4 West 37 Street
Manhattan, NY 10018BBL 1-00838-0054Map
Owner of record: 4 West 37th Street LLC
4 West 37 Street is a hotel built in 2017 in Manhattan, 10018. The owner of record is 4 West 37th Street LLC. HPD has no housing violations on record for this property.
- HPD violations
- 0
- DOB violations
- 49
- ECB violations
- 57
- HPD complaints
- 2
What to know
No open immediately-hazardous violations among recent records.
HPD has not cited this building.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 0
No HPD violations on record
DOB building violations · 49
- Low pressure boiler boiler required
Violation issued-failure to file 2020 external low pressure inspection
Jun 30, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2020 external low pressure inspection
Jun 30, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2018 external low pressure inspection
Jun 20, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2018 external low pressure inspection
Jun 20, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2019 external low pressure inspection
Jun 20, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2019 external low pressure inspection
Jun 20, 2023
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Aug 25, 2021
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Aug 25, 2021
Dob violation - resolved - Failure to benchmark none
Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4
Feb 2, 2020
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jan 9, 2020
Dob violation - dismissed
Show 39 more ↓
- Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2017 inspection report
Nov 8, 2019
Dob violation - dismissed - Failure to benchmark none
Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4
Nov 2, 2019
Dob violation - dismissed - Failure to benchmark none
Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4
Aug 2, 2019
Dob violation - dismissed - Failure to benchmark none
Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4
May 2, 2019
Dob violation - dismissed - Elevator annual inspection / test elevatorrequired
Violation issued to elevator - failure to file category 1 2017 inspection/test
Apr 5, 2019
Dob violation - dismissed - Failure to benchmark none
Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4
Feb 16, 2019
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Sep 10, 2018
Dob violation - resolved - Construction other optional
C-construction other optional
Aug 27, 2018
Vp*-violation unserved ecb- dismissed - Construction other optional
C-construction other optional
Aug 27, 2018
Vp*-violation unserved ecb- dismissed - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2016 inspection report
Apr 6, 2018
Dob violation - dismissed - Plumbing none
The borough commissioner has issued a notice of immediate stop work order due to applicant withdrawal of job #140368858 as of 01/11/18
Jan 16, 2018
Dob violation - dismissed - Elevator annual inspection / test elevatorrequired
Violation issued to elevator-failure to file category 1 2016 inspection/test
Sep 15, 2017
Dob violation - dismissed - Construction other optional
C-construction other optional
Aug 3, 2017
Vp*-violation unserved ecb- dismissed - Elevator affirmation of correction elevatorrequired
Vio issued to elevator - fail to correct defects on 2015 cat 1 insp/tst
Jan 3, 2017
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Oct 19, 2016
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Sep 8, 2016
Dob violation - resolved - Construction other optional
C-construction other optional
Jul 21, 2016
Vp*-violation unserved ecb- dismissed - Construction other optional
C-construction other optional
Jul 21, 2016
Vpw*-violation unserved ecb-work without permit-dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jul 13, 2016
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jul 13, 2016
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Jul 28, 2014
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Apr 3, 2012
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Dec 9, 2010
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
May 17, 2010
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Aug 12, 2009
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Feb 18, 2008
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Apr 10, 2007
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jun 20, 2006
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jun 14, 2006
Dob violation - active - Elevator elevatorrequired
E-elevator elevatorrequired
Sep 9, 2005
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Aug 11, 2004
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jan 13, 2004
Dob violation - resolved - Elevator elevatorrequired
1p6114
Aug 6, 2001
Dob violation - resolved - Elevator elevatorrequired
1p6114
Aug 6, 2001
Dob violation - resolved - Elevator elevatorrequired
1p6114
Mar 13, 2000
Dob violation - resolved - Construction other optional
C-construction other optional
Apr 17, 1997
Vpw-violation unserved ecb-work without permit-active - Construction other optional
C-construction other optional
Apr 17, 1997
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Mar 18, 1993
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Jun 7, 1990
Dob violation - resolved
ECB violations · 57
- Class - 2
Missing shut off valve at the tank as per 1307.1 missing fusible link valve in supply pipe at the wall of the generator room as per 1305.3.4 bottom of vertical shaft must be enclosed and drain into leak detecti
Mar 10, 2021
Resolve - Class - 1
Failure to comply with manufacture specifications on an nb active job site i observed yodock barriers an the street was not y2 full as required by manufacturer specks.remedy:comply with specifications.
