318 West 39 Street
Manhattan, NY 10018BBL 1-00762-0050Map
Owner of record: Quadri-Planetary Associates,
318 West 39 Street is an office building built in 1915 in Manhattan, 10018. The owner of record is Quadri-Planetary Associates,. HPD has no housing violations on record for this property.
- HPD violations
- 0
- DOB violations
- 135
- ECB violations
- 64
- HPD complaints
- 0
What to know
No open immediately-hazardous violations among recent records.
HPD has not cited this building.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 0
No HPD violations on record
DOB building violations · 135
- High pressure boiler boiler required
Violation issued-failure to file 2021 internal hgh pressure inspection
Jun 30, 2023
Dob violation - active - High pressure boiler boiler required
Violation issued-failure to file 2021 internal hgh pressure inspection
Jun 30, 2023
Dob violation - active - High pressure boiler boiler required
Violation issued-failure to file 2021 external hgh pressure inspection
Jun 30, 2023
Dob violation - active - High pressure boiler boiler required
Violation issued-failure to file 2020 internal hgh pressure inspection
Jun 30, 2023
Dob violation - active - High pressure boiler boiler required
Violation issued-failure to file 2020 internal hgh pressure inspection
Jun 30, 2023
Dob violation - active - High pressure boiler boiler required
Violation issued-failure to file 2020 external hgh pressure inspection
Jun 30, 2023
Dob violation - active - High pressure boiler boiler required
Violation issued-failure to file 2020 external hgh pressure inspection
Jun 30, 2023
Dob violation - active - High pressure boiler boiler required
Violation issued-failure to file 2019 external hgh pressure inspection
Jun 20, 2023
Dob violation - active - High pressure boiler boiler required
Violation issued-failure to file 2018 external hgh pressure inspection
Jun 20, 2023
Dob violation - active - High pressure boiler boiler required
Violation issued-failure to file 2018 internal hgh pressure inspection
Jun 20, 2023
Dob violation - active
Show 40 more ↓
- High pressure boiler boiler required
Violation issued-failure to file 2018 internal hgh pressure inspection
Jun 20, 2023
Dob violation - active - High pressure boiler boiler required
Violation issued-failure to file 2018 internal hgh pressure inspection
Jun 20, 2023
Dob violation - active - High pressure boiler boiler required
Violation issued-failure to file 2018 external hgh pressure inspection
Jun 20, 2023
Dob violation - active - High pressure boiler boiler required
Violation issued-failure to file 2019 external hgh pressure inspection
Jun 20, 2023
Dob violation - active - High pressure boiler boiler required
Violation issued-failure to file 2019 external hgh pressure inspection
Jun 20, 2023
Dob violation - active - High pressure boiler boiler required
Violation issued-failure to file 2019 internal hgh pressure inspection
Jun 20, 2023
Dob violation - active - High pressure boiler boiler required
Violation issued-failure to file 2019 internal hgh pressure inspection
Jun 20, 2023
Dob violation - active - High pressure boiler boiler required
Violation issued-failure to file 2019 internal hgh pressure inspection
Jun 20, 2023
Dob violation - active - High pressure boiler boiler required
Violation issued-failure to file 2022 external high pressure inspection
Apr 25, 2023
Dob violation - active - High pressure boiler boiler required
Violation issued-failure to file 2022 internal high pressure inspection
Apr 25, 2023
Dob violation - active - High pressure boiler boiler required
Violation issued-failure to file 2022 internal high pressure inspection
Apr 25, 2023
Dob violation - active - Elevator elevatorrequired
E-elevator elevatorrequired
Feb 24, 2021
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Feb 24, 2021
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Feb 24, 2021
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Feb 24, 2021
Dob violation - resolved - High pressure boiler boiler required
Violation issued - failure to file 2017 internal high pressure boiler inspection
Mar 16, 2020
Dob violation - dismissed - High pressure boiler boiler required
Violation issued - failure to file 2017 internal high pressure boiler inspection
Mar 16, 2020
Dob violation - dismissed - High pressure boiler boiler required
Violation issued - failure to file 2017 internal high pressure boiler inspection
Mar 16, 2020
Dob violation - dismissed - High pressure boiler boiler required
Violation issued - failure to file 2017 external high pressure boiler inspection
Mar 16, 2020
Dob violation - dismissed - High pressure boiler boiler required
Violation issued - failure to file 2017 external high pressure boiler inspection
Mar 16, 2020
Dob violation - dismissed - High pressure boiler boiler required
Violation issued - failure to file 2017 external high pressure boiler inspection
Mar 16, 2020
Dob violation - dismissed - Sprinkler none
Failed to file final sprinkler report by july 1, 2019
