roofy

10 West 55th Street

Manhattan, NY 10019BBL 1-01270-0044Map

Owner of record: 10 W 55 LLC

10 West 55th Street is an elevator apartment building built in 2024 in Manhattan, 10019. It has 97 residential units across 25 floors. The owner of record is 10 W 55 LLC. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
21
ECB violations
19
HPD complaints
0

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 21

  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    May 1, 2024

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued for failure to file annual boiler 2017 inspection report

    Nov 8, 2019

    Dob violation - dismissed
  • Elevator annual inspection / test elevatorrequired

    Violation issued to elevator - failure to file category 1 2017 inspection/test

    Apr 5, 2019

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued for failure to file annual boiler 2016 inspection report

    Apr 6, 2018

    Dob violation - dismissed
  • Elevator affirmation of correction elevatorrequired

    Vio issued to elevator - fail to correct defects on 2016 cat 1 insp/tst

    Jan 26, 2018

    Dob violation - dismissed
  • Elevator affirmation of correction elevatorrequired

    Vio issued to elevator - fail to correct defects on 2015 cat 1 insp/tst

    Jan 3, 2017

    Dob violation - dismissed
  • Residential elevator periodic inspection/test elevatorrequired

    Failure to perform category 5 inspection

    Jun 1, 2016

    Dob violation - dismissed
  • Elevator annual inspection / test elevatorrequired

    Violation issued to elevator-failure to file category 1 2014 inspection/test

    Jun 10, 2015

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued for failure to file annual boiler 2013 inspection report

    Mar 3, 2015

    Dob violation - dismissed
  • Elevator affirmation of correction elevatorrequired

    Vio issued to elevator - fail to correct defects on 2012 cat 1 insp/tst

    May 30, 2014

    Dob violation - dismissed
Show 11 more ↓
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Mar 29, 2013

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Nov 22, 2011

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Dec 22, 2010

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Aug 11, 2009

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    May 2, 2008

    Dob violation - resolved
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Jan 3, 2008

    Dob violation - dismissed
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jun 27, 2007

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jun 1, 2006

    Dob violation - resolved
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Feb 7, 2000

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Mar 18, 1993

    Dob violation - dismissed
  • Elevator elevatorrequired

    (51)perform 5 year test & tag governor

    Jul 20, 1988

    Dob violation - resolved

ECB violations · 19

  • Class - 1

    At time of inspection observed active construction site. at exposure 1 observed sidewalk shed installed contrary to approved drawings. drawings shows 4 large cross braces on detail of 10' high sws it only has 1

    Apr 16, 2025 · Penalty $2,500

    Resolve
  • Class - 2

    At time of inspection observed active construction activities. observed suspended scaffold platform 6 m. total length with walk-thru stirrups with 5'(1.5m) of cantilever as per specs only 3'(1m) is allowed. als

    Apr 16, 2025 · Penalty $1,250

    Resolve
  • Class - 2

    At time of inspection observed active suspended scaffolds on site. upon reviewing approved drawings observed setup on roof not as per drawings. drawings shows setup supported by concrete slab but on roof level

    Apr 16, 2025 · Penalty $1,250

    Resolve
  • Class - 2

    At time of inspection observed active construction site. upon inspecting monorail scaffold system observed setup resting on steel grid panels. on all drawings pages provided did not observed details of where sy

    Apr 16, 2025 · Penalty $1,250

    Resolve
  • Class - 1

    Incident occurred during one of plumber using a frame platform ladder due to failure to provide and maintain adequate housekeeping at working area materials, garbage, scarp and standing water on the way. respon

    Dec 2, 2024

    Resolve
  • Class - 2

    Upon inspection i observed and reviewed drawings for a sidewalk shed installed at exposure 1. installed shed did not match the drawings. no install details for the mid section appox 50ft of shed at expos 1. hor

    Nov 19, 2024

    Resolve
  • Class - 2

    Upon inspection i observed at construction fence installed at exposure 1 contrary to code 3307.7.3 viewing panels. i observed missing and panels with obstructed visual views installed. viewing panels shall be p

