51 East 42 Street
Manhattan, NY 10017BBL 1-01277-0027Map
Owner of record: One Vanderbilt Owner LLC
51 East 42 Street is an office building built in 2017 in Manhattan, 10017. The owner of record is One Vanderbilt Owner LLC. HPD has no housing violations on record for this property.
- HPD violations
- 0
- DOB violations
- 126
- ECB violations
- 99
- HPD complaints
- 1
What to know
No open immediately-hazardous violations among recent records.
HPD has not cited this building.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 0
No HPD violations on record
DOB building violations · 126
- Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Oct 4, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2021 external low pressure inspection
Jun 30, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2021 external low pressure inspection
Jun 30, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2021 external low pressure inspection
Jun 30, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2021 external low pressure inspection
Jun 30, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2021 external low pressure inspection
Jun 30, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2021 external low pressure inspection
Jun 30, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2021 external low pressure inspection
Jun 30, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2021 external low pressure inspection
Jun 30, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2021 external low pressure inspection
Jun 30, 2023
Dob violation - dismissed
Show 40 more ↓
- Low pressure boiler boiler required
Violation issued-failure to file 2021 external low pressure inspection
Jun 30, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2021 external low pressure inspection
Jun 30, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2021 external low pressure inspection
Jun 30, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2022 external low pressure inspection
Apr 25, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2022 external low pressure inspection
Apr 25, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2022 external low pressure inspection
Apr 25, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2022 external low pressure inspection
Apr 25, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2022 external low pressure inspection
Apr 25, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2022 external low pressure inspection
Apr 25, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2022 external low pressure inspection
Apr 25, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2022 external low pressure inspection
Apr 25, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2022 external low pressure inspection
Apr 25, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2022 external low pressure inspection
Apr 25, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2022 external low pressure inspection
Apr 25, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2022 external low pressure inspection
Apr 25, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2022 external low pressure inspection
Apr 25, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2022 external low pressure inspection
Apr 25, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2022 external low pressure inspection
Apr 25, 2023
Dob violation - dismissed - Construction other optional
Structure rendered non-complaint. observed device # 1p0990467 also known as the observation elevator, the elevator drifted with 3 elevator personnel in it.
Mar 22, 2023
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Oct 12, 2022
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Oct 12, 2022
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Nov 30, 2021
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Nov 30, 2021
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Nov 29, 2021
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Nov 29, 2021
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Nov 29, 2021
Dob violation - resolved - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Nov 13, 2019
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Sep 4, 2019
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Sep 4, 2019
Dob violation - dismissed - Sprinkler none
Failed to file final sprinkler report by july 1, 2019
Sep 3, 2019
Dob violation - dismissed - Sprinkler none
Failed to file final sprinkler report by july 1, 2019
Sep 3, 2019
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Aug 22, 2019