Nov 12, 2019
Dob violation - active - Elevator elevatorrequired
E-elevator elevatorrequired
Feb 1, 2017
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Feb 1, 2017
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Feb 1, 2017
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Feb 1, 2017
Dob violation - resolved - Elevator annual inspection / test elevatorrequired
Violation issued to elevator-failure to file category 1 2014 inspection/test
Jun 10, 2015
Dob violation - dismissed - Elevator annual inspection / test elevatorrequired
Violation issued to elevator-failure to file category 1 2014 inspection/test
Jun 10, 2015
Dob violation - dismissed - High pressure boiler boiler required
Violation issued for failure to file 2013 annual high pressure boiler inspection
Mar 3, 2015
Dob violation - dismissed - High pressure boiler boiler required
Violation issued for failure to file 2013 annual high pressure boiler inspection
Mar 3, 2015
Dob violation - dismissed - High pressure boiler boiler required
Violation issued for failure to file 2013 annual high pressure boiler inspection
Mar 3, 2015
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
May 23, 2014
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
May 23, 2014
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Sep 6, 2013
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Sep 6, 2013
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Sep 6, 2013
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jun 5, 2012
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jun 5, 2012
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jun 5, 2012
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jun 5, 2012
Dob violation - resolved
ECB violations · 64
- Class - 2
A. c. 27-929.1, failure to complete the installation of a full system of automatic sprinklers and file a final sprinkler report prepared by a registered design professional in an office building 100 feet or mor
Jun 17, 2024 · Penalty $3,125
Active - Class - 2
27-929.1 failure to complete installation of full system of automatic sprinklers & file final sprinkler report prepared by registered designprofessional in office bldg 100 ft or more in height in existence on
Feb 28, 2023 · Penalty $3,125
Active - Class - 2
27-929.1 failure to complete the installation of a full system of automatic sprinklers and file a final sprinkler report prepared by a registered design professional in an office building 100 feet or more in he
Mar 30, 2021 · Penalty $3,125
Active - Class - 2
Sec. 27-929.1 failure to complete the installation of a full system ofautomatic sprinklers & file a final sprinkler report prepared by a registered design professional in an office bldg 100 feet or more in heig
Sep 29, 2020 · Penalty $1,280
Active - Class - 2
59v15,68m7,68m7,60q7. no tag stating date of annual brake maintenancethere is no maintenance in machine room, no sticker on main line stat ing maintenance company information, covers for machine room lighting
Jul 13, 2017 · Penalty $250
Resolve - Class - 2
Failure to file annual certification that cooling tower 1000004349 hasbeen inspected,tested,and disinfected,and that a maintenance plan has been developed and implemented,by november 1,2016.rem:file annual cert
Jun 20, 2017 · Penalty $1,000
Resolve - Class - 2
03l10 - exit cover is wrong size replace & test.
Sep 14, 2013
Resolve - Class - 2
56y02 42g07 39q03 67b01 77x10 k3 40m07 k3. 56-clean oil from bed plate. 42-provide proper fuses for controler. 39-install guard for toc lite. 67-adjust volume on emergency phone. 77-under car lite inoperative.
Jul 20, 2011
Resolve - Class - 2
69m07 56y10 69m-provide code data plate 56y-repair oil leak
Jan 26, 2011
Resolve - Class - 2
69m07 56y10 69m-provide code data plate 56y10-repair oil leak
Jan 26, 2011
Resolve
Show 40 more ↓
- Class - 1
Failure to safeguard all persons & property affected by construction operations.noted:observed contractor ross window corp working on the 8th flr along west 39st (exposure#1)replacing windows.when shards of gla
Oct 6, 2010 · Penalty $2,400
Resolve - Class - 2
Failure to maintain adequate housekeeping per section requirements noted:upon insp observed construction & household debris @ adjacent bldg being thrown out of bldg windows on top of shed.rem:maintain adequate
Oct 6, 2010
Resolve - Class - 2
71x10.71q3.77x10.67b1.17h11.40r9 39 car top light 77 under car light 69 adjust volume of emerg. ph. 17 replace lobby door gibs 40 the machine rm is not a locker and storage room for other trades working in the
Apr 21, 2009
Resolve - Class - 1
Unlawfully continueed work while on notice of a stop work order. noted: continued work on outrigger suspended scaffolds while notice stop work order #919. remedy: comply w/stop work order. make site safe.
Mar 25, 2009
Resolve - Class - 1
Work w/o permit. upon physical inspection found sprinkler heads being violated/removed on 5fl w/o permit. remedy:obtain permit or restore premises to prior legal condition.
