433 West 53 Street
Manhattan, NY 10019BBL 1-01063-0051Map
Owner of record: 10524 Emmut Properties LLC
433 West 53 Street is an elevator apartment building built in 1963 in Manhattan, 10019. It has 60 residential units across 7 floors. The owner of record is 10524 Emmut Properties LLC. HPD has recorded 3 housing violations here, most recently on June 16, 2025.
- HPD violations
- 3
- DOB violations
- 54
- ECB violations
- 54
- HPD complaints
- 6
What to know
No open immediately-hazardous violations among recent records.
Date of the most recent HPD inspection that found a problem.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 3
- ANon-hazardous
File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.
Jun 16, 2025
Closed — Violation dismissed - ANon-hazardous
File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.
Apr 18, 2024
Closed — Violation dismissed - ANon-hazardous
File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.
Mar 10, 2022
Closed — Violation dismissed
DOB building violations · 54
- Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jun 26, 2019
Dob violation - dismissed - Elevator annual inspection / test elevatorrequired
Violation issued to elevator - failure to file category 1 2017 inspection/test
Apr 5, 2019
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Mar 6, 2019
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Mar 6, 2019
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Mar 6, 2019
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Mar 6, 2019
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Mar 6, 2019
Dob violation - dismissed - Construction other optional
C-construction other optional
Nov 27, 2018
Vp*-violation unserved ecb- dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Nov 14, 2018
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Nov 14, 2018
Dob violation - dismissed
Show 40 more ↓
- Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Sep 19, 2018
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Sep 19, 2018
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Aug 22, 2018
Dob violation - dismissed - Construction other optional
C-construction other optional
Aug 15, 2018
Vp*-violation unserved ecb- dismissed - Construction other optional
C-construction other optional
Aug 15, 2018
Vp*-violation unserved ecb- dismissed - Construction other optional
C-construction other optional
Aug 15, 2018
Vp*-violation unserved ecb- dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jul 11, 2018
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jul 11, 2018
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jul 11, 2018
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jun 27, 2018
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jun 27, 2018
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jun 13, 2018
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jun 13, 2018
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jun 13, 2018
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jun 13, 2018
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jun 13, 2018
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Apr 18, 2018
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Apr 18, 2018
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Apr 18, 2018
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Apr 18, 2018
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Apr 18, 2018
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Apr 18, 2018
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Feb 7, 2018
Dob violation - dismissed - Elevator affirmation of correction elevatorrequired
Vio issued to elevator - fail to correct defects on 2016 cat 1 insp/tst
Jan 26, 2018
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Nov 29, 2017
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Nov 29, 2017
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Nov 15, 2017
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Feb 20, 2017
Dob violation - resolved - Elevator annual inspection / test elevatorrequired
Violation issued to elevator-failure to file category 1 2015 inspection/test
Dec 1, 2016
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Feb 8, 2016
Dob violation - resolved - Elevator annual inspection / test elevatorrequired
Violation issued to elevator-failure to file category 1 2014 inspection/test
Jun 10, 2015
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Feb 22, 2012
Dob violation - resolved - Elevator annual inspection / test elevatorrequired
Violation issued to elevator-failure to file category 1 2010 inspection/test
Dec 13, 2011
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Jun 18, 2009
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Apr 16, 2008
Dob violation - resolved - Elevator elevatoroptional
Ll1081-local law 10/81 - elevator elevatoroptional
Mar 21, 2008
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Sep 21, 2005
Dob violation - resolved - Elevator elevatorrequired
1p26889
Jun 20, 2000
Dob violation - resolved - Elevator elevatoroptional
Ll1081-local law 10/81 - elevator elevatoroptional
Jan 20, 1999
Dob violation - dismissed - Elevator elevatoroptional
Ll1081-local law 10/81 - elevator elevatoroptional
May 31, 1994
Dob violation - dismissed
ECB violations · 54
- Class - 2
Permanent dwelling used/converted for other than permanent residentialpurposes. department of buildings records indicates premises to be legally approved as a class "a" multiple dwelling. illegal occupancy note
Aug 10, 2026 · Penalty $1,250
Active - Class - 1
B. c. 907.2.8. failure to provide a class "1" fire alarm system for transient use at unit 74 on the 7th floor. remedy: discontinue illegal occupancy.