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jun 26, 2019
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
May 16, 2019
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Mar 6, 2019
Dob violation - dismissed - Construction other optional
C-construction other optional
Feb 15, 2019
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Sep 5, 2018
Dob violation - dismissed - Construction other optional
C-construction other optional
Aug 6, 2018
Vp*-violation unserved ecb- dismissed - Construction other optional
C-construction other optional
Aug 6, 2018
Vp*-violation unserved ecb- dismissed - No report and / or late filing (facade) facade required
Failed to file fisp cycle 8b technical report by 02/21/2018
Jul 31, 2018
Dob violation - active
ECB violations · 99
- Class - 2
Failure to submit an acceptable required cycle 8b and 9b report of critical examination documenting condition of exterior wall and appurtenances required by 28-302.4 for control #904276. remedy: submit acceptab
Apr 11, 2024 · Penalty $1,250
Resolve - Class - 1
C/u;03i11,03i11,09i11,05i10,42x10,97x17:(03-i-11)cu,car enclosure walls damaged must be replaced (03-i-11)cu,car enclosure ceiling damaged must be replaced (09-i-11)cu,car floor damaged must be replaced (05-i-1
Mar 27, 2023 · Penalty $3,125
Resolve - Class - 1
Pending investigation
Mar 21, 2023
Resolve - Class - 2
Failure to submit an acceptable required cycle 8b report of critical examination documenting condition of exterior wall and appurtenances required by 28-302.4 for control#804276.rem:submit acceptable required t
Oct 19, 2022
Resolve - Class - 1
Failure to comply with manufacturers speciifcation note at the time of my inspection in repsonse to an incident where on eworker was moving scissors lift and his caught between lift and the wall he got bruised
Dec 21, 2020 · Penalty $2,500
Resolve - Class - 1
Bc3301.8.1-tampering with evidence note at the time of inspection in response to an incident where one injured his right hand when he was moving scissors is lift and his ahnd got stuck between lift and wall upo
Dec 21, 2020 · Penalty $2,500
Resolve - Class - 2
Failure to comply w/the commissioner's order contained in summons/violation #35474632k issued on 09/13/20 & to file a certificate of correction pursuant to 28-201.1 & 1rcny 102-01.failure to safeguard all perso
Nov 5, 2020
Resolve - Class - 1
Failure to safeguard all persons and property affected by constructionoperation.at the time of inspection at an active jobsite and responding to an incident observed at level 52 there was worker working without
Oct 19, 2020
Resolve - Class - 1
Failure to maintain @time of my inspection i observed the following(1) worker in lobby area working on ladder above with no fall protection/fall arrest visible or in use creating a hazardous condition-falling
Sep 13, 2020 · Penalty $2,500
Resolve - Class - 1
Bc330372-fire extinguishers inadequately maintained.noted:at time of my inspection of a new 59 storie building construction in progress,building almost topped off,i observed numerous fire extinguishers which we
May 12, 2020 · Penalty $250
Resolve
Show 40 more ↓
- Class - 1
Failure to institute/maintain safety equipment measures or temporary construction-guard rails.noted:at time of my inspection of a new 59 storie building,building close to top off construction on progress,i obse
May 12, 2020 · Penalty $625
Resolve - Class - 1
Failure to safe guard ice falling from the site was coming down hitting the debris sidewalk + streets. the ice also broke 2 skylights &(7) (atrium) window @335 madison ave.
Dec 22, 2019
Resolve - Class - 1
Work does not conform w/approved construction documents &/or amendments-2nd fl shoring sections. note: at time of inspection at a 59 sty nb,i observed on the ground level shoring on exp#1&2 corner that does not
Dec 6, 2019 · Penalty $625
Resolve - Class - 2
27-929.1 a.c. 27-929.1,failure to complete the installation of a full system of automatic sprinklers and file a final sprinkler report prepared by a registered design professional by 7/1/19,in an office buildin
Nov 15, 2019
Resolve - Class - 2
27-929.1 a.c. 27-929.1,failure to complete the installation of a full system of automatic sprinklers and file a final sprinkler report prepared by a registered design professional by 7/1/19,in an office buildin
Nov 15, 2019
Resolve - Class - 2
27-929.1 a.c. 27-929.1,failure to complete the installation of a full system of automatic sprinklers and file a final sprinkler report prepared by a registered design professional by 7/1/19,in an office buildin
Nov 15, 2019