Jan 26, 2009 · Penalty $1,600
Resolve - Class - 2
Failure to file an amended 6th round report acceptable to this department indicating correction of unsafe conditions described in initial local law 11/98 report. remedy: file an amended report following remedia
Nov 7, 2008 · Penalty $800
Resolve - Class - 2
Failure to provide approved/accepted plans at job site at time of inspection. noted: no drawing for outrigger beams on exposure 3. remedy: provide plans.
Oct 16, 2008
Resolve - Class - 1
No record of daily inspection of suspended scaffold performed by authorized person at site. noted: no daily insp log book on site. remedy: maintain daily inspection records on site.
Oct 16, 2008
Resolve - Class - 1
Licensed rigger failed to ensure scaffold worker met minimum requirements. noted: workers on suspended scaffold. w/o certificate of fitness.remedy: comply with code.
Oct 16, 2008
Resolve - Class - 1
Operations of hoisting equipment in an unsafe manner. using pulley system to lower debris from roof level piece of 2'x 2' sheet metal becameloose fell onto shed then bounced off into street hitting vehicle
Aug 1, 2008
Resolve - Class - 1
Erected maintained a scaffold over 40ft w/o permit. remedy: obtain a permit.
Jul 9, 2008 · Penalty $1,200
Resolve - Class - 2
Failed to notify the department/obtain prior to the use/installation of 'c' hooks and outrigger beams in connection with suspended scaffold.2 violations no 'c' hook/no outrigger beam notification, 2 types of sc
Jul 9, 2008 · Penalty $800
Resolve - Class - 2
Work does not conform to approved construction documents scaffold is not set-up according to approved cd-s. remedy: amend cd-s/re-rig.
Jul 9, 2008 · Penalty $500
Resolve - Non-hazardous
41g07.02x10.01b10.06b01.84r09.84m09. 41 provide proper fuses in controller 02 emg.phone inoperative 01 stop button doesn't ring alarm bell 06 wide gap on car door with gate sw. made up adjust gate sw. 84 illega
Jun 16, 2008 · Penalty $350
Resolve - Non-hazardous
Failure to file an amended 6th round report acceptable to this dept indicating correction of unsafe conditions described in initial local law 11/98 report. remedy: file an amended report following remedial
Mar 28, 2008 · Penalty $700
Resolve - Non-hazardous
18a,50a,b,c.fulton vt boiler,10hp,nb65022,gas,1992.18a-scale accumualation at handhole opening remove scale clean & regasket handholes.50a-no guard over air compressor motor drive shaft in boiler room.install
Dec 29, 2007 · Penalty $180
Resolve - Non-hazardous
50a,b.fulton vt boiler,15hp,nb 58421,gas 1989.50a-inadequate structuresupport of the flue pipe system.install a heavy duty support.50b-missing dial glass on steam pressure gauge.
Dec 29, 2007
Resolve - Non-hazardous
50a,b. fulton vt boiler,15hp,nb58421,gas,1989.50a-inadequate structuresupport of the boiler loaded flue pipe system.install a heavy duty hanger attached to the boiler room ceiling.50b-boiler room dirty & conges
Dec 29, 2007
Resolve - Non-hazardous
18a,b,50a,b,c,d.fulton vt boiler,15hp,nb 33767,gas 1991.18a,b-corrosion,scale accumulation & evidence of leakage at upper & lower hand holes.de-scale,clean & re-gasket hand hole openings.50a-blowdown valve leak
Dec 29, 2007 · Penalty $180
Resolve - Non-hazardous
83x10. repair elevator & return to service so proper inspection can be made
Jun 1, 2006
Resolve - Hazardous
51,50,48a,48b/1991 fulton nb 33767-fire hazardous condition/51-bottom left handhole area caseing has holes all around, exposing products of combustion to all people in the area/50-glass guards missing
May 23, 2006 · Penalty $500
Resolve - Non-hazardous
34b
May 23, 2006 · Penalty $2,500
Resolve - Non-hazardous
1989 fulton nail bd.# 58421
May 23, 2006 · Penalty $5,000
Resolve - Non-hazardous
50a/50b 50c/50d 44c fulton v.t. boiler, 10hp, nb65379, gas 1992 50a nostructural supports on the flue pipe system. install heavy duty hangerto boiler room ceiling. 50b improper arrangement of blowdown valves.