Aug 10, 2026 · Penalty $2,500
Active - Class - 2
Failure to maintain adequate housekeeping as per section requirements.noted: at time of my inspection of a 7 sty new bldg,construction operations in progress,i observed garbage & construction material & debris
Apr 11, 2019
Resolve - Class - 1
Holes/openings not convered. noted: at time of my inspection of a new 7 sty bldg,construction operations in progress. i observed numerous holes/openings in the floors which were either missing or had inadequate
Apr 11, 2019
Resolve - Class - 1
At time of inspection at an active 7 story new building construction site, i observed rear building on/at 442 west 54 street did not erect adjoing properyt chimney at minimum requirement as per section 2113.1.
Apr 4, 2019 · Penalty $1,250
Resolve - Class - 1
Removed written posted stop work order.at time of posting of violations observed on 11/27/2018 i observed the stop work order which i postedon 11/27/2018 at the construction entrance on west 53 street had been
Nov 29, 2018
Resolve - Class - 1
Unlawfully continued work while on notice of stop work order.noted:at time of posting of violation observed on 11/27/18 i observed the stop work order sticker had been removed from front entry door upon enterin
Nov 29, 2018 · Penalty $5,000
Resolve - Class - 2
Failure to provide approved construction documents at time of inspection cd-s.at time of inspection of a 7 story building under constructioni observed a material hoist on the 54th side roof.upon request for a c
Nov 27, 2018
Resolve - Class - 1
Bc3314.1.supported scaffold do not meet code specifications.at time ofinspection i observed supported scaffold at exp 3 and exp 1 54 side withh the following problems.platforms not fully planked.-planks not tie
Nov 27, 2018 · Penalty $2,500
Resolve - Class - 1
Work does not conform to approved construction documents.at time of inspection i observed masonry pieces at exp #1 and #3 were built out of solid brick which does not conform to approved drawings.architectual a
Nov 27, 2018 · Penalty $2,500
Resolve
Show 40 more ↓
- Class - 1
Bc3303.7.2.fire extinguishers not maintained as per nyc fire code.at time of inspection of a new 7 story buildign under construction i observed multiple fire extinguishers throughout the jobsite with the follow
Nov 27, 2018 · Penalty $2,500
Resolve - Class - 1
3303.4.6-storage of combustible material and equipment.at the time of my inspection of an active job site.i observed 3 combustible gas tanks stored in the cellar on the ground contrary to fdny fire code.failur
Aug 15, 2018 · Penalty $2,500
Resolve - Class - 2
Failure to provide approved/accepted design document.at time of inspection at an active jobsite i observed concrete decoring formwork in progress at exp 3 support by shoring resting on ground at cellar level,up
Aug 15, 2018 · Penalty $250
Resolve - Class - 1
3301.1.2-note=at the time of my inspection of anactive job site, i observed 3 flammable compressed gas tanks improperly stored in the cellar.upon request for fdny permit for flammable compressed gas storage non
Aug 15, 2018 · Penalty $2,500
Resolve - Class - 1
Failure to safeguard all persons and property affected by constructionoperations.note:at time of inspection through investigation it was determined site failed to adequately control pedestrian traffic.pedestria
Jul 27, 2018
Resolve - Class - 1
Failure to provide sidewalk shed where required.note:at time of inspection i observed sidewalk shed in process of removal.site demolition incomplete at time of inspection.roof joist still in place and state to
Jul 27, 2018
Resolve - Class - 1
No design drawing. at the time of inspection observed active jobsite. platform have been constructed in 1st floor. no design drawing provided for inspection as required. (two locations). rmdy: stop all work at
May 30, 2018 · Penalty $625
Resolve - Class - 1
No guardrails. at the time of inspection observed active jobsite. some workers was working at jobsite. observed inadequate guardrails was provided at exposure 1 and 3, 5th, 6th,7th floors and some locations
May 30, 2018 · Penalty $2,500
Resolve - Class - 1
Housekeeping. at time of inspection observed active jobsite. debris and construction materials has not been maintained adequately as required. debris has been found along the perimeter edge outside the vertic
May 30, 2018 · Penalty $2,500
Resolve - Class - 2
Project info panel. at the time of inspection observed active job site. observed no project information and was not posted on teh fence at a height of 4'above the ground failure maintain project info panel
May 30, 2018 · Penalty $625
Resolve - Class - 2
Vertical safety netting system. at the time of inspection observed active jobsite. some workers was working at jobsite. inadequate vertical safety netting has been found on 3rd, 5th and 6th floor and some loca
May 30, 2018 · Penalty $625
Resolve - Class - 1
Sec. 3305.3.6.1.2 reshores in proximity to enclosed perimeters. at time of inspection of new 7 sty bldg i observed reshores on leading edge at exp#1 & 3 at 3rd sty & up not secured as required. failure to secur
Apr 21, 2018 · Penalty $625
Resolve - Class - 2
Sec. 3301.2 signs. at time of inspection of new 7 sty bldg active jobsite i observed inadequate & missing exit signs & floor signs throughout jobsite. remedy: provide/maintain adequate signs.
