roofy

525 Avenue Of The Americas

Manhattan, NY 10011BBL 1-00609-0039Map

Owner of record: 525 6th Ave LLC

525 Avenue Of The Americas is an elevator apartment building built in 2024 in Manhattan, 10011. It has 60 residential units across 13 floors. The owner of record is 525 6th Ave LLC. HPD has recorded 8 housing violations here, most recently on November 22, 2024.

HPD violations
8
DOB violations
6
ECB violations
17
HPD complaints
9

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
Last violation Nov 22, 2024

Date of the most recent HPD inspection that found a problem.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 8

  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 22, 2024

    Closed — Violation closed
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Apr 1, 2024

    Closed — Violation closed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 15, 2023

    Closed — Violation closed
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Mar 15, 2023

    Closed — Violation closed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 2, 2022

    Closed — Violation closed
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Apr 1, 2021

    Closed — Violation dismissed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Oct 5, 2018

    Closed — Violation dismissed
  • B

    Properly repair the broken or defective intercom system in front of building

    Aug 18, 2015

    Closed — Violation dismissed

DOB building violations · 6

  • Construction other optional

    C-construction other optional

    May 16, 2002

    Vw*-violation - work w/o permit dismissed
  • Construction other optional

    C-construction other optional

    Mar 12, 2001

    Dob violation - dismissed
  • Construction other optional

    C-construction other optional

    Mar 10, 2000

    Dob violation - dismissed
  • Construction other optional

    C-construction other optional

    Mar 9, 2000

    Dob violation - dismissed
  • Electric signs none

    Es-electric signs none

    Mar 31, 1994

    Dob violation - dismissed
  • Electric signs none

    Es-electric signs none

    Mar 31, 1994

    Dob violation - dismissed

ECB violations · 17

  • Class - 2

    At time of inspection, observed yodock barriers with chain link fence on top not maintained in work / storage zone. the barriers were tilted over, creating hazardous conditions to the general public.stop all wo

    Feb 7, 2026 · Penalty $2,400

    Resolve
  • Class - 2

    Observed exp's 1&4 erected/installed non-illuminated business signs read 8 times "the village west" with decals with no permits or approvals from dob, remove unlawful signs; remove unlawful signs

    Jun 27, 2025 · Penalty $2,500

    Resolve
  • Class - 2

    Site plans; c-hook plans indicate u shape plywood over parapet coping. c-hook on site with 2x 8 lumber does not conform to plans.stop all use of susp. scaff- c-hook at exposure 2. conform site to plans. contact

    Apr 14, 2025

    Resolve
  • Class - 2

    Observe missing mirrors at exposure 1; pedestrian walkways, blind spots, and where construction condition creates a hazard to public safety. provide mirrors where pedestrian view is obstructed, where blind sp

    Apr 14, 2025

    Resolve
  • Class - 2

    Bc 3307.6.5.8 at time of inspection i observed sidewalk in place at exposure # 1 and 4 with supported scaffold on top of it , upon request for periodic inspection letter as require to verify safety inspection

    Feb 11, 2025 · Penalty $2,500

    Resolve
  • Class - 2

    Bc3320.1 response to an incident where 2 workers was injured during delivery operation and was taken to hospital, inspection reveals 8 bundles of metal stud that were on the a frame when pushing it from hoist

    Feb 11, 2025 · Penalty $2,500

    Resolve
  • Class - 2

    At the time of inspection, the supported scaffold at two locations on the first floor, exposure 2, was found to be non-compliant with building code 3314. it lacked guardrails, toe boards, proper planking, and s

    Oct 17, 2024 · Penalty $2,500

    Resolve
  • Class - 2

    Bc 3303.3 at time of inspection of a 13 stories new buildings at exterior finishing level approximately 10,184 sq feet, site was closed under padlock no construction activities , upon shouting and banging the g

    Aug 24, 2024 · Penalty $2,500

    Resolve
  • Class - 1

    At time of inspection observed completed demolition work of a 4-story building. upon researching dob records no notification was given to dob prior to the commencement of full demolition. gc did not notify the

