46 West 21 Street
Manhattan, NY 10010BBL 1-00822-0066Map
Owner of record: Redleaf Capital LLC
46 West 21 Street is a mixed residential and retail building built in 1860 in Manhattan, 10010. It has 4 residential units across 5 floors. The owner of record is Redleaf Capital LLC. HPD has recorded 1 housing violation here, most recently on November 2, 2022.
- HPD violations
- 1
- DOB violations
- 13
- ECB violations
- 30
- HPD complaints
- 2
What to know
No open immediately-hazardous violations among recent records.
Date of the most recent HPD inspection that found a problem.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 1
- IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Nov 2, 2022
Closed — Violation dismissed
DOB building violations · 13
- Low pressure boiler boiler required
Violation issued-failure to file 2021 external low pressure inspection
Jun 30, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2022 external low pressure inspection
Apr 25, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2022 external low pressure inspection
Apr 25, 2023
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Aug 6, 2021
Dob violation - resolved - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Sep 9, 2015
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Aug 26, 2015
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Aug 26, 2015
Dob violation - dismissed - Construction other optional
C-construction other optional
Apr 17, 2015
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2010 inspection report
Dec 13, 2011
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Jan 31, 2005
Dob violation - dismissed
Show 3 more ↓
- Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Mar 26, 2002
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
May 4, 1998
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Sep 1, 1994
Dob violation - dismissed
ECB violations · 30
- Class - 1
Permit holder failed to ensure that each construction or demolition worker working/engaged at the site successfully completed the required training under bc 3321.1 & has an osha 30 card that was issued ib the
Sep 21, 2020
Resolve - Class - 1
Owner failed to ensure that each construction or demolition worker working/engaged at the site successfully completed the required training under bc 3321.1 & has an sst card,limited sst card,temporary sst super
Sep 21, 2020
Resolve - Class - 2
Pedestrian protection does not meet code specifications. at time of inspection on an active jobsite 5 sty alteration. i observed a sidewalk shed installed at exp#1. i asked the competent person for the daily
Aug 24, 2020 · Penalty $625
Resolve - Class - 1
Ac 28-204.1.1 owner failed to ensure that each construction or demolition worker working/engaged at the site successfully completed the required training under bc 3321.1 and has an osha 30 card that was issued
Mar 24, 2020 · Penalty $1,250
Resolve - Class - 1
Ac 28-204.1.1 permit holder failed to ensure that each construction ordemolition worker working/engaged at the site successfully completed the required training under bc 3321.1 and has an osha 30 card that was
Mar 24, 2020
Resolve - Class - 1
Failure to institute/maintain safety equipment measures or temporary construction: no guardrails @the time of inspection i observed there was no guardrails inplace @the 1st sty lvl exp3 exterior while this area
Sep 30, 2019 · Penalty $5,000
Resolve - Class - 1
Bc3309.14 failure to protect or adequately protect adjoing properties during construction or demolition. operation @the time of my inspection of a(15) sty alt bulding i observed a supported scaffold @exp 3 with
Sep 30, 2019 · Penalty $2,500
Resolve - Class - 1
28-418.1.1 work w/o license- gc @the time of inspection of a 5 sty altunoccupied bldg i observed the gc red leaf capital llc license have expired as of 9/3/2019. i also observed that the jobsite's daily log
Sep 30, 2019 · Penalty $2,500
Resolve - Class - 1
Failure to install/provide sws according to code @the time of my inspection, i observed a(fire) escape @the 2nd sty lvl exp1, open & accessible to any persons in the area. installed over the public walkay. the
Sep 30, 2019 · Penalty $10,000
Resolve - Class - 1
Failure to maintain adequate house keeping per section requirment.@thetime of my inspection i observed the housekeeping throughout the jobsite not being, adequately maintained. particullarly the 1st & cellar
Sep 30, 2019 · Penalty $2,500
Resolve
Show 20 more ↓
- Class - 2
Bc3307.6.5.10 failure to provide preshift inspection log for sidewalkshed. at the time of inspection on an active jobsite, i observed sidewalk shed was erected at exp1, when i ask the contracotr for the inspec
Jul 10, 2019 · Penalty $625
Resolve - Class - 2
Failure to maintain adequate housekeeping per section requirement. at the time of inspeciton on an active jobsite currently at roof level, iobserved inadequate housekeeping consisting of garbage bags, plywood
Jul 10, 2019 · Penalty $625
Resolve - Class - 2
Bc3314.4.3.5 failure to provide preshif inspection log for supportedscaffold. at the time of inspection on an active jobsite, i observed supported scaffold was erected at exp3 when i asked the contractor for
Jul 10, 2019 · Penalty $625
Resolve - Class - 2
Failure to provide construciton documents at jobsite at time of inspeciton. at time of inspection on an active jobsite i observed scaffold erected at exp3 on 2nd fl supporitng 3rd floor. when asked for design
Jul 10, 2019 · Penalty $625
Resolve - Class - 2
Stiar and/or floor identification signs missing and/or defective. at the time of inspection of a 5th story building currently at roof levelwith construction operaiton in progress, i observed at various floors
Jul 10, 2019 · Penalty $312
Resolve - Class - 2
Failure to maintain housekeeping (at cellar and 1&3 stories) adequate as per section requirement. at the time of inspection i observed construction materials wood, debris and metal beams at cellar and 1 and 3
Feb 20, 2019 · Penalty $625
Resolve - Class - 1
Failure to produce the daily log for inspection.at the time of inspection the permit holder failed to produce for inspection the daily log that is required by bc3321.2 item 3. remedy: maintain and produce
Feb 15, 2019
Resolve - Class - 1
Failure to comply w/the commissioner's order contained in nov#35153906l issued on 04/17/15 and to file a certificate of correction pursuant to 28-201.1, 28-204.4 and 1rcny102-01. rmdy: comply w/commissioner's o
Oct 14, 2015 · Penalty $6,000
Resolve - Class - 1
Failure to comply w/the comm's order contained in nov #35153906l issued on 4/17/15 & to file a c of c pursuant to 28-201.1,28-204.4 & 1rcny 102-01. left-east store work w/o permit. remedy: comply w/comm's order
Aug 25, 2015 · Penalty $2,400
Resolve - Class - 2
Failure to comply w/the comm's order contained in nov #35153905j issued on 4/17/15 & to file a c of c pursuant to 28-201.1,28-204.4 & 1rcny 102-01. remedy: comply w/comm's order &/or file a c of c.
