcny 102-01.failure to maintain build
Mar 1, 2021 · Penalty $3,125
Resolve - Class - 2
Failure to comply w/the comm's order contained in sum/vio#39004732r issued on 06/27/19 & to file a cert of correction pursaunt to 28-201.1 &1rcny 102-01. failure to maintain bldg in code compliant manner.
Aug 13, 2020 · Penalty $3,125
Resolve - Class - 2
Failure to comply w/the comm's order contained in summons/vio#39004732r issued on 06-27-19 & to file a c of c pursuant to 28-201.1 & 1rcny 102-01. remedy: comply w/comm's order &/or file a c of c.
Jan 31, 2020 · Penalty $1,250
Resolve - Class - 2
Failure to comply w/the comm's order contained in summons/vio#39004732r issued on 06-27-19 & to file a c of c pursuant to 28-201.1 & 1rcny 102-01. no c of c on file. remedy: comply w/comm's order &/or file a c
Dec 21, 2019 · Penalty $3,125
Resolve - Class - 2
Failure to comply with commissioners order to file a certificate of correction with the department of buildings for violation #39004732r, file a certificate of correction
Nov 22, 2019 · Penalty $3,125
Resolve - Class - 2
Failure to comply with the commissioners order contained in summons/violation#39004732r issued on 6/27/19 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01.no c/of/o on file.remedy:c
Oct 30, 2019 · Penalty $3,125
Resolve
Complaints
No HPD complaints in our records
Sales history
No recorded sales in our data
Building details
- Building type
- Elevator apartment building (D6)
- Year built
- 2025
- Floors
- 19
- Residential units
- 29
- Building area
- 47,717 ft²
- Lot area
- 3,524 ft²
- Zoning
- C1-9
- Community board
- 106
- Council district
- 4
- Block / lot
- 1327 / 23
- Assessed value
- $722,250
- Landmark / historic district
- No
Questions about 1009 2 Avenue
Who owns 1009 2 Avenue?
The owner of record in NYC Department of City Planning PLUTO data is Lfl Partners, LLC.
Does 1009 2 Avenue have violations?
NYC HPD has no housing violations on record for this property.
Is 1009 2 Avenue rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 1009 2 Avenue built?
City records list 2025 as the year it was built.
How many apartments are in 1009 2 Avenue?
It has 29 residential units and 30 units in total.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.