Resolve - Class - 1
Lift director failed to perforn duties as required tower crane cn#1035/18 cd#4988 is erected and in operation at 10 vanderbilt ave upon request lift director edward meahan was unable to produce ny lift director
Jul 10, 2019 · Penalty $312
Resolve - Class - 1
Failure to notify the dept of an incident that resulted in an fatalityor injury a worker was injured got his finger crushed between a rails and a concrete floor slab. he was taken by ambulance to the hospital
Jun 11, 2019
Resolve - Class - 2
3301.2;safety measures and standard failure at the time of responding to an incident at a new building under construction of a workers fingers being injured by an elevator rail i observed area where worker was
Jun 11, 2019
Resolve - Class - 1
28-402.1:ssm performing duties with expired license at the time of responding to an incident at an active new building under construction fo an injured worker i observed the acting site safety manage on site ha
Jun 11, 2019 · Penalty $1,250
Resolve - Class - 1
Supervision or use of rigging equipment without a rigger's license. note: at the time of my inspection of a 67 story building at 62nd floor level. i observed outrigger beams and equipment being install for susp
Jun 4, 2019 · Penalty $5,030
Resolve - Class - 1
Work does not conform to approved construction documents and or approved amendments. note: at the time of my inspection i observed a turnstile erecred at exposure 3 for egress, turnstile was not provided with a
Jun 4, 2019 · Penalty $2,500
Resolve - Class - 1
At the time of inspection at the above address on the above date stripping operations were occuring on the 55th floor. during the operation a piece of form work had hit an worker in the foot. an ambulance was
Jun 3, 2019
Resolve - Class - 1
Failure to insitute/maintain safety equipment measures or temporary construction. note: follow up inspection to complaint where a worker was injured during stripping operation. at the time of my inspection whic
Jun 3, 2019
Resolve - Class - 1
Failure to notify the dept of an incident that resulted in a falaity or injury. during stripping formwork operation a worker was struck by apiece of formwork on the foot and injuring him. an ambulance was call
Jun 3, 2019
Resolve - Class - 1
Partial stop work all exterior work .note:@time of inspection a observed a black audi convertible winshield broken and a pice of const material lodged into dashboard vent, failure to protect public & property
May 8, 2019
Resolve - Class - 1
At time of inspection tower crane cd#5059 operating under cn#835/17 w/o a certificate of approval, certificate of operation expried on 0312012919. rmdy:obtain certificate of approval/operation.
Mar 21, 2019
Resolve - Class - 1
Failure to safeguard all persons and property affected by construction operations.at the time of inspection responding to an incident where a piece of plexi glass wedge between the mullion and glass of the
Mar 6, 2019
Resolve - Class - 1
Gc3308.9.1/safe condition.note:at my inspection of a 67 story building at 55 flr level construction work in progress.i observed safety netting systeem (diaper)use in conjunction with alternative horizontal nett
Feb 15, 2019 · Penalty $2,500
Resolve - Class - 2
3301.5 unsafe conditions and equipment. at time of inspection of 67 story new building ,temp stairs tower has burned holes thru steel tube supports at various locations and alterationto its structure
Feb 15, 2019
Resolve - Class - 2
Work without a permit. at time of inspection of 67 story new building under construction temporary stair tower erected without permit obtained. remedy: obtain permit.
Feb 15, 2019
Resolve - Class - 2
330.1.2 fire code fire extinguishers.a the time of inspectionof 67 story new buiding,fire extinguishers on several floors have been discharged and are not 3 feet of floor. not as per code. remedy:
Feb 15, 2019
Resolve - Class - 1
Bc3317.5 operation. note: at the time of my inspection of a 67 story building at 55 floor level construction work in progress. i observed amaterial hoist workhorse being use on 25th floor level at exp3 with a
Feb 15, 2019
Resolve - Class - 1
Failure to institute/maintain safety equipment measures and temporary construction equipment. note:at the time of my inspection of a 67 story building at 55 floor level construction work in progress, i observed
Feb 15, 2019 · Penalty $2,500
Resolve - Class - 1
Bc3310.8.6/reasonable prudence.note:at the time of inspction of a 67 story building at 55 flr level construction work in progress.i observedsite safety manager logs continue to note comply with ccd1 that was is