Jul 19, 2004
Resolve - Non-hazardous
36/50a 50b/50c 50d/50e fulton v.t. boiler, nb 58421, 15hp, gas, 1989 50a) no hanger on the flue pipe. 50b) no discharge pipe on the safety valve. 50c) no drain line on the gage cease assembly. 50d) no secondary
Jul 19, 2004 · Penalty $180
Resolve - Non-hazardous
50a/50b fulton v.t. boiler, 15hp, nb 67688, gas, 1993 50a improper arrangement of blowdown valves on the boiler. install a secondary screw-type gate valve at the outlet end of the blowdown line. 50b air vent
Jul 19, 2004
Resolve - Non-hazardous
50a/50b fulton v.t. boiler 15hp, nb 76526, gas 1996 50a flue pipe supported by loose band iron. replace with a heavy-duty hanger to the boiler room ceiling. 50b) improper arrangement of the blowdown valves.
Jul 19, 2004
Resolve - Non-hazardous
50a/50b 50c fulton v.t. boiler, 15hp nb 33767, gas, 1991 50a) no structural supports on the flue pipe system. install a heavy duty hanger to the boiler room ceiling. 50b) missing guard for the compressor fly
Jul 19, 2004 · Penalty $180
Resolve - Non-hazardous
48ab/50a 50b/50c fulton v.t. boiler, 10hp, nb 65022, gas 1992 50a no structural supports on the flue pipe system. install a heavy duty hanger to the boiler room ceiling. 50b flue pipe barometric damper resting
Jul 19, 2004
Resolve - Non-hazardous
Failure to file an amended round five report acceptable to this depar tment pursuant to rule r.c.n.y. 32-03b(5), indicating correction of hazardous conditions described in initial ll11/98 report. remedy: file a
Mar 14, 2003 · Penalty $1,000
Resolve - Hazardous
Failure to file an amended round five report acceptable to this department pursuant to rule r.c.n.y. 32-03b(5), indicating correction of hazardous conditions described in initial ll11/98 report. remedy : file a
Jan 13, 2003 · Penalty $400
Resolve - Hazardous
Failure to file an amended round five report acceptable to this department pursuant to rule r.c.n.y. 32-03b(5), indicating correction of hazardous conditions described in initiall ll11/98 report. remedy: file a
Nov 8, 2002 · Penalty $400
Resolve - Hazardous
Failure to maintain exterior of building. damaged terra cotta tile on the north elev. 11th floor. brick buiging on the east palapetwall. severe clack in brick work on the south ele. remedy: make area safe. obta
Apr 18, 2002 · Penalty $800
Resolve - Non-hazardous
40o02,47oo2,50o02,57o02,74o02,46o02,59o02,46t13,37t07,18q03 - 74-o-02 clean car tcp, 46-t-13 reshackle heist cables, 18-o-03 provide cover for 8 fl interlock, 87-t-07 provide proper city i.d. tags (1f2828)
Feb 4, 2002
Resolve - Non-hazardous
57o02/ 73o02/ 30o02/ 74i04/ 74i04 lobby wall above hall buttons huge hole repair & patch hole
Nov 14, 2001
Resolve - Non-hazardous
46h13-last date on top of car is 1989 overhead drum machines have to be reshacled every year on top of car drom counter eight was done in 1998.
Oct 10, 2001
Resolve - Hazardous
Cease use 05n09-22d06-57p07-73o02 05-gate switch inoperable 22-secure 57-provide 73-clean entire device
Sep 7, 2001 · Penalty $500
Resolve - Hazardous
Operator was operating device with jump gate switch cease use call dept of building before returning back to service replace missing covers
Aug 1, 2001 · Penalty $2,500
Resolve - Hazardous
Failure to maintain building(hazardous) noted: all fire doors in building are not up to code. most missing panic bars ab=nd self closing me chanisms. most have regular locks which do not belong. also fire balca
Nov 10, 1999 · Penalty $800
Resolve - Non-hazardous
18a,18b,49. 18a-handholes corroded. 18b-handholes leaking. 49-low water safety relay switch not connected.
Oct 21, 1998 · Penalty $180
Resolve
Complaints
No HPD complaints in our records
Sales history
No recorded sales in our data
Building details
- Building type
- Office building (O6)
- Year built
- 1915
- Floors
- 12
- Residential units
- —
- Building area
- 156,508 ft²
- Lot area
- 12,343 ft²
- Zoning
- C6-4M
- Community board
- 104
- Council district
- 3
- Block / lot
- 762 / 50
- Assessed value
- $11,701,800
- Landmark / historic district
- No
Questions about 318 West 39 Street
Who owns 318 West 39 Street?
The owner of record in NYC Department of City Planning PLUTO data is Quadri-Planetary Associates,.
Does 318 West 39 Street have violations?
NYC HPD has no housing violations on record for this property.
Is 318 West 39 Street rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 318 West 39 Street built?
City records list 1915 as the year it was built.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.