Feb 27, 2020 · Penalty $2,500
Resolve - Class - 1
Failure to maintain adequate housekeeping per section requirements.at time of my inspection on an nb at 23 floor,i observed large amounts ofdebris on 1st floor at expo#1 creating a tripping hazard for person an
Feb 27, 2020 · Penalty $2,500
Resolve - Class - 2
Bc33016-design,sizes,and capacity of materials,structures,temporary constructoin,and equipment.at the time of inspection of a propose 23 story new bulding,i observed at exposure one,erected steel beams with woo
Jan 29, 2020 · Penalty $1,250
Resolve - Class - 1
Bc33141010-support devices(c-hooks)at time of inspection of a propose 23 story new building i observed on the roof of exposure 3,suspended scaffolds supported by c-hooks on the parapet walls the c-hooks had no
Jan 29, 2020 · Penalty $6,250
Resolve - Class - 2
At time of inspecoitn of a propose 23 story new building,i observed when requested approve drawings with footing details,non were provided.drawings provided did not show step footing.remedy:provide approve draw
Jan 29, 2020
Resolve - Class - 1
Failure to provide/miantain the required documents (no cd-5) at the tim eof inspection on an actiev jobsite of a 24 story building i observed on teh roof top level a set of outrigger beams supporting a suspende
Nov 20, 2019 · Penalty $625
Resolve - Class - 1
Failure to fiel evidence of compliance with workers comp law and or disbility benefits law(expired disbiloty) at the time of my inspection on an active job site of a 24 story building i observed workers on site
Nov 20, 2019 · Penalty $5,000
Resolve - Class - 1
Inadequate safety measures:open hoisting equipment in unsafe manner at the tim fo my inspection on an atciev jobsite 02 a 24 story building i observed 2 sets of suspended scaffold installed on the parapit walls
Nov 20, 2019
Resolve - Class - 1
Work contrary to plan(heavy duty sidewalk shed)at the time of the inspection of an active job site for which a site safety manager is required,i observed that the sidewalk shed did not conform with the drawings
Nov 13, 2019 · Penalty $2,500
Resolve
Show 40 more ↓
- Class - 2
Storage of material on overhead protection.at the time of the inspection of an active job site for which a site safety manager is required,iobserved materials and cmu's on the overhead protection at exposure 3.
Nov 13, 2019
Resolve - Class - 1
Failure to institute/maintain safety equipment measures or temporary construction-no guardrails. at time of my inspection of 24 sty blkdg i observed employee climing down from 2nd fl roof to top of 6' baker sca
Oct 2, 2019 · Penalty $2,500
Resolve - Class - 1
Sec. 3301.1.3 use of equipment not to manufactures specifications/ladders at time of my inspection of 24 sty bldg,i observed the following an employee straddle on top of step ladder reaching abovce his head ins
Oct 2, 2019
Resolve - Class - 1
Failure to maintain adequate housekeeping per section requirements. at time of my inspection of 24 sty bldg i observed the following-debris pile 6'in some places,materials stock piled in numerous rooms-hazardou
Oct 2, 2019 · Penalty $625
Resolve - Class - 1
Unsafe storage of materials during construction at time of my inspection of 24 sty bldg,i observed conduit wheels not checked to prevent rolling off bldg-loose materials stored closer than 5ft from edge of bldg
Oct 2, 2019 · Penalty $2,500
Resolve - Class - 1
Failure to provide unobstructed exit passageway. at time of inspectionof 24 sty bldg,i observed egress blocked by sheetrock,pipes & debris. creates the hazard at unobstructed exit of bldg in case of emergency
Oct 2, 2019 · Penalty $312
Resolve - Class - 1
3307.6.5.8-periodic inspection.at the time of inspection of an active job site.i observed sidewalk shed erected at exposure one.upon requestfor periodic inspection report, non was provided sidewalk shed shall
Aug 27, 2018 · Penalty $2,500
Resolve - Class - 1
3301.2 failure to institute and maintain safety measures covering holes. at time of inspection on an active jobsite holes greater than 2" upto 2ft were not covered or covers were not fastened adequately through
Aug 27, 2018 · Penalty $2,500
Resolve - Class - 1
3318.3 no valid permit for material (hoist) at time of inspection on an active site. no valid inspection permit was present for personnel hoist at exp 3. failure to inspect hoist creates a hazard or mechanical
Aug 27, 2018
Resolve - Class - 2