Apr 21, 2018 · Penalty $625
Resolve - Class - 1
Sec. 3301.4 inspection at time of my inspection of a new 7 sty bldg atroof level construction work in progress. i observed concrete embeddedsafety straps installed 2nd sty & up. upon request for inspection logs
Apr 21, 2018 · Penalty $250
Resolve - Class - 1
Sec. 3306.9.12.1 removal of material at time of inspection of new 7 sty bldg active job site i observed at 1st sty debris being removed fromfloors above via a hole opening in the ceiling. i also observed the ar
Apr 21, 2018 · Penalty $2,500
Resolve - Class - 1
No competent person. @ time of insp of new 7 story bldg on active jobsite, no superintendent present on site. i asked if there was an assigned competent person on site & no competent person assigned was present
Mar 29, 2018
Resolve - Class - 1
No designated super on site as required per code. @ time of insp of an active jobsite, observed no super was present & no log sheet for the day in the log book. upon further review of the log book, 1 found seve
Mar 28, 2018 · Penalty $1,250
Resolve - Class - 2
Construction superintendent upon review if the daily jobsite log book at time of inspection i observed missing information i.e. jobsite address,areas & floors inspected for hazards conditions. designated compan
Mar 22, 2018 · Penalty $5,000
Resolve - Class - 1
No roof protection. at time of inspection of new bldg under construction i observed no roof protection at occupied bldg at exp#2 framing,(dgcking)& cmu block wall along perimeter of exp#2 is approx 9' above roo
Mar 22, 2018 · Penalty $12,500
Resolve - Class - 1
No drawings pipe scaffold. at time of inspection of new bldg under construction bldg at the 6th fl level. i observed pipe scaffold at exp#1&3 erecvted 40'. upon request for approved drawings none were provided
Mar 22, 2018 · Penalty $6,250
Resolve - Class - 1
Sec. 3314.4.5.2 scaffold user at the the time of inspection of new bldg under construction i observed workers on pipe scaffold at exp#3. upon request for dept approved training program card none was provided or
Mar 22, 2018 · Penalty $6,250
Resolve - Class - 2
Sec. 3307.6 sidewalk shed. at time of inspection of new bldg under construciton-work at the 6th fl level, i observed that the sidewalk shed located at exp#1 had a light bulb that was not illuminated,upon reques
Mar 22, 2018 · Penalty $3,125
Resolve - Class - 2
Sec. 3301.2 guardrails. at the time of inspection i observed that the guardrails provided at floors 2-6 at perimeters of exp#1&3 had no top rails at 60" as required by code perimeter openings at these exposures
Mar 22, 2018 · Penalty $3,125
Resolve - Class - 2
No design drawing. at the time of inspection of new bldg under construction i observed temporary platforms at the elevator shafts on floors 2-6. platforms on several floors had construciton debris & material
Mar 22, 2018 · Penalty $3,125
Resolve - Class - 1
No temporary handrails. at the time of inspection of new bldg under construciton i observed no handrails at the stairway leading from the 5th to the 6th fl. this creates a hazardous condition(i.6)nothing to hol
Mar 22, 2018 · Penalty $3,125
Resolve - Class - 1
Sec. 3301.1.2 no fire guard. at the time of inspection of new bldg under construction i observed 2 workers (tac) welding angle iron beam at exp#3 at the 2nd floor level. i observed sparks from welding operation
Mar 22, 2018 · Penalty $6,250
Resolve - Class - 1
Failure to designate and/or have construction superintendent present at site when required. at time of inspection of a new 7story building under construction at 3rd floor level, active job site, upon request
Jan 22, 2018 · Penalty $10,000
Resolve - Class - 1
Bc 3304.4.4. failure to provide 3'6" guardrail system or solid enclosure around open and accessible sides of excavation. at time of inspec tion of a new 7story bldg at 3rd floor level under construction active
Jan 22, 2018 · Penalty $1,600
Resolve - Class - 1
Failure to safeguard all persons affected by construction operations-lack of egress. at time of inspection of a new 7story bldg under construction at 3rd floor level, active jobsite, i observed that the only