Aug 25, 2015 · Penalty $800
Resolve - Class - 1
Failure to comply w/commissioner's order contained in nov #35153906l issued on 04/17/15 and to file a certificate of correction pursuant to28-201.1, 28-204.4 and 1rcny 102-01. for work w/o a permit at 1st flr
Jul 14, 2015 · Penalty $2,400
Resolve - Class - 2
Failure to comply w/the comm's order contained in nov #35153905j issued on 4/17/15 & to file a c of c pursuant to 28-201.1,28-204.4 & 1rcny 102-01. for occupancy contrary at 1st fl. remedy: comply w/comm's orde
Jul 14, 2015 · Penalty $800
Resolve - Class - 1
Failure to ground electrical systems.bsmt service ground conductor:no water main ground provided. "please note" the ground conductor is not attached to the waer pipe.rmdy: provide grounding.
Jun 16, 2015 · Penalty $4,800
Resolve - Class - 2
Electrical work w/o a permit. "temporary wiring" ground floor store front: branch circuit wiring, receptacles outlets,lighting fixtures. "not on file" m368799 does not cover the above work!!!rmdy:obtain perm
Jun 16, 2015 · Penalty $400
Resolve - Class - 1
Unapproved/unsafe/unsuitable electrical equipment,apparatus materials,devices,appliances on wiring in use. the entire ground floor and bsmt service switches are not grouped, temporary wiring (gfci) provided,def
Jun 16, 2015 · Penalty $1,600
Resolve - Class - 1
Occupancy contrary to that allowed by the c of o or bldg dept record. dob records alt 1921-11p indicates premises to be occupied by store & offices. illegal occupancy noted: at 1st fl left office converted to
Apr 17, 2015 · Penalty $2,400
Resolve - Class - 1
Work w/o a permit. work noted: at 1st fl left installed water & waste lines for a 3pc bathroom(toilet,sink,shower)& residential sink at kitchen. installed gas line for gas stove at kitchen. created full height
Apr 17, 2015 · Penalty $1,600
Resolve - Non-hazardous
Work w/o permit @ 1st flr east side built new partitions to form roomsinstalled new drop ceilings w/vents thru out new electric & plumbing stop all work.remedy:file obtain const electrical & plumbing permits
Aug 25, 2006 · Penalty $500
Resolve - Non-hazardous
Work w/o a permit - alteration on 3rd floor building partitions to fo-rm a bathroom w/o permit also 4th floor - typical stop all work reme-dy - obtain permit if feasible.
Jun 28, 1993 · Penalty $175
Resolve - Non-hazardous
Work w/o a permit - installing plumbing - water line, waste lines for shower, sink, water heater w/o permit 3rd & 4th floor remedy - stop all work obtain permit if feasible.
Jun 28, 1993 · Penalty $175
Resolve
Complaints
- Unsanitary condition
Pests
Aug 13, 2018 · Apt 12
Close - Unsanitary condition
Mold
Jun 11, 2015 · Apt 1FRONT
Close
Sales history
No recorded sales in our data
Building details
- Building type
- Mixed residential and retail building (S4)
- Year built
- 1860
- Floors
- 5
- Residential units
- 4
- Building area
- 9,499 ft²
- Lot area
- 2,300 ft²
- Zoning
- C6-4A
- Community board
- 105
- Council district
- 3
- Block / lot
- 822 / 66
- Assessed value
- $1,595,250
- Landmark / historic district
- Ladies' Mile Historic District
HPD registration #145050, last renewed Sep 10, 2025.
Questions about 46 West 21 Street
Who owns 46 West 21 Street?
The owner of record in NYC Department of City Planning PLUTO data is Redleaf Capital LLC.
Does 46 West 21 Street have violations?
Yes. NYC HPD has recorded 1 housing violations at this property.
Is 46 West 21 Street rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 46 West 21 Street built?
City records list 1860 as the year it was built.
How many apartments are in 46 West 21 Street?
It has 4 residential units and 5 units in total.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.