Bc3303.3.watchperson not present.at time of inspection i walked into the worksite,i observed generator running,site door was open/unlocked, i walked the perimeter and the first three stories of the site,no one,
Jul 7, 2018
Resolve - Class - 1
Unsafe storage of materials during construction or demo as noted @ time of insp 21 story nb, active site observed different types of materials (wood,alum,construction materials,woods) are stored w/in 10ft (most
May 30, 2018 · Penalty $2,500
Resolve - Class - 1
Work does not conform to approved construction documents and/or approved amendments. note: at the time of my inspection of a 23 story building at 16th floor level, i observed existing site condition does not re
Apr 12, 2018 · Penalty $625
Resolve - Class - 1
Housekeeping. note: at time of my inspection of a 23 story building at 16th floor level, construction work in progress. i observed multiple areas at exposure 1 and 3 from 2nd to 13th floor consumed with debris
Apr 12, 2018 · Penalty $2,500
Resolve - Class - 1
Bc3305.3.6.1 reshores limitations. note: at the time of my inspection of a 23 story building at 16th floor level, construction work in progress. i observed reshores at exposure 1 and 3 from 11th to 13th floor w
Apr 12, 2018 · Penalty $2,500
Resolve - Class - 1
Bc3309.10 protection of roofs. note: at the time of my inspection of a 23 story building at 16th floor level, construction work in progress. i observed that there was no protection provided for parapet at roof
Apr 12, 2018 · Penalty $625
Resolve - Class - 2
Failure to institute and maintain safety equipment measures and temporary construction. note: at the time of my inspection of a 23 story building at 16th floor level, construction work in progress. i observed t
Apr 12, 2018 · Penalty $5,000
Resolve - Class - 1
Bc3301.6 design, sizes and capacity of material, structures, temporary construction and equipment. note: at the time of my inspection of a 23 story building at 16th floor level, construction work in progress. i
Apr 12, 2018 · Penalty $625
Resolve - Class - 1
Bc3307.4 warning signs, personnel and barriers. note: at the time of my inspection of a 23 story building at 16th floor level construction work in progress. i observed debris removal operation being conducted a
Apr 12, 2018 · Penalty $625
Resolve - Class - 2
Failure to provide approved(demo)plans.at time of inspection i observed that demolition work(removal of bricks)was ongoing at expo#4 site safely manager could not provide demo plans for the removal of bricks.re
Aug 18, 2017 · Penalty $250
Resolve - Class - 2
Bc3309.9/failure to waterproof adjoining wall of building during construction or demolition operations.at the time of inspection i observed at expo#4 no water proofing was done on the wall against seep into adj
Aug 18, 2017 · Penalty $400
Resolve - Class - 2
Failure to safeguard:@ time of inspection of an incident of a worker being injured during rebar delivery operations of a proposed 22 story new bldg @ cellar phase.i ask for a pre task rebar delivery operation i
Aug 3, 2017 · Penalty $5,000
Resolve - Class - 1
Work does not conform to approved plans or approved documents.at the time of inspection i did observe that the excavation at exposure #3 is not in accordance to aproved plans.engineer need to provide shoring de
Mar 21, 2017 · Penalty $1,000
Resolve - Class - 1
Work doesn't conform to approved construction documents or approved amendments @time of inspection noted that the basement of jobsite was locked w.debris approx 8'ht &approx 30long by 10'wide the plans show no
Jul 21, 2016 · Penalty $1,000
Resolve - Class - 1
Failure to maintain safety equipment measures @(term property)construction no guardrail system.@time of inspection noted that there was no guard rail system @expo#3 &@ opening by the staircase.(pstewtial)for wo
Jul 21, 2016 · Penalty $1,200
Resolve - Class - 1
Failure to maintain saftey equipment measures or temporary construction no guardrail system.@time of inspection noted that @3rd flr level ofjob work on going removal of flr joist there were workers @ unprotecte
Jul 21, 2016 · Penalty $1,200
Resolve - Class - 1
3301.6.1 design whenever design is specifically required by provitionsof this chapter such design shall be in accordance w.the requirement of his code executed by a registered professional w. seal&signature.@ti
Jul 21, 2016 · Penalty $250
Resolve - Class - 1
