roofy

536 West 26 Street

Manhattan, NY 10001BBL 1-00697-0056Map

Owner of record: Jmcr W 26th NY, LLC

536 West 26 Street is an office building built in 2016 in Manhattan, 10001. The owner of record is Jmcr W 26th NY, LLC. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
33
ECB violations
29
HPD complaints
1

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 33

  • Low pressure boiler boiler required

    Violation issued-failure to file 2022 external low pressure inspection

    Apr 25, 2023

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued-failure to file 2022 external low pressure inspection

    Apr 25, 2023

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued-failure to file 2022 external low pressure inspection

    Apr 25, 2023

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued-failure to file 2022 external low pressure inspection

    Apr 25, 2023

    Dob violation - dismissed
  • Elevator annual inspection / test elevatorrequired

    Violation issued to elevator-failure to file category 1 2016 inspection/test

    Sep 15, 2017

    Dob violation - dismissed
  • Elevator annual inspection / test elevatorrequired

    Violation issued to elevator-failure to file category 1 2016 inspection/test

    Sep 15, 2017

    Dob violation - dismissed
  • Elevator annual inspection / test elevatorrequired

    Violation issued to elevator-failure to file category 1 2016 inspection/test

    Sep 15, 2017

    Dob violation - dismissed
  • Elevator annual inspection / test elevatorrequired

    Violation issued to elevator-failure to file category 1 2016 inspection/test

    Sep 15, 2017

    Dob violation - dismissed
  • Elevator annual inspection / test elevatorrequired

    Violation issued to elevator-failure to file category 1 2016 inspection/test

    Sep 15, 2017

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jul 12, 2017

    Dob violation - dismissed
Show 23 more ↓
  • Construction other optional

    C-construction other optional

    May 7, 2017

    Vp*-violation unserved ecb- dismissed
  • Failure to benchmark none

    Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4

    May 2, 2017

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jan 25, 2017

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jan 25, 2017

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jan 25, 2017

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jan 11, 2017

    Dob violation - dismissed
  • Construction other optional

    C-construction other optional

    Nov 1, 2016

    Vp*-violation unserved ecb- dismissed
  • Construction other optional

    C-construction other optional

    Nov 1, 2016

    Vp*-violation unserved ecb- dismissed
  • Construction other optional

    C-construction other optional

    Nov 1, 2016

    Vp*-violation unserved ecb- dismissed
  • Construction other optional

    C-construction other optional

    Oct 11, 2016

    Vp*-violation unserved ecb- dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jul 27, 2016

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Mar 9, 2016

    Dob violation - dismissed
  • Construction other optional

    Boro-comm

    Dec 29, 2015

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Nov 18, 2015

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Oct 21, 2015

    Dob violation - dismissed
  • Elevator annual inspection / test elevatorrequired

    Violation issued to elevator-failure to file category 1 2014 inspection/test

    Jun 10, 2015

    Dob violation - dismissed
  • Elevator affirmation of correction elevatorrequired

    Vio issued to elevator - fail to correct defects on 2012 cat 1 insp/tst

    May 30, 2014

    Dob violation - dismissed
  • Elevator annual inspection / test elevatorrequired

    Violation issued to elevator-failure to file category 1 2010 inspection/test

    Dec 13, 2011

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jul 27, 2011

    Dob violation - dismissed
  • Elevator annual inspection / test elevatorrequired

    Vcat1-elevator annual inspection / test elevatorrequired

    Oct 8, 2010

    Dob violation - dismissed
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Apr 20, 2010

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Nov 28, 2007

    Dob violation - resolved
  • Electric signs none

    Es-electric signs none

    Jan 24, 1991

    Dob violation - dismissed

ECB violations · 29

  • Class - 2

    No controlled access zone. at time of inspection of a 9 sty bldg currrently topped & tco'd, i observed loose material & evidence of roof work(pavers)in process of being installed at exp#3 edge on the roof. belo

    May 7, 2018 · Penalty $5,030

    Resolve
  • Class - 2

    Project information panel/sidewalk shed parapet panel/construction sign not provided or not incompliance w/section. noted: at time of inspection there is no sign on sidewalk shed parapet panel at all.