    Nov 19, 2024 · Penalty $1,000

    Resolve
  • Class - 2

    Work does not conform to approved construction documents or approved amendments. as noted, at time of inspection on an active construction site, 26 story new building concrete placement work at 24th floor level

    May 15, 2024

    Resolve
  • Class - 1

    Failure to obtain registered design professional evaluation prior to using existing structure to support concrete load. as noted, at time ofmy inspection at an active construction site 26 story new building obs

    May 15, 2024

    Resolve
  • Class - 1

    At time of inspection respond to an incident where a worker fell while carrying 10ft metal track .inspector observed standing water in the area where the worker fell .this created a slipping and fall hazard

    Feb 28, 2024 · Penalty $2,500

    Resolve
Show 9 more ↓
  • Class - 1

    At time of inspection on a nb 25 story at 11 level. inspector requested for the electrical air pressurized alarm system for dry standpipe systems a licensed electrician shall obtain all required electrical pe

    Feb 28, 2024 · Penalty $1,630

    Resolve
  • Class - 2

    Loose cement@flue@chimney/fresh air louver 1/2 clogged/opening@boiler room wall@gas meter/no outdoor air@gas meter/storage@gas meter/noise@start from gas burner motor/gas piolit not hard pipe@regulator/co detec

    Nov 4, 2022

    Resolve
  • Class - 2

    Failure to submit a required cycle 8b report of critical examination documenting condition of exterior walls & appurtenances required by 28-302.4 for control#804203. agg2 history of noncompliance on 37009263n,

    Oct 28, 2019 · Penalty $3,125

    Active
  • Class - 1

    Unlawful acts. failure to comply w/ an order of the commissioner. on 8/24/2015. two electrical violations was issue to the respondent,in 3/3/2016 the respondent find in violation & failed to comply w/ the local

    Apr 29, 2016 · Penalty $12,000

    Resolve
  • Class - 2

    Fail to file an acceptable tech report in compliance w/code provisions:nov #36026863p periodic inspection of exterior walls & appurtenances as req by dob.rem:file required report to dob.

    Nov 23, 2015 · Penalty $2,000

    Active
  • Class - 2

    67l10,42o02,68b07,71m07,70z09,16j01,16m07,10j10. 67l10-in car communication defective repair; 42o02-controller dirty clean; 68b07-maintenance control program insufficient,provide; 71m07-pit light missing;16m07-

    Apr 7, 2015 · Penalty $500

    Resolve
  • Class - 2

    Failure to comply w/the commissioner's order to file a c of c w/the dept of buildings for notice of violation #35095661j issued on 5/12/14 pursuant to 28-204.4 & 1rcny 102-01. for: erected full height partition

    Sep 9, 2014 · Penalty $4,000

    Resolve
  • Non-hazardous

    Failure to maintain plumbing and or appurtenances non-hazardous on right side in back of roof has section of leader line on that right side missing remedy: maintain plumbing and or appurtenances

    Dec 28, 1993 · Penalty $140

    Resolve
  • Non-hazardous

    73#, 05- perform 5 year test, properly tag device and file elev3 form

    Mar 18, 1992 · Penalty $75

    Resolve

Complaints

No HPD complaints in our records

Complaint data is still being backfilled from NYC Open Data.

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Elevator apartment building (D6)
Year built
2024
Floors
25
Residential units
97
Building area
141,409 ft²
Lot area
10,343 ft²
Zoning
C5-P
Community board
105
Council district
4
Block / lot
1270 / 44
Assessed value
$22,529,700
Landmark / historic district
No

Questions about 10 West 55th Street

Who owns 10 West 55th Street?

The owner of record in NYC Department of City Planning PLUTO data is 10 W 55 LLC.

Does 10 West 55th Street have violations?

NYC HPD has no housing violations on record for this property.

Is 10 West 55th Street rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 10 West 55th Street built?

City records list 2024 as the year it was built.

How many apartments are in 10 West 55th Street?

It has 97 residential units and 98 units in total.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.