Work doesn't conform to approved construction documents or approved amendments @time of inspection noted@ basement level of job debris loaded approx 8'x30long &approx 10'wide the plans call to removal of debris
Jul 21, 2016 · Penalty $1,000
Resolve - Class - 1
3309.1 protection required adjoining property public including person (theron sanel).be protected than damage &injury during construction ordemolition.@time of inspection noted @exp#2 of jobsite adjoining prope
Jul 21, 2016
Resolve - Class - 1
Failure to safeguard all persons&property affected by construction operations.@time of inspection noted workers removing debris from a demolition site @exp#1 where demo continue was @the street,there was no pro
Jul 21, 2016 · Penalty $10,000
Resolve - Class - 1
3314.4.3.2.1 partial *swo* installation inspection report:not provided.note:active demo stie, 5th fl.demo in progress.@exp #1 and 3 there is a supported scaffold in place approx 50'h.obs material and equip on s
Apr 21, 2016 · Penalty $1,600
Resolve - Class - 2
Sec. 3301.1.1 responsibility for safety: obstructed egress. note: active demolition site. at the ground floor the main in/egress for workerson site is obstructed by large room of bricks/debris equipment in/egre
Apr 21, 2016
Resolve - Class - 2
3301.1.1 responsibility for safety:obstructed egress.note:activie demo site.@ground floor the main in/egress for workers on sit is obstructed by large amt of bricks/debris,equipment.in/egress shall be maintaine
Apr 21, 2016
Resolve - Class - 1
3301.2 full *swo* safety measures and standards.note:active demo jobsite.demo in progress.5th fl.the adjoining property @exp #3 deos not have overhead protection in place as per approved demo plan causing immed
Apr 21, 2016 · Penalty $1,600
Resolve - Class - 1
(1 rcny 48) failure to adequately supervide work @ a const. site. so as to maintain a safe cont. site & ensure compliance w/ approved const.documents & chapter 33 (safeguard during const. & demo) the following
Apr 21, 2016 · Penalty $1,600
Resolve - Class - 1
3301.2 full *swo* safety measures and standards.note:active demo jobsit,demo in progress @6th flleading to 5th fl.the adjoining property @exp #3 deos not have overhead protection in place causing immediate haza
Apr 21, 2016 · Penalty $1,600
Resolve - Class - 2
Work does not conform to approved const. documents and/or approved amendments.note:demo jobsit,demo in progress @6h fl.the chute that is being used is contrary to design/details in approved demo plans.chute is
Apr 21, 2016 · Penalty $250
Resolve - Class - 2
Partial *swo* work does not conform to approved const. documents and/or approved amendments.note:demo jobsite,demo in progress @6th fl.the chute that is being used is contrary to plans.it is not sealed fl-ceili
Apr 21, 2016 · Penalty $250
Resolve - Class - 1
3314.4.3.2.1 partial*swo*installation inspection report:not provided.note:active demo site @5th fl.demo in progress.@exp #1 and 3 there is a supportd scaffold in place approx 50'h.obs material equp on scaffold
Apr 21, 2016 · Penalty $1,600
Resolve - Class - 2
3306.9.8.3 glass:not removed completely.note:active demo site,demo in progress @5th fl.@ex #3 there is galss that has not been removed prior to demo.glass in place @various floors 4-2.rem:remove all glass prior
Apr 21, 2016
Resolve - Class - 2
Sec. 3306.9.8.3 glass: not removed complete. note: active demolition jobsite,(demo)in progress at 5th fl. at exp#3 there is glass that was not removed as per code prior to(demo). glass in place at exp#3 at vari
Apr 21, 2016
Resolve
Complaints
- Unsanitary condition
Pests
Jan 28, 2026 · Apt HOTELR
Close - Unsanitary condition
Pests
Nov 13, 2025 · Apt THEDRA
Close
Sales history
No recorded sales in our data
Building details
- Building type
- Hotel (H2)
- Year built
- 2017
- Floors
- 22
- Residential units
- —
- Building area
- 56,572 ft²
- Lot area
- 4,246 ft²
- Zoning
- M1-9A/R12
- Community board
- 105
- Council district
- 4
- Block / lot
- 838 / 54
- Assessed value
- $12,290,850
- Landmark / historic district
- No
HPD registration #145157, last renewed Jul 14, 2025.
Questions about 4 West 37 Street
Who owns 4 West 37 Street?
The owner of record in NYC Department of City Planning PLUTO data is 4 West 37th Street LLC.
Does 4 West 37 Street have violations?
NYC HPD has no housing violations on record for this property.
Is 4 West 37 Street rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 4 West 37 Street built?
City records list 2017 as the year it was built.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.