    May 10, 2017 · Penalty $400

    Resolve
  • Class - 2

    Failure to provide approved/accepted plan construction documents at site. noted: pswo suspended scaffold at time of inspection plans on site were not accepted the plans are blurry & can not read the details and

    May 10, 2017

    Resolve
  • Class - 2

    Failure to provide approved/accepted plan construction documents at site. noted: at time of inspection no complete set of plan could be provide for sidewalk shed on site. plans were missing page 1 of 3.

    May 10, 2017 · Penalty $250

    Resolve
  • Class - 1

    Work does not conform to approved construction documents &/or approvedamendment. note: at the time of my inspection of a 9 sty bldg at bulkhead level construction work in progress. i observed suspended scaffold

    Apr 18, 2017 · Penalty $1,000

    Resolve
  • Class - 1

    Failed to perform safe/proper inspection of suspended scaffold-installation inspection. note: at the time of my inspection of a 9 sty bldg at bulkhead level,construction work in progress. i observed suspended

    Apr 18, 2017 · Penalty $10,000

    Resolve
  • Class - 2

    Failure to institute & maintain safety equipment measures or temporaryconstruction. note: at the time of inspection of a 9 sty new bldg at roof level,construction work in progress. i observed window installatio

    Feb 7, 2017 · Penalty $5,030

    Resolve
  • Class - 1

    Sec. 3301.1.3 manufacturer specifications. note: at the time of my inspection of a 9 sty bldg at roof level,construction work in progress. i observed an reusable concrete anchor system being use on 8th fl level

    Feb 7, 2017 · Penalty $1,630

    Resolve
  • Class - 2

    Collection & containment. note: at the time of my inspection of a 9 sty bldg at 7 fl level,i observed concrete washout being perform in a metal container upon request for designed & manufactured specification

    Nov 1, 2016 · Penalty $1,200

    Resolve
  • Class - 1

    Failure to safeguard public & property affected by construction operations. note: at the time of my inspection,responding to complaint #1436534 where ssm reported worker was moving horizontal netting up to next

    Nov 1, 2016 · Penalty $10,000

    Resolve
Show 19 more ↓
  • Class - 1

    Sec. 3301.1.1 responsibility for safety. note: at the time of my inspection of a 9 sty bldg at 7th fl,construction work in progress. i observed storage & work zone area at exp#1 grade level was not provided wit

    Nov 1, 2016 · Penalty $1,600

    Resolve
  • Class - 1

    Sec. 3301.6 design,sizes & capacity of materials,structures,temporary construction & equipment. note: at the time of my inspection of a 9 sty bldg at 7 fl level,construction work in progress. i observed a tempo

    Nov 1, 2016 · Penalty $1,600

    Resolve
  • Class - 2

    3307.2.6 requirements for sidewalk,temporary walkways and pathways.at the time o inspection noted that there were blind corners in pedestrian walkway under sidewalk bridge that require mirrors were not installe

    Oct 11, 2016

    Resolve
  • Class - 1

    3301.2 safety measures and safeguards.at the time o insopection noted workers using a harness hook in tandam with a c hook attached to a retractor and hooked to a concrete embeded strap.the proper use of the

    Oct 11, 2016 · Penalty $1,630

    Resolve
  • Class - 2

    Failure to post permit for work at premises.at time of inspection no nb permit posted on job site fence as required by code at expo #1.remedy comply with code post permit on job site fence.