Feb 15, 2019 · Penalty $2,530
Resolve - Class - 1
3308.5 inadequate vertical safety netting .at the time of inspection 67 stories active site in response to complaint #1499846 observed inadequate vertical safety netting at 46th and 44th floors.the net an
Jan 23, 2019 · Penalty $2,500
Resolve - Class - 1
Bc3303.11 stairs during construction or demolition. note: at the time of my inspection of a 67 story building at 48th floor level (steel) 42 fl level walking deck, construction work in progress. i observed that
Dec 7, 2018 · Penalty $2,500
Resolve - Class - 2
Bc3308.3 safety netting design and documentation. note: at the time of my inspection of a 67 story building at 48th fl level construction work in progress. i observed both a full height netting system in place
Dec 7, 2018 · Penalty $1,250
Resolve - Class - 1
Bc3320.7 power buggies. note: at the time of my inspection of a 67 story building at 48th fl level construction work in progress. i observed concrete power buggies being used for concrete operation on 7th fl. u
Dec 7, 2018
Resolve - Class - 2
Work does not conform to approved construction documents and/or approved amendments. note: at the time of my inspection of a 67 story building at 48th fl level construction work in progress. i observed section
Dec 7, 2018 · Penalty $1,250
Resolve - Class - 2
Failure to institute and maintain safety equipment measures and temporary construction. note: at the time of my inspection of a 67 story building at 48th fl level construction work in progress. i observed a wor
Dec 7, 2018 · Penalty $5,000
Resolve - Class - 2
Failure to submit a required cycle 8b report of critical examination documenting condition of exterior wall and appurtenances required by 28-302.4 for control#804277. remedy: submit required technical report
Oct 15, 2018
Resolve - Class - 2
Failure to submit a required cycle 8b report of critical examination documenting condition of exterior wall and appurtenances required by 28-302.4 for control#804279. remedy: submit required technical report
Oct 15, 2018
Resolve - Class - 2
Failure to submit a required cycle 8b report of critical examination documenting condition of exterior wall and appurtenances required by 28-302.4 for control #804276. rmdy: submit required technical report.
Oct 15, 2018
Resolve - Class - 2
Operation of a crane/ derrick without a certificate of onsite inspection. crane cn (062/17) has expired and therefore the crane cd(4988) can not be in use., discontinue use, renew cn, and call cranes & derricks
Aug 8, 2018 · Penalty $625
Resolve - Class - 2
20180927
Aug 8, 2018
Resolve - Class - 1
Approved plans for construction(cocoon)at time of inspection of a 67 sty bldg currently at 28 sty & active,upon request to see cocoon plans,the plans present were fuzzy & no properly readable. failure to provid
Aug 6, 2018 · Penalty $250
Resolve - Class - 1
Sec. 3308.8.1 alteration netting system(daily inspeciton log book)at time of inspection of a 67 sty bldg currently at 28 sty decking,upon request for daily inspection,the one provided was inadequate. blank page
Aug 6, 2018 · Penalty $1,250
Resolve - Class - 1
Inadequate safety measures operation of a crane/derrick hoisting equipment is an unsade manner user of tower crane co#4988.cn#61207nyc constructions llc failed to provide the safety measures to protect iron wor
Jun 6, 2018
Resolve - Class - 1
Inadequate safety measures operation of crane operations john k schaffner,hmo #9227 around iron worker to climb over boomhead on the crane block suspended above building to change from two paints of height 1 pa
Jun 6, 2018 · Penalty $10,000
Resolve
Complaints
- Heat/hot water
Entire building
Jan 12, 2021 · Apt BLDG
Close
Sales history
No recorded sales in our data
Building details
- Building type
- Office building (O4)
- Year built
- 2017
- Floors
- 60
- Residential units
- —
- Building area
- 1,678,135 ft²
- Lot area
- 44,048 ft²
- Zoning
- C5-3
- Community board
- 105
- Council district
- 4
- Block / lot
- 1277 / 27
- Assessed value
- $604,668,150
- Landmark / historic district
- No
Questions about 51 East 42 Street
Who owns 51 East 42 Street?
The owner of record in NYC Department of City Planning PLUTO data is One Vanderbilt Owner LLC.
Does 51 East 42 Street have violations?
NYC HPD has no housing violations on record for this property.
Is 51 East 42 Street rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 51 East 42 Street built?
City records list 2017 as the year it was built.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.