    Oct 31, 2023 · Penalty $2,500

    Resolve
  • Class - 2

    Failure to maintain sidewalk shed clearance to avoid existing obstructions, not to exceed 18 inches (457 mm) along the curb, creating a hazardous of struck by trucks and traffic and in contrary with code 3307.6

    Jun 29, 2023 · Penalty $5,000

    Resolve
Show 7 more ↓
  • Class - 1

    Failure to designate a competent person for each job site. the construction superintendent must not use one competent person for more than one site at same time to ensure such competent person is always the des

    Jun 29, 2023

    Resolve
  • Class - 1

    Failure to designate a competent person for each job site. the construction superintendent must not use one competent person for more than one site at same time to ensure such competent person is always the des

    Jun 29, 2023

    Resolve
  • Class - 1

    Observed hose hooked to fire hydrant for water supply on job site without adequate measures as it was missing no return flow device / value, creating an immediate hazardous disturbing of utilities water contami

    Jun 29, 2023 · Penalty $2,500

    Resolve
  • Class - 3

    Work without permit.note at time of inspection no permit on file for sign.sign reads a + r gourmet market place(approx.20' long 2' high amouted on exterior wall illuminated)rem:obtain all required permits.

    May 12, 2020 · Penalty $500

    Resolve
  • Non-hazardous

    Work without a permit: expired permits noted: work permits for job in progress, permit#'s 100251674 and 101165276 posted have expired on 3/9/00. remedy:stop all work, renew permits make area safe.

    May 19, 2000

    Resolve
  • Non-hazardous

    Failure to provide approved plans at premises at time of inspection.noted:no approved plans available under permit#100251674 remedy:stop allwork make are safe.arrange for inspection with approved plans.

    Feb 16, 2000 · Penalty $130

    Resolve
  • Non-hazardous

    Occupancy contrary to that allowed by the bldg dept records or c of o 104544. noted: 4th fl occupied as a health club. 2nd & 5th fl occupied as comm offices w/o a valid c of o.

    Nov 28, 1997 · Penalty $800

    Resolve

Complaints

  • Heat/hot water

    Apartment only

    Dec 5, 2021 · Apt THIRDF

    Close
  • Heat/hot water

    Entire building

    Jun 18, 2018 · Apt 2

    Close
  • Heat/hot water

    Apartment only

    Aug 14, 2015 · Apt 3

    Close
  • General

    Bell/buzzer/intercom

    Aug 14, 2015 · Apt 3

    Close
  • Plumbing

    Water-leaks

    Feb 1, 2009 · Apt 4

    Close
  • General

    Stairs

    Feb 1, 2009 · Apt 4

    Close
  • Paint/plaster

    Wall

    Feb 1, 2009 · Apt 4

    Close
  • Plumbing

    Water supply

    Sep 26, 2008 · Apt 4

    Close
  • Heating

    Heat related

    Nov 19, 2007 · Apt 4

    Close

Sales history

DatePriceTypeUnits
May 27, 2026Non-market transferRentals - elevator apartments62

Building details

Building type
Elevator apartment building (D6)
Year built
2024
Floors
13
Residential units
60
Building area
123,697 ft²
Lot area
12,900 ft²
Zoning
—
Community board
102
Council district
3
Block / lot
609 / 39
Assessed value
$12,319,650
Landmark / historic district
No

HPD registration #142276, last renewed Oct 15, 2021.

Questions about 525 Avenue Of The Americas

Who owns 525 Avenue Of The Americas?

The owner of record in NYC Department of City Planning PLUTO data is 525 6th Ave LLC.

Does 525 Avenue Of The Americas have violations?

Yes. NYC HPD has recorded 8 housing violations at this property.

Is 525 Avenue Of The Americas rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 525 Avenue Of The Americas built?

City records list 2024 as the year it was built.

How many apartments are in 525 Avenue Of The Americas?

It has 60 residential units and 62 units in total.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.