    Oct 11, 2016

    Resolve
  • Class - 2

    Job site fence does not meet code specifications.at time of inspectionnoted that job site fence @ expo#1 storage used at jersey barrier did not have as per code debris hunter green netting on it to provide from

    Oct 11, 2016 · Penalty $400

    Resolve
  • Class - 2

    Project information panel.at time of inspection job site did not have a project information panel on the jobsite fence as required by code.remedy:comply with code provide project information panel

    Oct 11, 2016

    Resolve
  • Class - 2

    28-207.2.2 failure to comply w/ an order to stop work by the dept.the respondent failed to comply w/ an order to stop work by dob.there is apartial swo in effect for all work w/in 15ft of exp3 & @ the time of i

    Jun 2, 2016 · Penalty $400

    Resolve
  • Class - 1

    Failure to maintain adequate housekeeping per section. as noted: at time of inspeciton at active jobsite observed at grade level exp1.excessive debris, equipment, materials on site site blocking egress and wa

    May 25, 2016 · Penalty $2,400

    Resolve
  • Class - 1

    Failure to notify the dept of an accident at the consrtruction site. the respondent failed to notify the dob of the damage to the adjoining bldg at exp#3. the bldg sustained cracks during caisson drilling opera

    Apr 28, 2016 · Penalty $2,530

    Resolve
  • Class - 1

    Failure to safeguard all persons and property affected by constructionoperations.pile installation (drilling) at the jobsite caused settlement and cracking in the adjoining building at exposure 3 stop work orde

    Dec 18, 2015 · Penalty $2,430

    Resolve
  • Class - 2

    Failure to safeguard all persons & property affected by construction operations. it was reported to the dob that there was movement in the adjoining bldg at exp33. site condition indicate that pile drilling was

    Nov 25, 2015 · Penalty $1,200

    Resolve
  • Class - 1

    Bc 3301.1.2 failure to comply w/nyc fire code @time of insp demo in progress under 122041860 observed storage of oxygen/acetylene on site & permit expired 5/19/15 stop all use oxygen/acetylene @site (cutting/bu

    Jun 17, 2015 · Penalty $400

    Resolve
  • Class - 1

    Failure to safeguard all persons and property affected by demolition operations.at time of inspection observed demolition of 2 story build ing in progress. mechanical equipment being used along adjoining prope

    Jun 12, 2015 · Penalty $2,400

    Resolve
  • Class - 2

    Bc3307.7.1 no fence viewing panel provided as per code requirements. observed 8'high solid plywood,fence erected at exp1.no viewing panel in fence for its entire length.rmdy: provide viewing panel and comply

    May 16, 2015

    Resolve
  • Class - 2

    Project information panel not in compliance with section.observed: building demolition.propject information panel posted on parapet or sws. which should be posted on fence at a height of 4"above ground.rmdy:

    May 16, 2015

    Resolve
  • Class - 2

    Ac 28-104.7.1 respondent's plans fail to comply w/the 1968 bldg code (bc) respondent filed professionally certificed appl #120839450 for alteration type 1 appl to "obtain certificate of occupancy"for above pre

    Oct 10, 2013 · Penalty $800

    Resolve
  • Class - 2

    Failure to comply w/comm's order to correct the violating conditions and file a cofc w/dept of bldg for open ecb nov#34879966j.rem:comply w/comm's order and file a cofc

    Jun 23, 2011 · Penalty $800

    Resolve
  • Class - 1

    Occupancy contrary to that allowed by the cofo @ first flr bldg is currently occupied as "lehmann maupin & stephen haller, gallery contrary to c/o#15497 which states the bldg legal occupancy as garage on 1st fl

    Apr 29, 2011 · Penalty $1,200

    Resolve

Complaints

  • Heat/hot water

    Entire building

    Nov 22, 2023 · Apt BLDG

    Close

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Office building (O6)
Year built
2016
Floors
9
Residential units
—
Building area
144,079 ft²
Lot area
19,750 ft²
Zoning
M1-5
Community board
104
Council district
3
Block / lot
697 / 56
Assessed value
$49,351,950
Landmark / historic district
No

Questions about 536 West 26 Street

Who owns 536 West 26 Street?

The owner of record in NYC Department of City Planning PLUTO data is Jmcr W 26th NY, LLC.

Does 536 West 26 Street have violations?

NYC HPD has no housing violations on record for this property.

Is 536 West 26 Street rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 536 West 26 Street built?

City records list 2016 as the year it was built.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.