Jan 22, 2018 · Penalty $10,000
Resolve - Class - 1
Failure to safeguard all persons and property affected by constructionoperation-no overhead protection. at time of inspection of a new 7story bldg under construction at 3rd floor level, active job site, i obser
Jan 22, 2018 · Penalty $10,000
Resolve - Class - 1
Bc3313.1 and bc 3301.1.2 failure to comply with nyc fire code-general no perit for oxygen, acetylene-storage/use o job site. at time of inspection of this active jobsite i observed that there were oxygen/acetyl
Jan 22, 2018
Resolve - Class - 1
Construction superintendent failed to prform duties as per rule.the following violating hazardous conditions were observed on this date and stop work order issued; 1-inadequate job site logs; 2-no superint
Jan 22, 2018 · Penalty $10,000
Resolve - Class - 2
Construction superintendent falls to adequately maintain and/or make job site logs available. at time of inspection of a new 7story bldg under construction at 3rd flr level, active job site, upon request for th
Jan 22, 2018 · Penalty $2,000
Resolve - Class - 1
Sec: bc 3307.3.2. failure to provide job site fence as required- no viewing panels provided. @ time of insp of a new 7 story bldg @ excavation stage, no work in progress, observed that there were no viewing pan
Nov 13, 2017 · Penalty $800
Resolve - Class - 1
Sec: bc 3306.5.1. the respondent failed to meet minimum requirements set forth in bc 3306.5.1, mandates demolition drawings to have plans,sections,details properly showing the sequence,means & methods of the de
Aug 30, 2017 · Penalty $1,600
Resolve - Class - 1
Sec. 3306.5.1 the respondent failed to meet minimum requirements set 4th in bc 3306.5.1 bc 3306.5.1 mandates demolition dwgs to have plans,sections & details properly showing in the sequence;means & methods of
Aug 30, 2017
Resolve - Class - 3
Work does not conform to approved construction documents &/or amendments. at the time of inspection,an existing wall along west 53rd st was found left in place & not demolished while non conforming excavation
Aug 30, 2017 · Penalty $100
Resolve - Class - 2
Construction superintendent failed to perform duties per rules.at timeof inspection observed an active construction site with foundation work in progress.during inspection noted that the construction superinten
Aug 21, 2017 · Penalty $800
Resolve - Non-hazardous
40t07 40-elevator machine room door is without signage indicate "elvevator machine room
May 18, 2004 · Penalty $180
Resolve - Non-hazardous
64l10 38l10 28q03 25d06 39o02 41p16 60b07 64-repair work light 38-repair work light 35-secure escape cower or call dept 39-clear hoist way room 41-provide rooms to right controller 39-remove stored materials
Jul 29, 2003
Resolve
Complaints
- Plumbing
Toilet
Aug 22, 2026 · Apt 11
Close - Water leak
Heavy flow
Feb 13, 2026 · Apt 12
Close - Plumbing
Water supply
Mar 29, 2025 · Apt 5C
Close - Heat/hot water
Apartment only
Jan 18, 2024 · Apt 62
Close - Heat/hot water
Apartment only
Jan 12, 2024 · Apt 62
Close - Unsanitary condition
Mold
Jun 29, 2023 · Apt MULTIP
Close
Sales history
No recorded sales in our data
Building details
- Building type
- Elevator apartment building (D3)
- Year built
- 1963
- Floors
- 7
- Residential units
- 60
- Building area
- 41,617 ft²
- Lot area
- 10,042 ft²
- Zoning
- C6-2
- Community board
- 104
- Council district
- 3
- Block / lot
- 1063 / 51
- Assessed value
- $5,737,950
- Landmark / historic district
- No
HPD registration #144938, last renewed Oct 17, 2025.
Questions about 433 West 53 Street
Who owns 433 West 53 Street?
The owner of record in NYC Department of City Planning PLUTO data is 10524 Emmut Properties LLC.
Does 433 West 53 Street have violations?
Yes. NYC HPD has recorded 3 housing violations at this property.
Is 433 West 53 Street rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 433 West 53 Street built?
City records list 1963 as the year it was built.
How many apartments are in 433 West 53 Street?
It has 60 residential units.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.